Beeman v. Worrell

612 S.W.2d 953, 1981 Tex. App. LEXIS 3273
CourtCourt of Appeals of Texas
DecidedFebruary 12, 1981
Docket20423
StatusPublished
Cited by18 cases

This text of 612 S.W.2d 953 (Beeman v. Worrell) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Beeman v. Worrell, 612 S.W.2d 953, 1981 Tex. App. LEXIS 3273 (Tex. Ct. App. 1981).

Opinion

GUITTARD, Chief Justice.

The principal question in this case is the measure of a building contractor’s recovery for a part performance which the jury has found was not substantial. The trial court apparently awarded the market value of the house as constructed, less the owners’ payments and the cost of remedying certain defects, and the owners appeal. We hold that this amount was properly determined to be the net benefit to the owners from the contractor’s part performance. We also hold that the owners are not entitled to recover damages for breach of a contractual warranty without establishing the contract price under a cost-plus-fee contract. Accordingly, we affirm.

The contractor sued for a balance alleged to be due on a cost-plus-fee contract and in the alternative in quantum meruit for “money, time, labor and materials” advanced for the construction of a home at the instance and request of the owners. The owners counterclaimed under the Deceptive Trade Practices Act, section 17.50, 1977 Tex.Gen.Laws, ch. 216, § 5, at 605, for damages for breach of an express warranty that the work would be of “fine quality construction.” As damages, they alleged the reasonable cost of completing the work and remedying defects and, alternatively, the difference between the value of the building as constructed and its value if constructed according to plans and specifications.

No complaint is made of the sufficiency of the evidence to support the verdict or the submission of any of the special issues. In answer to the issues submitted, the jury found, respectively, (1) that the contractor did not substantially perform, (2) that $30,-500 would be the reasonable cost to place the house in the condition it would have been in, had there been substantial performance, (3) that $170,000 was the reasonable cash market value of the house, excluding the lot, when the contractor discontinued working, (4) that $185,000 would have been the reasonable cash market value, of the house if constructed according to the contract, (5) that the reconstruction of the game room in accordance with the contract would be economically wasteful, but that the reconstruction or repair of four other items would not be economically wasteful, and (6) that the reasonable cost to remodel and reconstruct these other four items would be $20,500 in the aggregate. The jury also found (7) that the contractor warranted that he would construct the house “within the limits of fine quality construction,” (8) that the owner relied on such warranty, (9) that the contractor did not comply with the warranty, and (10) that his failure to comply was a producing cause of the damages suffered by the owners.

On this verdict both parties moved for judgment. The owners moved for judgment for three times the $20,500 found by *956 the jury as the cost of reconstructing or remodeling those items that could be repaired or reconstructed without economic waste, and for an attorney’s fee in an agreed amount. The contractor moved for judgment for $71,538.45, which he alleged to be his costs and his fee under the contract over and above the owners’ payments, less the offset of $20,500 which the jury found in answer to issue number six, a net of $51,038.45, plus an attorney’s fee in an agreed amount. The contractor’s motion does not mention a quantum meruit recovery. The trial court overruled both of these motions, denied recovery on the counterclaim, and rendered judgment for the contractor for $37,500 and the agreed attorney’s fee of $3,000. The judgment does not recite how the sum of $37,500 was computed, but the parties agree that the court took the figure of $170,000, found by the jury in answer to special issue number three, as the market value of the house as constructed, and deducted from that figure the owner’s payments of $112,000 and also the $20,500 cost of repairs and reconstruction found by the jury in answer to special issue number six.

1. Contractor’s Claim for Part Performance

On this appeal both parties complain of the judgment. The contractor concedes that he cannot recover under the contract, but contends that the trial court erred in refusing to award him judgment in quantum meruit for $170,000, which the jury found to be the value of the house as constructed, less the payments of $112,000 already received. He argues that this finding of the value of the defective building necessarily allows for any defects, and that the court erred in allowing another deduction for the cost of remedying defects. The owners contend that the court erred in awarding any recovery in addition to the payments received because recovery in quantum meruit can only be based on the value of the contractor’s services rather than on the market value of the building, which may be attributable to other factors and because no issues were requested or submitted justifying recovery in quantum meruit.

We conclude that the trial court properly allowed recovery in quantum me-ruit for the owner’s net benefit after offsetting the owner’s damages against the market value of the building. Since the contractor has not complied with his contract, his recovery must make allowance for all costs necessary to permit the owner to remedy any defects that can be remedied without economic waste, even though the cost of remedying such defects may not be reflected in the market value. To award the contractor the full market value of the defective building would have the effect of denying the owner’s right to damages sufficient to give them the building for which they contracted.

On the other hand, the value of the contractor’s services cannot be considered apart from enhancement of the value of the property, because what the contractor’s labor and materials were reasonably worth in the market may be more or less than the amount of the enhancement. Thus the market value of the building as constructed, less the cost of remedying defects that may be remedied without economic waste, is a proper measure of the contractor’s recovery in quantum meruit. We recognize that this recovery should not be in excess of the contractor’s reasonable expenditures for labor and materials, but in the absence of proof that the amount of these expenditures would be less than the value of the net benefit received, we hold that judgment for the amount of the net benefit was proper.

These conclusions are well supported by authority. The principle controlling a defaulting contractor’s recovery for a part performance, as stated in Restatement of Contracts, § 357 (1932), is the net benefit to the owner in excess of the harm caused by the contractor’s breach. Accord: 5A Corbin, Contracts §§ 1124, 1125 (1962). In determining this net benefit, the market value of the partially completed building is a relevant inquiry. Gonzales College v. McHugh, 21 Tex. 256, 259-60 (1858) (evi *957 dence of market value admissible); Grube v. Nick’s No. 2, 278 S.W.2d 252, 254 (Tex.Civ.App. — El Paso 1955, writ ref’d n. r. e.) (market value of land before construction and after abandonment of incomplete structure must be shown); cf. Krupicka v. White, 584 S.W.2d 733, 736-37 (Tex.Civ. App. — Tyler 1979, no writ) (net benefit from improvements erected under void contract).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Avis Ann Stahler v. Holly Hall
Court of Appeals of Texas, 2024
Corrections Products Company, LTD v. Gaiser Precast Construction
394 S.W.3d 818 (Court of Appeals of Texas, 2013)
IT Corp. v. Motco Site Trust Fund
903 F. Supp. 1106 (S.D. Texas, 1994)
Ramirez Co. v. Housing Authority of City of Houston
777 S.W.2d 167 (Court of Appeals of Texas, 1989)
Shafer Plumbing & Heating, Inc. v. Controlled Air, Inc.
742 S.W.2d 717 (Court of Appeals of Texas, 1987)
Box v. Au Forgeron de la Cour-Dieu, Inc.
708 S.W.2d 538 (Court of Appeals of Texas, 1986)
Southern Steel Co. v. Consolidated Engineering Co.
677 S.W.2d 97 (Court of Appeals of Texas, 1984)
Birds Construction, Inc. v. McKay
657 S.W.2d 514 (Court of Appeals of Texas, 1983)
Pickens v. Stroud
653 S.W.2d 146 (Court of Appeals of Arkansas, 1983)
St. John v. Barker
638 S.W.2d 239 (Court of Appeals of Texas, 1982)
Guerra v. Brumlow
630 S.W.2d 425 (Court of Appeals of Texas, 1982)

Cite This Page — Counsel Stack

Bluebook (online)
612 S.W.2d 953, 1981 Tex. App. LEXIS 3273, Counsel Stack Legal Research, https://law.counselstack.com/opinion/beeman-v-worrell-texapp-1981.