MHI Partnership, Ltd. v. DH Real Estate Investment Company D/B/A DH Investment Company

CourtCourt of Appeals of Texas
DecidedAugust 20, 2008
Docket03-04-00485-CV
StatusPublished

This text of MHI Partnership, Ltd. v. DH Real Estate Investment Company D/B/A DH Investment Company (MHI Partnership, Ltd. v. DH Real Estate Investment Company D/B/A DH Investment Company) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
MHI Partnership, Ltd. v. DH Real Estate Investment Company D/B/A DH Investment Company, (Tex. Ct. App. 2008).

Opinion

TEXAS COURT OF APPEALS, THIRD DISTRICT, AT AUSTIN




NO. 03-04-00485-CV

MHI Partnership, Ltd., Appellant


v.



DH Real Estate Investment Company d/b/a DH Investment Company, Appellee



FROM THE DISTRICT COURT OF TRAVIS COUNTY, 200TH JUDICIAL DISTRICT

NO. GN200866, HONORABLE PAUL DAVIS, JUDGE PRESIDING



M E M O R A N D U M O P I N I O N


Appellant MHI Partnership, Ltd., appeals from the trial court's judgment against it in its breach-of-contract action against appellee DH Real Estate Investment Company d/b/a DH Investment Company. We affirm the trial court's judgment.



Factual and Procedural Background



DH, a real estate development company, purchased land to develop into residential lots for later sale to builders to create the "Covered Bridge" subdivision. Two builders, MHI and Wilshire homes, entered into contracts with DH to purchase these lots. Under the initial contract, the lots were to be developed and sold to the builders in three phases, at a fixed price. In June 1999, this pricing method was modified to a "cost pass-through" method to allow for additional construction costs. The allowed pass-through had a percentage cap based on the original fixed price for the lots. DH was required to show proof of the need for cost escalation by giving written notice of any escalation together with backup information verifying the cost increases for each phase at least three weeks prior to the date of closing the purchase. The 22-page contract (excluding exhibits), in paragraph L of "Miscellaneous Provisions" stated: "Time of the Essence. Time is of the essence of this Contract."

In January 2001, the parties made various contract amendments. The change with significance to this dispute was the modification of the provision allowing for higher costs to be passed through so that it became a "two-way street": if the actual costs were less than the budgeted costs for the phase, then the purchase price of each lot would be reduced. The same documentation and notification requirements continued to apply.

On February 28, 2002, DH provided MHI with written notice of substantial completion of Phase 1 and demanded that closing on the lot sales occur within 10 days, on or before March 11, 2002. DH also notified MHI that the additional cost amount for Phase 1 was 2% more than the base purchase price, an increase within the cap. DH provided written notice of the actual construction and engineering costs but it did not provide backup information for all the costs at least three weeks before the proposed closing date.

On March 5, 2002, MHI responded to DH's request to set the closing date on March 11 by requesting that the closing be extended so that MHI would have an opportunity to review the backup cost information. DH responded on the same day, requesting that the closing proceed on the proposed date and also proposing, as an alternative, to delay closing for three weeks. On the same day, DH sent an email to MHI proposing the following modification:



As to the Actual Costs versus Budgeted Costs, if you are concerned about what happens if there is a price reduction, this is to confirm that, assuming we close as we have proposed, we will execute an agreement that in the event the cost review results in a reduction in prices we will reimburse MHI that amount plus interest from the date of closing. Conversely, we would expect MHI to do likewise.



MHI did not respond to the proposed modification. MHI received the construction and engineering cost backup information for Phase 1 two days later on March 7, 2002.

The next day, March 8, MHI terminated the contract based on DH's failure to provide the backup information for all construction and engineering costs three weeks before the proposed closing date, as required in the contract. On March 11, DH responded to MHI's termination letter by offering to extend the closing date and waive any interest charges. MHI responded on March 13, confirming the termination and requesting reimbursement of its earnest money. DH refused to reimburse the earnest money and MHI sued. (1)



The Trial and Verdict



The case was tried to a jury in April 2004. After hearing testimony from both sides, the trial court denied MHI's motion for directed verdict. It also overruled MHI's objections to Jury Question No. 1, "Was Defendant's [DH's] conduct in this case a material breach of contract between the parties?" The question then provided instructions for determining materiality. The jury answered no to the question. The trial court entered judgment in favor of DH. This appeal followed.

In this appeal, MHI presents six issues. Five of its issues hinge on its assertion that it established a material breach as a matter of law. MHI contends that the trial court erred in: (1) denying MHI's motion for directed verdict because the evidence established a material breach of contract as a matter of law; (2) overruling MHI's objections to the submission of Question No. 1 to the jury because the evidence established a material breach of contract as a matter of law; (3) overruling MHI's objections to the inclusion of Instruction 1 in Jury Question No. 1 because the evidence established a material breach of contract as a matter of law; (2)

(4) overruling MHI's objection to the inclusion of Instruction 5 in Jury Question No. 1 because the evidence established a material breach of contract as a matter of law; (3) and (5) denying MHI's motion to disregard jury finding and motion for entry of final judgment because the evidence established a material breach of contract as a matter of law. In its sixth issue, MHI contends that the trial court erred in denying MHI's motion for new trial because the jury's answer to Question No. 1 is against the great weight and preponderance of the evidence, or alternatively, is not supported by factually sufficient evidence.

Discussion

The essence of MHI's complaint is that DH materially breached the contract by violating the "time is of the essence" provision of the contract because it did not provide the required backup information at least three weeks before the proposed closing date as specified in the contract. MHI asserts that it was entitled to a directed verdict because it established this material breach as a matter of law. There are two aspects to analyzing this complaint. One aspect is MHI's burden of proof to be entitled to the directed verdict for which it moved. Another aspect is whether this "boilerplate" time is of the essence clause tucked into a section of miscellaneous contract provisions meant that a failure to comply with any deadline was a material breach justifying contract termination or whether this clause was simply a term that time was important to some aspects of the contract, requiring a search for the parties' intent with regard to this particular contract.



Directed Verdict Review



An appeal from the denial of a motion for directed verdict is in essence a challenge to the legal sufficiency of the evidence. Solares v. Solares

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Mustang Pipeline Co. v. Driver Pipeline Co.
134 S.W.3d 195 (Texas Supreme Court, 2004)
Ford Motor Co. v. Ledesma
242 S.W.3d 32 (Texas Supreme Court, 2007)
Texas Workers' Compensation Insurance Fund v. Mandlbauer
34 S.W.3d 909 (Texas Supreme Court, 2001)
Compass Bank v. MFP Financial Services, Inc.
152 S.W.3d 844 (Court of Appeals of Texas, 2005)
Byrd v. Delasancha
195 S.W.3d 834 (Court of Appeals of Texas, 2006)
Beaumont Bank, N.A. v. Buller
806 S.W.2d 223 (Texas Supreme Court, 1991)
Municipal Administrative Services, Inc. v. City of Beaumont
969 S.W.2d 31 (Court of Appeals of Texas, 1998)
Collora v. Navarro
574 S.W.2d 65 (Texas Supreme Court, 1978)
Solares v. Solares
232 S.W.3d 873 (Court of Appeals of Texas, 2007)
McKnight v. Renfro
371 S.W.2d 740 (Court of Appeals of Texas, 1963)
Kennedy Ship & Repair, L.P. v. Pham
210 S.W.3d 11 (Court of Appeals of Texas, 2006)
Trinity Industries, Inc. v. Ashland, Inc.
53 S.W.3d 852 (Court of Appeals of Texas, 2001)
City of Keller v. Wilson
168 S.W.3d 802 (Texas Supreme Court, 2005)
Armstrong v. Collin County Bail Bond Board
233 S.W.3d 57 (Court of Appeals of Texas, 2007)
Perez v. Embree Construction Group, Inc.
228 S.W.3d 875 (Court of Appeals of Texas, 2007)
Strackbein v. Prewitt
671 S.W.2d 37 (Texas Supreme Court, 1984)
Bocquet v. Herring
972 S.W.2d 19 (Texas Supreme Court, 1998)
Siderius, Inc. v. Wallace Co., Inc.
583 S.W.2d 852 (Court of Appeals of Texas, 1979)
Langley v. Norris
173 S.W.2d 454 (Texas Supreme Court, 1943)

Cite This Page — Counsel Stack

Bluebook (online)
MHI Partnership, Ltd. v. DH Real Estate Investment Company D/B/A DH Investment Company, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mhi-partnership-ltd-v-dh-real-estate-investment-co-texapp-2008.