Da Moth & Rose v. Hillsboro Independent School Dist.

186 S.W. 437, 1916 Tex. App. LEXIS 659
CourtCourt of Appeals of Texas
DecidedApril 8, 1916
DocketNo. 7449. [fn*]
StatusPublished
Cited by7 cases

This text of 186 S.W. 437 (Da Moth & Rose v. Hillsboro Independent School Dist.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Da Moth & Rose v. Hillsboro Independent School Dist., 186 S.W. 437, 1916 Tex. App. LEXIS 659 (Tex. Ct. App. 1916).

Opinions

* Application for writ of error pending in Supreme Court. *Page 438 Appellants contracted with the Hillsboro independent school district to build a certain school building according to certain plans and specifications for the consideration of $50,000, and for the faithful performance of said contract appellants executed a bond for $25,000, payable to said school district with the General Bonding Casualty Company as surety. When the building was nearing completion, the roof fell in and damaged the building. The said school district had to repair the building, causing it to expend more than the contract price, to recover which it brought suit against Da Moth Rose and the surety company on its bond. Da Moth Rose answered, denying that they were required to rebuild the house after it fell, and deny that there were any plans for concrete work prepared or agreed to by them, and that they furnished the building according to the original contract, and deny that they agreed upon the system of concrete reinforcement actually used, and that after the building fell plaintiffs in rebuilding it materially changed the plans, and expended more than was necessary to reconstruct the building. They further answered that under the contract they were to prepare the plans for the concrete work, but while doing so they were informed by the architect that he had adopted plans prepared by the Trussed Concrete Steel Company, and that they had never seen the same; that they proceeded in exact accordance with said plans under the direction of plaintiffs and the architect, the steel company superintending every step in the construction of that part of the building; that they constructed the building in accordance with the substituted plans of good material and workmanship. They allege that said plans were faulty, and that the fall of the building was due to that fact, and pray for judgment for $13,500 balance due on the contract price. The bonding company answered, admitting the execution of the bond, guarantying the carrying out of the original contract, but alleged that another and different contract between plaintiffs and Da Moth Rose was entered into without its knowledge, setting out the particulars in which the changes were made; that said changes were material and caused the fall of the building, and *Page 439 therefore claims it was released from said bond. It further alleged that the stipulated notice was not given; that after the fall of the building plaintiffs took charge of same, and made a different contract with another to complete it in a different manner, and knew, or could have known, that the work was being defectively done, and by failing to give notice they were estopped; that —

"the contract with Da Moth Rose is unilateral on account of certain quoted powers given the trustees."

Da Moth Rose interpleaded the two Trussed Concrete Steel Companies, and alleged that these companies are owners and exploiters of a system of reinforcing concrete known as the "Kahn System," and they make a part of their cross-plea their entire answer to the action of plaintiff, and in addition set out that such steel companies, knowing that the contractors were entitled under the contract to prepare their own plans for concrete reinforcement, took up secretly with the architect the matter, and induced him to adopt their plans and buy their product, and then notified the contractors that the steel companies' plans therefor had been adopted, and thereupon the architect instructed them to construct the same according to the steel companies' plans; that such system is a patented device, and novel and experimental, and their course in this instance in keeping with their usual course, and that these contractors had not used or known of said system before; and that the instructions of said architect made it necessary for them to proceed or give up the building. They further allege that when the revised plans of the steel companies adopted by the architect were submitted to them, they did not have a copy of the original plans, which had been delivered to the steel companies by the architect, and did not know that a material departure had been made from the original plans, and that both the architect and steel companies assured them that the original plans had been complied with in preparing the revised plans; that they believed these representations and relied upon the same; that thereupon the steel companies and the architect took control of the direction and construction of the reinforced concrete work, and took the same entirely out of the hands of the contractors; that they now know that said revised plans were insufficient and dangerous; that they materially departed from the original plans, and reduced the carrying power of all floors and the roof; that all such changes were made without the knowledge or consent of defendant contractors, and with the full knowledge of the steel companies; that the steel companies and architect made no effort to conform the strength and carrying capacity of the building in the revised plans to those of the original plans, well knowing that the contractors had no means of discovering the same, and that the contractors were wholly relying upon them to see that the same was done. They further allege that the architect and steel companies assumed absolute control, and superintended the mixing of the concrete and all other details; that by reason of the premises and those set out in their answer to the plaintiffs' petition, the steel companies are indebted to them for $12,000, less $2,500 that it would have cost them to finish the building, had it not fallen, and ask for judgment in the sum of $9,500, and that, in the event of recovery by the plaintiff against them, they have judgment over and against the steel companies therefor; and that such judgment inure to the benefit of the school district. The steel companies, in answer to the plea of Da Moth Rose, deny that they were negligent in the construction of the plans, and deny that the building fell wholly by reason of defects in the roof. They allege they prepared plans and specifications for the construction of the reinforced part of said building under its system, and procured the architect to adopt them, and then procured Da Moth Rose to order from them their materials for the construction thereof; that Da Moth Rose knew in advance that they intended to submit such plans, and never objected or offered to submit any themselves; that after the plans had been adopted Da Moth Rose waived their right to object by agreeing to purchase material from them; that it was agreed by Da Moth Rose and them that the plans and drawings furnished by them should have no further effect than to show the amount of material required; that Da Moth Rose were wholly incompetent, and did not keep a competent foreman on the job; that they failed to protect the concrete from the sun, which caused it to become weak, and contributed to the fall of the building; that they used poor sand; that they did not provide sufficient compressive resistance of concrete used; that they did not properly mix the concrete used; that they did not use proper proportions of sand, cement, gravel, etc., in making the concrete for slabs, beams, etc.; that they poured concrete into molds that contained boards, shavings, etc.; that they used the longer steel where it was not needed, and left an insufficient amount of long steel where needed; that they failed to connect the steel of one section to that of another; that they failed to dowel the steel and bend up the bars; that they failed properly to wet the mixtures and to protect the roof from the heat, and failed to test the development of the compressive strength of the concrete before removing the supports.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Freeman v. Shannon Construction, Inc.
560 S.W.2d 732 (Court of Appeals of Texas, 1978)
Danaho Refining Co. v. Pan American Petroleum Corp.
383 S.W.2d 941 (Court of Appeals of Texas, 1964)
McKnight v. Renfro
371 S.W.2d 740 (Court of Appeals of Texas, 1963)
American Employers' Ins. Co. v. Huddleston
39 S.W.2d 952 (Court of Appeals of Texas, 1931)
Mood v. Methodist Episcopal Church South
289 S.W. 461 (Court of Appeals of Texas, 1926)
Garrett v. Dodson
199 S.W. 675 (Court of Appeals of Texas, 1917)

Cite This Page — Counsel Stack

Bluebook (online)
186 S.W. 437, 1916 Tex. App. LEXIS 659, Counsel Stack Legal Research, https://law.counselstack.com/opinion/da-moth-rose-v-hillsboro-independent-school-dist-texapp-1916.