Mood v. Methodist Episcopal Church South

289 S.W. 461
CourtCourt of Appeals of Texas
DecidedOctober 22, 1926
DocketNo. 225.
StatusPublished
Cited by17 cases

This text of 289 S.W. 461 (Mood v. Methodist Episcopal Church South) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mood v. Methodist Episcopal Church South, 289 S.W. 461 (Tex. Ct. App. 1926).

Opinions

The appellant, plaintiff below, sought to recover for services rendered in supervising the construction of a church building for appellees.

The trial was had upon appellant's sixth amended original petition in which recovery was prayed for on a quantum meruit for services performed after alleged mutual abandonment of a contract between the parties stipulating for specific compensation, and, in the alternative, for compensation under the contract. Special exceptions were sustained to that part of the petition seeking a recovery under the contract on the theory that such allegations set up a new cause of action and were inserted in an amended petition more than four years after performance of the service sued for. A trial before a jury was had upon the issue of quantum meruit, and upon an instructed verdict judgment was rendered against appellant.

Before proceeding with a discussion of the questions determinative of the appeal it is, perhaps, in order to dispose of those parties in whose favor the trial court's ruling was undoubtedly correct.

H. C. Rominger was originally a party defendant; his name was omitted from the fourth amended original petition and all subsequent amendments.

Appellees Webb, Bowman, Godbey, Elkins, Southern, Bailey, Witten, and Bedford were brought into the suit for the first time by the fifth amended original petition, filed March 26, 1925, more than four years after appellant's cause of action accrued, and the court rightfully sustained their exceptions that the cause of action was barred as to the appellees last above named.

As between appellant and the remaining appellees the following statement is submitted as being sufficient to illustrate the rulings under complaint and the conclusions reached thereon: Appellant, Mood, and one Page, contractors, entered into a contract with appellees Garner and Fisk, building committee of the M. E. Church South of Cisco, whereby the contractors agreed to provide all material and labor and to build a church building at a cost not to exceed $47,100. Upon completion of the building the contractors were to receive the amounts expended by them plus 10 per cent.; the building to be erected according to certain plans and specifications which were attached to the agreement. The contractors guaranteed that the cost of the building should not exceed the sum named; that no alterations be made in the work except upon the written order of the architect employed by the owners. The owners agreed to pay all labor and material bills as they accrued, when approved by the architect. This contract was made with the approval of the church trustees. Two contracts were signed, the first June 27, 1919, and the second about two weeks later. The building was completed at a cost of $67,093.64. During the progress of the work, appellees paid all bills for labor and material. Appellant (claiming an assignment of the interest of Page) in his original petition predicated his right to recover solely on a quantum meruit, based on allegations of mutual rescission and abandonment of the contract. In his third amended original petition filed within the bar of the statute of limitations, appellant pleaded the contract and attached a copy of the same as an exhibit to his petition, averred that the contractors had proceeded with the work thereunder until about the 15th day of August when the contract was mutually rescinded and abandoned, different plans for the building substituted, and the latter thereafter completed under the subsequent direction of appellees and their architect; that said building was not erected in all things in accordance with the original plans and specifications; that certain changes were made by appellees and were accepted and ratified by the architect, and in consequence the cost of the structure was enhanced and therefore exceeded the contract price; that but for said changes the cost of the building would not have exceeded the contract price; that the contractors fulfilled and carried out all the orders of appellees and their architect; that by virtue of said contract and the facts alleged appellees had become liable to the contractors for the full amount of 10 per cent. of the cost of the building and in the alternative for the reasonable value of the services of the contractors. These allegations were repeated in all subsequent amendments and were elaborated in great detail in the amended pleading on which the trial was had. In that pleading the causes of action were separated and relief asked, first, for quantum meruit after mutual rescission of the contract, and, in the alternative, the contract was pleaded and recovery sought thereon.

As stated, exceptions were sustained to that part of the petition seeking a recovery on the contract, and this ruling must be sustained under the authority of Reasoner v. G. C. S. F. Ry. Co., 109 Tex. 204,203 S.W. 592, where a judgment was sought for damages for personal injuries, and, in the alternative, for breach of contract to furnish *Page 463 employment, and the ruling was that the trial court correctly sustained the defendants' exception to that part of the petition seeking relief for failure to furnish employment, because it appeared from the allegations of the petition that ever since the injury plaintiff had been wholly disabled physically and incapable of performing any labor. In the third amended petition, the allegations that the contract had been mutually rescinded were carried throughout the entire pleading, and nowhere was there any claim of performance of the agreement, and not until the statement of the amount due appellant was there any claim, other than that the contract had been annulled by both parties; therefore the third amended original petition presented a claim for quantum meruit only, and the cause of action inserted in subsequent petitions seeking recovery on the contract was barred.

Appellant relied on the trial on evidence of abandonment by conduct; no evidence of any agreement to rescind was tendered. The substance of the evidence relied on is as follows: That after the first contract was signed and before execution of the new one, a different kind of brick to be used was substituted for that called for in the original specifications. That a change in the position of the pulpit and choir stand was made after the second contract was signed. That this change made necessary the rearrangement of the whole auditorium. That a number of defects in the original plans were discovered, and these and the changes in the auditorium required the preparation of new blue prints, which were delivered to the contractors. The change in the auditorium also required changes in the entrance and in the windows. The defects in the plans were in the height of the basement walls and in the roof and in the position of the windows. The changes noted may not detail all the changes alleged and proved, but are illustrative. The changes in the plans did not affect the general design, but related to the arrangement principally of the interior — the position of the windows; different materials for supporting the roof; for the cornices; for the bases of the columns; for height and approaches to basement. These changes appear to be mere deviations in the plans and not to substitute an entirely different building from the one originally contracted for. It is not denied that all deviations were made with the consent of the contractors. There was an agreement in writing between appellees and the contractors for extra payment of $800 for the changes in the auditorium, and, while there is a dispute as to the time the agreement was made, whether before the plans were changed or afterwards, this is believed to be immaterial.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cox v. Thee Evergreen Church
836 S.W.2d 167 (Texas Supreme Court, 1992)
Ro-Lo Enterprises v. Hicks Enterprises, Inc.
362 S.E.2d 888 (Court of Appeals of South Carolina, 1987)
Abrams v. Brent
362 S.W.2d 155 (Court of Appeals of Texas, 1962)
Ford v. Hofer
111 N.W.2d 214 (South Dakota Supreme Court, 1961)
Campbell v. Hart
256 S.W.2d 255 (Court of Appeals of Texas, 1953)
Capitol Steel & Iron Co. v. Standard Accident Insurance Co.
299 S.W.2d 738 (Court of Appeals of Texas, 1952)
Grossman v. Liedeker
202 S.W.2d 267 (Court of Appeals of Texas, 1947)
Collins v. Hall
161 S.W.2d 311 (Court of Appeals of Texas, 1942)
Sauder v. Dittmar
118 F.2d 524 (Tenth Circuit, 1941)
City of Del Rio v. Ulen Contracting Corporation
94 F.2d 701 (Fifth Circuit, 1938)
Sammons v. Hodges
95 S.W.2d 734 (Court of Appeals of Texas, 1936)
Redden v. Capps
15 S.W.2d 670 (Court of Appeals of Texas, 1929)
Humble Oil & Refining Co. v. Southwestern Bell Telephone Co.
2 S.W.2d 488 (Court of Appeals of Texas, 1927)
Mood v. Methodist Episcopal Church
296 S.W. 506 (Texas Commission of Appeals, 1927)

Cite This Page — Counsel Stack

Bluebook (online)
289 S.W. 461, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mood-v-methodist-episcopal-church-south-texapp-1926.