McKnight v. Renfro

371 S.W.2d 740, 1963 Tex. App. LEXIS 1730
CourtCourt of Appeals of Texas
DecidedSeptember 27, 1963
Docket16236
StatusPublished
Cited by31 cases

This text of 371 S.W.2d 740 (McKnight v. Renfro) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
McKnight v. Renfro, 371 S.W.2d 740, 1963 Tex. App. LEXIS 1730 (Tex. Ct. App. 1963).

Opinion

DIXON, Chief Justice.

Dan McKnight, a building contractor, brought suit against Otis Renfro and wife, Nellie Renfro, for alleged breach of a written contract whereby McKnight for a consideration of $8,597.00 agreed to build a house within 90 days on property owned by the Renfros.

McKnight pled that he was performing the work in a reasonable and workmanlike manner when the Renfros on February 13, 1960, the 93rd day, contrary to his wishes, took over the construction job, which had progressed 90% toward completion. McKnight further alleged that he was ready, able and willing to continue the work and could have completed the job in about ten days if the Renfros had permitted him to do so. McKnight went to trial on his alternative plea wherein he seeks recovery on a quantum meruit basis for labor and materials he had furnished up to the time the Renfros took over.

The Renfros filed an answer and a cross-action. They alleged that time was of the essence of the contract and that McKnight breached the contract by failing to complete the house within 90 days. As a consequence of such breach, as well as other alleged breaches, they took over the work and finished the house themselves. They seek recovery for the amount by which the cost of the completed house exceeded the contract price of $8,597.00.

The record before us does not include a statement of facts. However, some of the facts are undisputed. McKnight had actually begun work in the construction of the house on November 2, 1959. Subsequently, on November 17, 1959, the parties executed their written contract. The instrument expressly provides that McKnight «will within a period of ninety (90) days from November 12, 1959, build a house” on the Renfros’ property. McKnight did not complete the house within the 90 day period. On February 13, 1960, the Renfros took over the job and thereafter finished the house at their own expense. Prior to taking over the Renfros had made payments to McKnight totalling $6,000.00.

A jury made findings in substance as follows: (1) the reasonable value of the material and services furnished by McKnight was $6,912.00; (2) on February 19, 1960, McKnight presented his claim for materials and services in excess of the $6,000.00 he had been paid; (3) reasonable attorneys’ fees for McKnight are $500.00; (4) McKnight agreed to complete the house within 90 days from November 12, 1959; (5) for a consideration of $8,597.00; (6) the property is the homestead of the Ren-fros; (7) McKnight performed the work he did in substantial compliance with the contract, and (8) in good and workmanlike manner; (9) none of the materials used by McKnight are defective; (11) the Renfros reasonably and necessarily expended the sum of $3,400.00 in order to complete the house; and (12) the reasonable value of shiplap belonging to the Renfros that was used by McKnight was $60.00.

In his written judgment, dated November 2, 1962, the trial court also made findings and conclusions which in substance are as follows: (1) time was of the essence of the contract; (2) McKnight is entitled to the sum of $6,912.00 (the value of materials furnished by him) less the sum of $6,000.00 previously paid by the Renfros, leaving a remainder of $912.00 due to McKnight; (3) the Renfros were entitled to recover from McKnight the sum of $3,-400.00 (the amount they expended in completing the house) less the sum of $2,597.00 (the difference between the $6,000.00 paid to McKnight and the contract price of $8,597.00), leaving a remainder of $803.00, which is the amount by which the cost of the house exceeded the contract price; (4) the Renfros were also entitled to recover $60.00, the value of the shiplap, making a total of $863.00 due the Renfros; *743 (5) the Renfros’ recovery of $863.00 should be set off against McKnight’s recovery of $912.00, leaving a balance due McKnight of $49.00; (6) McKnight is also entitled to attorneys’ fees of $500.00, making a total of $549.00 as the amount of the judgment to which McKnight is entitled.

Both sides filed motions for judgment based on the jury’s verdict. Judgment was rendered in favor of McKnight for $549.00 against Otis Renfro, but not against his wife, Nellie Renfro.

Both McKnight and Otis Renfro have appealed.

McKNIGHT’S APPEAL

McKnight contends that he should have judgment for $1,412.00, being $6,912.00 (the value, as found by the jury, of his part performance) less the $6,000.00 paid to him by the Renfros, plus $500.00 attorneys’ fees.

Since the record before us does not contain a statement of facts, we must base our decisions on the undisputed facts as disclosed by the pleadings and briefs, the findings of the jury and the findings and conclusions of the court insofar as it is permissible for fact findings by the court to be considered in this case.

The sum and substance of McKnight’s contention is that he is entitled to recover for his partial performance on a quantum meruit basis for the work and materials furnished by him even if the total cost of the house after completion exceeded the contract price of $8,597.00. In support of this contention McKnight cites authorities which hold that such a recovery is permissible when full performance by the contractor is excused by reason of the wrongful acts of the owner. Texas Associates v. Joe Bland Construction Co., Tex.Civ.App., 222 S.W.2d 413; 10 Tex.Jur.2d 47-48; 17 C.J.S. Contracts § 112, p. 834.

We have concluded that McKnight is not entitled to recover under the above theory because he has failed to show that full performance by him was prevented by the wrongful conduct of the Renfros. There is no finding by the jury of any wrongful conduct by the Renfros and no showing that submission of pertinent issues was requested. McKnight’s pleadings do allege wrongful acts by the Renfros, but the Renfros plead in denial of McKnight’s allegations. Of course McKnight’s pleadings do not constitute any proof whatsoever. In the absence of a statement of facts we cannot know that there was even any evidence of the alleged wrongful conduct of the Renfros.

McKnight apparently relies on the jury’s answers to Special Issues Nos. 7, 8 and 9 to support his claim. The jury found that (7) McKnight performed the work he did “in substantial compliance with the contract and plans”; (8) he performed the work he did “in a good and workmanlike manner” and (9) “the materials used by Dan McKnight” were not defective.

The three issues and the jury’s answers do not explain why McKnight failed to complete the performance of his contract. Certainly they are not findings of any wrongful conduct on the part of the Ren-fros in taking over and completing the construction of the house.

A good portion of McKnight’s brief is taken up by argument and citations of authorities in an effort to show that time was not of the essence of the contract. We shall postpone our discussion of that question until we consider the appeal of the Renfros later in this opinion.

McKnight’s first three points on appeal allege error because the court sustained three special exceptions leveled at McKnight’s first amended petition. We do not find in the transcript any order or copy of an order sustaining the exceptions, therefore, we cannot consider McKnight’s first three points. George v. Senter, Tex.Civ.App., 194 S.W.2d 290; Garcia v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

TrueStar Petroleum Corp. v. Eagle Oil & Gas Co.
323 S.W.3d 316 (Court of Appeals of Texas, 2010)
Walker & Associates Surveying, Inc. v. Austin
301 S.W.3d 909 (Court of Appeals of Texas, 2010)
Clarence Rakestraw v. State
Court of Appeals of Texas, 1998
Beavers v. Goose Creek Consolidated I.S.D.
884 S.W.2d 932 (Court of Appeals of Texas, 1994)
D.E.W., Inc. v. Depco Forms, Inc.
827 S.W.2d 379 (Court of Appeals of Texas, 1992)
Vance v. My Apartment Steak House of San Antonio, Inc.
677 S.W.2d 480 (Texas Supreme Court, 1984)
Gulf Oil Corp. v. Williams
642 S.W.2d 270 (Court of Appeals of Texas, 1982)
Ybarra v. Saldana
624 S.W.2d 948 (Court of Appeals of Texas, 1981)
Beeman v. Worrell
612 S.W.2d 953 (Court of Appeals of Texas, 1981)
Smith v. Kinslow
598 S.W.2d 910 (Court of Appeals of Texas, 1980)
Mecey v. Seggern
596 S.W.2d 924 (Court of Appeals of Texas, 1980)
Siderius, Inc. v. Wallace Co., Inc.
583 S.W.2d 852 (Court of Appeals of Texas, 1979)
Freeman v. Shannon Construction, Inc.
560 S.W.2d 732 (Court of Appeals of Texas, 1978)
Mayer v. Alexander and Baldwin, Inc.
532 P.2d 1007 (Hawaii Supreme Court, 1975)
Laredo Hides Co., Inc. v. H & H Meat Products Co., Inc.
513 S.W.2d 210 (Court of Appeals of Texas, 1974)
Superior Signs, Inc. v. American Sign Services, Inc.
507 S.W.2d 912 (Court of Appeals of Texas, 1974)

Cite This Page — Counsel Stack

Bluebook (online)
371 S.W.2d 740, 1963 Tex. App. LEXIS 1730, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mcknight-v-renfro-texapp-1963.