Capitol Steel & Iron Co. v. Standard Accident Insurance Co.

299 S.W.2d 738, 1952 Tex. App. LEXIS 2246
CourtCourt of Appeals of Texas
DecidedApril 21, 1952
Docket6207
StatusPublished
Cited by5 cases

This text of 299 S.W.2d 738 (Capitol Steel & Iron Co. v. Standard Accident Insurance Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Capitol Steel & Iron Co. v. Standard Accident Insurance Co., 299 S.W.2d 738, 1952 Tex. App. LEXIS 2246 (Tex. Ct. App. 1952).

Opinion

LUMPKIN, Justice.

On this appeal the appellant is the Capitol Steel & Iron Company, and the appellee is the Standard Accident Insurance Company. The suit was originated by the Lev-elland Independent School District filing a bill of interpleader in the District Court of Hockley County, Texas. The bill alleged that on July 30, 1948, the School District had entered into a contract with D. D. Humphries for the construction of a school building. Among other conditions, the contract provided that Humphries should make a bond guaranteeing the full performance of the contract. The bill alleged that Humphries, as contractor and principal, and the appellee, Standard Accident Insurance Company of Detroit, Michigan, as surety, did make and execute and deliver to the School District a statutory performance bond in the sum of $440,917, conditioned that Humphries would fully perform the contract. The School District pleaded that Humphries incurred obligations amounting to approximately $119,000 to various individuals, firms and corporations for materials and supplies for which he could not entirely pay. Under the contract the School District was allowed to retain 10% of the amounts owed the contractor on the architect’s estimates. The School District alleged that it had retained $43,154.71, and that after it had received notice from various creditors that Humphries was not paying their bills, it retained the sum of $19,-451.21 and offered into court the aggregate of these two sums — $62,605.95. In the in-terpleader petition all of Humphries’ creditors who had furnished labor and material —including the appellant, Capitol Steel & Iron Company, and the appellee, Standard Accident Company — were made parties and called upon to set up their respective claims against this fund.

On August 19, 1950, the court ordered the cause as to issues between the Level-land Independent School District and the creditors to be severed from the issues as made by the creditors in their cross-action against the contractor, D. D. Humphries, and the appellee, Standard Accident Insurance Company. The fund held by the School District was distributed pro rata to all the creditors. The claims of certain of the creditors were dismissed, while others filed no claim or cross-action or aban *740 doned their respective claims against Humphries and the appellee.

On February 1, 1951, the appellant, Capitol Steel & Iron Company, filed its second amended petition alleging that it had received only $7,049.73 out of the School District funds and that a balance of $6,537.27 was due from Humphries and the appellee. The appellant pleaded that it had entered into a contract with Humphries to furnish the steel products for the sum of $78,000. In addition to asking for a recovery against Humphries, the appellant sought recovery against the appellee alleging that the appel-lee’s bond with the School District guaranteed the payment of all claims arising in favor of the materialmen, such as the appellant. In the alternative, the appellant alleged that the bond was a common law obligation; that, in the second alternative, if it were not a common law obligation, then the appellant had performed all that was required and satisfied the provisions of Article 5160, Revised Civil Statutes, and Chapter 2, Title 90, Vernon’s Annotated Civil Statutes. In addition the appellant pleaded that certain claims were purchased by the appellee without ascertaining whether they had been filed in accordance with the Mechanic’s Lien Statute; that, further, deeds of trust and chattel mortgages were taken by the appellee from Humphries to secure the appellee against a loss; and that appellee by reason of its actions was in law estopped to deny its liability — that it had, in effect, waived absolute compliance with Article 5160 and had ratified and confirmed the appellant’s claim. The appellee filed a number of exceptions to the appellant’s pleading; all were sustained by the trial court. Thereafter, in a supplemental petition, the appellant again set up its claim for material furnished and further alleged that the contractor had abandoned the job and that the appellee, as surety, had taken over the building contract.

At the beginning of the trial, which was to a jury, Humphries stipulated that certain creditors — to wit, the appellant, Capitol Steel & Iron Company; Engineering Service, Inc.; Hillsdale Gravel Company; E. H. Sheldon & Company; and Frank Wallis Plastering Company — should recover judgment against him in the amounts of their respective claims. The trial thereafter proceeded only upon the claims of these same creditors against the appellee. After the appellant and the other claimants had rested, the appellee moved the court to withdraw the case from the jury or peremptorily to instruct the jury to find in its favor on the ground that the evidence was insufficient to raise an issue of fact as to whether on or about June 8, 1949, Hum-phries had abandoned his contract with the School District and the appellee had then taken over the job and completed the contract. Moreover, the appellee stated that the question of the validity of the mechanic’s lien claims filed by the claimants presented an issue of law and not one of fact. After the claimants agreed that the issue of the amount and validity of the mechanic’s liens should be withdrawn from the jury, the trial court sustained the appellee’s motion and on August 30, 1951, rendered judgment in favor of the claimants and against Humphries for the respective amounts of their claims, but the court decreed that none of them was entitled to recover anything against the appellee. From this judgment only the appellant, Capitol Steel & Iron Company, has perfected an appeal to this court.

The appellant contends that since there were facts from which the jury could have found that Humphries abandoned his contract and that the construction of the building was taken over by the appellee, the court erred in granting a motion for an instructed verdict. The appellant insists that the proffered evidence shows that the appellee paid for some of the labor and materials and moreover took a deed and chattel mortgage on Humphries’ property.

“Abandonment” is principally a matter of intention which must be established by clear and satisfactory evidence. *741 Humble Oil & Refining Co. v. Cook, Tex.Civ.App., 215 S.W.2d 383, 384. The abandonment of a contract is a matter of intent. Lohn v. Fletcher Oil Co., 38 Cal.App.2d 26, 100 P.2d 505, 507; Pearson v. Black, Tex.Civ.App., 120 S.W.2d 1075. In Mood v. Methodist Episcopal Church South, Tex.Civ.App., 289 S.W. 461, 464, it is said: “To constitute abandonment of contract by conduct, the acts relied upon must be positive, unequivocal and inconsistent with the existence of the contract.”

It appears that on May 30, 1949, after learning that Humphries was not paying his bills promptly, R. G. Burchell, an employee of the appellee in its bond claim department, came to Levelland and made an investigation which resulted in several recommendations.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Vaughn v. State
456 S.W.2d 879 (Court of Criminal Appeals of Tennessee, 1970)
Wiseman Hardware Co. v. R. L. King Construction Co.
387 S.W.2d 79 (Court of Appeals of Texas, 1965)
Maryland Casualty Co. v. Barron-Britton, Inc.
327 S.W.2d 769 (Court of Appeals of Texas, 1959)

Cite This Page — Counsel Stack

Bluebook (online)
299 S.W.2d 738, 1952 Tex. App. LEXIS 2246, Counsel Stack Legal Research, https://law.counselstack.com/opinion/capitol-steel-iron-co-v-standard-accident-insurance-co-texapp-1952.