Trinity Industries, Inc. v. Ashland, Inc.

53 S.W.3d 852, 2001 Tex. App. LEXIS 5357, 2001 WL 893411
CourtCourt of Appeals of Texas
DecidedAugust 9, 2001
Docket03-00-00217-CV
StatusPublished
Cited by83 cases

This text of 53 S.W.3d 852 (Trinity Industries, Inc. v. Ashland, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Trinity Industries, Inc. v. Ashland, Inc., 53 S.W.3d 852, 2001 Tex. App. LEXIS 5357, 2001 WL 893411 (Tex. Ct. App. 2001).

Opinion

ABOUSSIE, Chief Justice.

Trinity Industries, Inc. (“Trinity”) sued Ashland, Inc. and ATEC, Inc. (collectively “Ashland”) 1 for damages arising out of Ashland’s sale of its subsidiary, Beaird Industries, Inc. (“Beaird”), to Trinity. 2 Ashland asserted third-party claims against Beaird. A jury found against Trinity on its claims against Ashland and against Ashland on its claims against Beaird, and the trial court rendered judgment, which Trinity now appeals. We will affirm the judgment.

*858 BACKGROUND

On January 12, 1990, Trinity entered into a Purchase and Sale Agreement (the “Agreement”) with Ashland whereby Trinity would purchase all of the outstanding stock of Beaird. Beaird’s industrial plant is located in Shreveport, Louisiana, where it manufactures steel vessels and other equipment. The Agreement required Ash-land to perform an environmental audit on the Beaird facility. Ashland retained the environmental engineering firm of Dames & Moore to assess environmental conditions at the Beaird facility. Dames & Moore prepared a preliminary environmental assessment, dated January 22, 1990. The final version, entitled “Environmental Assessment,” was completed on February 8, 1990. In its environmental assessment, Dames & Moore identified two areas of possible environmental contamination on the property: a storm-water ditch and a soil-stained area. Trinity responded to the February 8 environmental assessment by sending Ashland a letter detailing twenty items that Trinity wished resolved before it would complete the Beaird purchase.

Dames & Moore then conducted a second environmental assessment to more specifically define the areas of environmental concern identified in the February 8 environmental assessment. Dames & Moore completed its second assessment, entitled “Phase II Environmental Assessment Final Report” (“Phase II Assessment”), on April 6, 1990. The Phase II Assessment identified a soil-stained area near Beaird’s maintenance building and the presence of trichloroethene (“TCE”) in the groundwater under the Beaird facility; the contamination was estimated “to be limited to a 400-foot diameter area ... at a depth of 42 feet.” The Phase II Assessment also proposed a remediation plan and remedial cost estimates for the contaminated groundwater and stained soil of $81,000 to $102,000. Ashland relied on Dames & Moore’s environmental assessments in making representations to Trinity in connection with the sale.

After Dames & Moore prepared the Phase II Assessment, Ashland and Trinity entered into the Second Amendment to the Purchase and Sale Agreement (the “Second Amendment”). The Second Amendment defined the area of soil staining and groundwater contamination described in the Phase II Assessment as the “Identified Contamination.” The Second Amendment also addressed the cleanup of the Identified Contamination, referred to as the “Identified Contamination Remediation,” by defining Ashland’s obligations to clean up the property. This appeal principally concerns section 3.12(m) of the Second Amendment relating to Ashland’s obligations to pay for cleanup of the Identified Contamination.

Before closing the sale, Ashland obtained a certificate signed by William Adams, then president of Beaird, dated April 23, 1990. Ashland had obtained a similar certificate from Adams dated February 12, 1990. In the February 12 and April 23 certificates (the “Adams certificates”), Adams certified that “to the best of [his] knowledge and belief, all of the representations and warranties of ATEC, Inc. and Ashland Oil, Inc. (“Ashland”) in the Purchase and Sale Agreement among ATEC, Ashland, and Trinity Industries, Inc. dated January 12, 1990, are materially true and correct.”

The sale of Beaird to Trinity closed on April 23, 1990. After closing, Ashland hired Dames & Moore to perform the Identified Contamination Remediation. On February 11, 1991, Dames & Moore compiled a status report on the soil and ground water remediation at the Beaird property. The report stated that Dames <& Moore had not encountered a confining layer of soil as it had expected and that *859 the contaminants had increased in certain wells. In October 1991, the Louisiana Department of Environmental Quality conducted an investigation at the Beaird facility based on a complaint it received that paint and other waste had been buried on the property.

In 1996 after spending $500,000 on cleanup operations at Beaird, Ashland turned over remediation of the site to Trinity. Ashland’s decision to cease cleanup operations was apparently based on its interpretation of a provision in the Agreement that purported to limit Ashland’s obligations to $500,000. As Beaird’s new parent company, Trinity began to oversee the cleanup. Trinity thereafter filed suit against Ashland for breach of the Agreement and fraud. The case was tried before a jury, which found in favor of Ash-land on Trinity’s claims against Ashland and in favor of Beaird on Ashland’s claims against Beaird. Specifically, the jury found that Ashland’s total obligation to pay for cleanup of the property would under no circumstances exceed $500,000. The jury failed to find Ashland hable for breach of contract, fraud, or statutory fraud. The trial court consequently rendered judgment against Trinity on its claims against Ashland, and against Ashland on its claims against Beaird. Trinity now appeals the trial court’s judgment.

DISCUSSION

Submission of Jury Instruction

By its first two issues on appeal, Trinity argues that submission of the first jury question and accompanying instruction constituted harmful error. Alternatively, Trinity argues that even if question number one was properly submitted, there was insufficient evidence to support the jury’s affirmative answer. The first jury question asked the following: “Did Ashland and Trinity agree that Ashland’s total obligation to pay for cleanup of the property would under no circumstances exceed $500,000?” The trial court, apparently determining that the Agreement at issue was ambiguous, instructed the jury as follows with respect to section 3.12(m):

It is your duty to interpret the following language of the second amendment:
[3.12(m) ]
Notwithstanding any other provision of this Agreement to the contrary, the obligations of Ashland and ATEC described in Sections 3.12(e) and 5.2(a)(10) shall be limited to a maximum amount of Five Hundred Thousand Dollars ($500,000).
You must decide its meaning by determining the intent of the parties at the time of the agreement. Consider all the facts and circumstances surrounding the making of the agreement, the interpretation placed on the agreement by the parties, and the conduct of the parties.

The jury answered the question in the affirmative.

Trinity objected at trial that, because section 3.12(m) is unambiguous as a matter of law, its construction was a question of law for the court, not of fact for the jury. The trial court overruled Trinity’s objection and submitted the matter to the jury.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Elmen Holdings v. Martin Marietta
86 F.4th 667 (Fifth Circuit, 2023)
Linda S. Nowlin v. Samarra Davis
Court of Appeals of Texas, 2019
R2 Restaurants, Inc. v. Mineola Community Bank, SSB
561 S.W.3d 642 (Court of Appeals of Texas, 2018)
U.S. Kingking, LLC v. Precision Energy Servs., Inc.
555 S.W.3d 200 (Court of Appeals of Texas, 2018)
Linda Frew v. Chris Traylor
820 F.3d 715 (Fifth Circuit, 2016)
Henning, Kenneth v. OneWest Bank FSB
405 S.W.3d 950 (Court of Appeals of Texas, 2013)
White Oak Operating Co. v. BLR Construction Companies
362 S.W.3d 725 (Court of Appeals of Texas, 2011)
RSI International, Inc. v. CTC Transportation, Inc.
291 S.W.3d 104 (Court of Appeals of Texas, 2009)
Sydlik v. REEIII, INC.
195 S.W.3d 329 (Court of Appeals of Texas, 2006)
Fasken Land & Minerals, Ltd. v. Occidental Permian Ltd.
225 S.W.3d 577 (Court of Appeals of Texas, 2005)

Cite This Page — Counsel Stack

Bluebook (online)
53 S.W.3d 852, 2001 Tex. App. LEXIS 5357, 2001 WL 893411, Counsel Stack Legal Research, https://law.counselstack.com/opinion/trinity-industries-inc-v-ashland-inc-texapp-2001.