Manett, Seastrunk & Buckner v. Terminal Building Corp.

39 S.W.2d 1, 120 Tex. 374, 77 A.L.R. 1122, 1931 Tex. LEXIS 173
CourtTexas Supreme Court
DecidedMay 16, 1931
DocketNo. 5717.
StatusPublished
Cited by12 cases

This text of 39 S.W.2d 1 (Manett, Seastrunk & Buckner v. Terminal Building Corp.) is published on Counsel Stack Legal Research, covering Texas Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Manett, Seastrunk & Buckner v. Terminal Building Corp., 39 S.W.2d 1, 120 Tex. 374, 77 A.L.R. 1122, 1931 Tex. LEXIS 173 (Tex. 1931).

Opinion

Mr. Commissioner LEDDY

delivered the opinion of the court.

Plaintiffs in error entered into a contract with the defendant in error to do all of the electrical work required under the plans and specifications-for what is known as the Terminal Building, in the city of Dallas, for the agreed sum of $78,654.50. It was stipulated that defendant in error was given the privilege under the contract of ordering extra work, or of making any changes in the original plans and specifications; with the provision that if the value of such work or alteration was not agreed upon, it should be determined in one or more of the following ways:

*376 “(a) By estimate and acceptance in a lump sum;

“(b) By unit prices named in the contract or subsequently agreed upon;

“(c) By cost and percentage or by cost and a fixed fee;

“(d) If none of the above methods is agreed upon, the contractor, provided he receives an order as above, shall proceed with the work, no appeal to arbitration being allowed from such order to proceed.

“In cases (c) and (d), the contractor shall keep and present in such form as the architect may direct, a correct amount of the net cost of labor and materials together with vouchers. In any case, the architect shall certify to the amount due the contractor. Pending final determination of value, payments on account of changes shall be made on the architect’s certificate.”

Plaintiffs in error began work under this contract in the fall of 1923 and continued working thereon until October, 1925. The 28th estimate furnished by them to the architect was presented on July 9, 1925. Under this estimate they claimed defendant in error was due them, after due allowance for all credits, the sum of $27,986.64. After filing this estimate, they continued working on the buildings until October 16, 1925, claiming that during this interval they did additional work of the approximate value of $28,000. On October 16, 1925, plaintiffs in error, after giving notice of their intention to do so, in accordance with the terms of the contract, abandoned work thereon because of failure of defendant in ■error to pay their estimate No. 28.

They instituted this suit to recover on a quantum meruit the value of the labor performed and material furnished in the installation of the ■electrical work on said Terminal Building, which they claimed amounted to the sum of $189,829.28, on which they admitted a credit for payments in the sum of $95,415.16, and judgment was sought for the remaining portion of the amount of $94,414.12.

Defendant in error contended upon the trial that it was not in default in refusing to pay plaintiff in error’s estimate No. 28, or to have the architect issue a certificate on such estimate for the reason that plaintiffs in error had failed and refused to submit, either to it or to the architect, the invoices showing the net cost price of labor and materials used for the extra work, and that by reason thereof there was no way for it or the architect to determine correctly the amount due plaintiffs in error under their estimate.

When the evidence was closed, both parties presented requests for peremptory instructions. Plaintiffs in error requested the submission of a number of special issues in line with the cause of action set up in their pleadings, such requests being conditioned upon the refusal of their summary instruction. The trial judge indicated to the parties that he was of the opinion that plaintiffs in error were not entitled to recover under a *377 quantum meruit, but that he thought on equitable grounds they should be permitted to recover the sum of $28,960.89, which it seems defendant in error admitted was due by them as the unpaid balance for the work done under the contract after allowing the amount it had been required to pay to complete the contract.

When the above suggestion was made by the court, defendant in error immediately filed a trial amendment, which, after reciting the views of the court as above expressed, alleged that “without prejudice otherwise to its insistence that a verdict should now be directed for it, this defendant admits that under the contract referred to in plaintiffs’ petition, if such contract had not been breached by plaintiffs, they would be entitled to recover the sum of $28,960.89. And this defendant concedes that the jury may be instructed to return a verdict for like amount with interest thereon only from this date, however, may be entered in favor of plaintiffs and against this defendant.”

Upon the filing of the above pleadings, the court overruled the motions for peremptory instructions requested by both parties, as well as all special issues requested by plaintiffs in error, granted the request contained in defendant in error’s trial amendment and instructed the jury to render a verdict in favor of plaintiffs in error for the sum stipulated. Judgment upon the verdict rendered in accordance with said instruction was duly entered.

The Court of Civil Appeals upon original hearing affirmed the judgment of the trial court. Later it granted plaintiffs in error’s motion for rehearing and reformed the judgment so as to eliminate the amount awarded plaintiffs in error, and rendered judgment that they take nothing on their claim against defendant in error. 23 S. W. (2d) 786.

The acount of the Court of Civil Appeals reversing the judgment for the amount admitted to be due under defendant in error’s trial amendment was undoubtedly proper. Plaintiffs in error were entitled to a trial upon the cause of action set up in their pleadings. They could not be compelled, over their protest, to have their rights adjudicated upon a theory pleaded by defendant in error in its trial amendment. The only legal effect that could be given defendant in error’s trial amendment was that of an offer in the nature of a compromise. If it had been acceptable to plaintiffs in error the court’s action in directing verdict for that sum would have been entirely proper. Defendant in error, however, had no legal right to force upon plaintiffs in error, over their protest, the acceptance of the compromise proposal.

This brings us to a consideration of the correctness of the action of the Court of Civil Appeals in rendering judgment against plaintiffs in error. In order to decide this question, we must determine whether plaintiffs in error under their pleadings and evidence presented any issues *378 which they were entitled to have submitted for the determination of the jury.

Plaintiffs in error alleged in their petition that there was collusion between the architect and the Terminal Company to defraud them by arbitrarily reducing the cost of the buildings and that plaintiffs in error were influenced thereby in their decision to stop work under their contract.

It was further alleged by them that defendant in error waived all of its rights under the contract and was estopped to rely upon any provision thereof because in designating L. R. Whitson as architect it breached said contract in view of the provision contained therein with reference to the architect that “as the architect is in the first instance the interpreter of the conditions of the contract and the judge of its performance,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ramirez Co. v. Housing Authority of City of Houston
777 S.W.2d 167 (Court of Appeals of Texas, 1989)
Shafer Plumbing & Heating, Inc. v. Controlled Air, Inc.
742 S.W.2d 717 (Court of Appeals of Texas, 1987)
Bernard Johnson, Inc. v. Continental Constructors, Inc.
630 S.W.2d 365 (Court of Appeals of Texas, 1982)
Beeman v. Worrell
612 S.W.2d 953 (Court of Appeals of Texas, 1981)
Untitled Texas Attorney General Opinion
Texas Attorney General Reports, 1971
Salmon v. Salmon
406 S.W.2d 949 (Court of Appeals of Texas, 1966)
Johnson v. Woodard
352 S.W.2d 9 (Supreme Court of Missouri, 1961)
Burg v. Hitzfeld
89 S.W.2d 272 (Court of Appeals of Texas, 1935)
American Surety Co. of New York v. Shaw
69 S.W.2d 47 (Texas Commission of Appeals, 1934)
State v. Gentry
44 S.W.2d 27 (Supreme Court of Missouri, 1931)
State v. Hill
44 S.W.2d 103 (Supreme Court of Missouri, 1931)

Cite This Page — Counsel Stack

Bluebook (online)
39 S.W.2d 1, 120 Tex. 374, 77 A.L.R. 1122, 1931 Tex. LEXIS 173, Counsel Stack Legal Research, https://law.counselstack.com/opinion/manett-seastrunk-buckner-v-terminal-building-corp-tex-1931.