Manett-Seastrunk v. Terminal Bldg. Corp. of Dallas

23 S.W.2d 786
CourtCourt of Appeals of Texas
DecidedDecember 12, 1929
DocketNo. 852.
StatusPublished
Cited by1 cases

This text of 23 S.W.2d 786 (Manett-Seastrunk v. Terminal Bldg. Corp. of Dallas) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Manett-Seastrunk v. Terminal Bldg. Corp. of Dallas, 23 S.W.2d 786 (Tex. Ct. App. 1929).

Opinions

Appellants entered into a written contract with appellee to do the electrical work on what is known as the Terminal Building in Dallas, for an agreed price of $78,645.50. Said contract provided that appellee would pay appellants on the 1st and 15th of each month 90 per cent. of the value of the work done and material placed on the ground, upon certificates issued by the architect. The contract further provided that appellee could order extra work done or make any changes in the original plans and specifications, and provided that the value of such extra work, where not agreed upon, should be determined: (c) By cost and percentage, or by cost and fixed fee; and provided that appellants as contractors "shall keep and present in such form as the architect may direct, a correct amount of the net cost of labor and materials, together with vouchers." The contract provided that, before the architect should issue a certificate for the payment of any sum due under the original plans and specifications, the contractor should submit to the architect an application for each payment, and, if required, submit receipts or other vouchers showing his payments for material and labor, and submit a statement based upon the original schedule, itemized in such form *Page 787 and supported by such evidence as the architect might direct, and provides that the architect shall upon such proof issue to the contractor a certificate for such amount as he (the architect) decides to be properly due. The contract further provides that the architect could refuse to issue a certificate for several reasons, among others: (d) A reasonable doubt that the contract could be completed for the balance unpaid. Article 12 of the contract provides:

"* * * If the architect shall fall to issue any certificate for ten days after it is due, and the owner shall fail for twenty days after written notice of such fault by architect to have such certificate issued and the amount due thereunder paid * * * then the contractor may upon seven days written notice to the owner and the architect, stop work or terminate this contract, and recover from the owner payment for all work executed and any loss sustained upon plant, materials, materials contracted for, and reasonable profit on work completed to that date."

Under said contract appellants began work in the fall of 1923, and continued until October, 1925. During the construction of the building, a number of changes were made in the plans and specifications relative to the electrical work, which materially enhanced the cost thereof. Appellants presented at intervals twenty-two estimates prior to March 1, 1925, totalling $89,605.06, and same were paid, less $8,960.50, the 10 per cent. withheld under the terms of the contract. Between March 1st and July 9th appellants submitted their estimates 23 to 28, inclusive, each of said estimates for the total amount claimed by appellants to be due for work done and material furnished both under the original contract and for extra work. Neither of said estimates was approved by the architect, and neither of them was paid by appellee. During said time, however, appellee made payments to appellants on account as follows: April 5th, $5,000; June 8th, $3,000; and July 8, $5,369.66. The twenty-eighth estimate, being the last one filed by appellants with the architect, was dated July 9th, under which appellants claimed that there was due them, after allowing the credits for advancements above set forth, $27,986.64. Said estimates showed that the work called for in the original contract lacked $7,500 of being completed, and that the extra work called for by order No. 1 lacked $1,000 of being completed. It further showed that appellants had been paid for work done on the contract a total of $91,423.11. The architect refused to issue a certificate for any portion of said estimate. Appellants continued from the time they filed said estimate No. 28 on July 8, 1925, to work on said building until October 16th, claiming that during said time they did approximately $28,000 worth of additional work. On October 16th appellants ceased to work on said building, and abandoned their contract, claiming that appellee had breached its part of said contract by having refused to pay their estimate No. 28, as required under provision No. 12 of the contract, quoted above. The record shows that on September 5, 1925, appellants wrote appellee that the architect had refused to issue a certificate on their estimate No. 28, and demanded that appellee pay the amount of said estimate.

On October 9th appellants wrote appellee and the architect that, since estimate No. 28 had not been paid, they would, at the end of 7 days from said date, stop work and terminate said contract. In conformity therewith, appellants did on October 16th quit work, and on November 10, 1925, they instituted this suit against appellee to recover on quantum meruit for the work they had done and the material furnished in the installation of the electrical engineering work on said Terminal Building; appellant's theory being that, since appellee had breached the contract by failure to pay estimate No. 28, they could abandon the contract and recover from appellee the reasonable market value of the material furnished and the work done under the contract in its entirety, which they alleged to be $189,829.58, and on which they alleged they had been paid $95,415.16, and they asked for judgment for the unpaid portion to wit, $94,414.12.

Appellee contends that it was not in default in refusing to have the architect issue a certificate on estimate No. 28, or in refusing to pay said estimate, and contends that appellants were in no position to demand the issuance of a certificate on said estimate or the payment thereof, because they had failed and refused to submit either to the architect or to appellee the invoices showing the net cost price of labor or the material used for the extra work, and that by reason thereof there was no way for either the architect or for appellee to check and determine whether said estimate was correct or whether there was anything due thereunder. Appellee further alleged that, after appellants had abandoned their contract, it was required to and did complete the work called for under said contract at a cost of $8,000, and that it was entitled to retain said amount out of any sum which appellants might recover.

The cause was tried to a jury, and at the conclusion of the testimony the trial court indicated that he thought, under the undisputed facts, appellants were not entitled to recover on the cause as alleged for quantum meruit, but that he thought on equitable grounds they should, if possible, recover the $28,960.89 which appellee admitted was due them as the unpaid balance for the work done under the contract, after allowing appellee the amount it had been required to pay to complete said contract, and thereupon appellee filed a trial amendment, tendering said *Page 788 amount to appellants, and the court then instructed the jury to return a verdict in favor of appellants against appellee for said amount, and judgment was entered in accordance therewith.

Appellants did not sue on the contract, and made no claim thereunder. Their sole contention is that appellee breached the contract by having failed to make a payment on their estimate No. 28, and that, since appellee did breach said contract, they had a right to abandon the same and sue on quantum meruit for the reasonable market value of the labor and material furnished in the construction of the work they had done.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Manett, Seastrunk & Buckner v. Terminal Building Corp.
39 S.W.2d 1 (Texas Supreme Court, 1931)

Cite This Page — Counsel Stack

Bluebook (online)
23 S.W.2d 786, Counsel Stack Legal Research, https://law.counselstack.com/opinion/manett-seastrunk-v-terminal-bldg-corp-of-dallas-texapp-1929.