Harris County Water Control and Improvement District No. 89 v. Philadelphia Indemnity Insurance Company

CourtDistrict Court, S.D. Texas
DecidedJune 1, 2020
Docket4:19-cv-01755
StatusUnknown

This text of Harris County Water Control and Improvement District No. 89 v. Philadelphia Indemnity Insurance Company (Harris County Water Control and Improvement District No. 89 v. Philadelphia Indemnity Insurance Company) is published on Counsel Stack Legal Research, covering District Court, S.D. Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Harris County Water Control and Improvement District No. 89 v. Philadelphia Indemnity Insurance Company, (S.D. Tex. 2020).

Opinion

IN THE UNITED STATES DISTRICT COURT June 01, 2020 FOR THE SOUTHERN DISTRICT OF TEXAS David J. Bradley, Clerk HOUSTON DIVISION

HARRIS COUNTY WATER CONTROL § AND IMPROVEMENT DISTRICT NO. 89, § § Plaintiff, § § v. § CIVIL ACTION NO. H-19-1755 § PHILADELPHIA INDEMNITY § INSURANCE COMPANY, § § Defendant. §

MEMORANDUM AND OPINION Harris County Water Control and Improvement District No. 89 sued E&M Enterprises, Inc. and Philadelphia Indemnity Insurance Company in state court, alleging that E&M breached its March 2016 Agreement to build the District’s administrative building and related facilities by constructing them improperly and failing to make the progress the Agreement required. (Docket Entry No. 1-B). The District alleges that the March 2016 Agreement also required E&M to provide a payment bond and a performance bond issued by a surety company and that Philadelphia issued both bonds, naming E&M as principal and the District as obligee. (Id. at ¶¶ 9, 10, 12). The District asserted claims for breach of contract and breach of warranty against E&M and claims for breach of contract and breach of the performance bond obligations against Philadelphia. (Id. at ¶¶ 14, 25– 26). Although E&M consented to Philadelphia’s removal to federal court, it did not file an answer or otherwise defend. This court entered default against E&M in July 2019. (Docket Entry No. 14). The District and Philadelphia have cross-moved for partial summary judgment on three issues: (1) whether Philadelphia’s performance bond obligations are enforceable under the March 2016 Agreement; (2) whether the construction project was abandoned and the one-year statute of limitations has already passed; and (3) whether there are genuine factual disputes material to determining Philadelphia’s affirmative defenses of assumption of the risk, contributory negligence, damages that not recoverable under the bond, and release. Based on the complaint, the motions and responses, the summary judgment record, and the

applicable law, the court grants Philadelphia’s motion in part and denies it in part, and grants the District’s motion in part and denies it in part. The court finds, based on the undisputed facts or disputed facts resolved in the nonmovant’s favor for the purpose of this motion, that, as a matter of law: (1) Philadelphia is not required to perform its performance bond obligations because it did not assent to the 2016 Agreement;

(2) the construction project was not abandoned as of April 2018 and the one-year statute of limitations has not passed;

(3) Philadelphia’s affirmative defense that damages are not recoverable under the bond is legally relevant to this dispute, but the affirmative defenses of assumption of the risk, contributory negligence, and release are not available.

In sum, Philadelphia is not required to perform under the 2016 Agreement, the statute of limitations has not passed, and Philadelphia may continue to claim that damages are not recoverable under the performance bond. The reasons for these rulings are set out below. I. Background Starting in September 2015, Harris County Water Control and Improvement District No. 89 entered into several agreements with E&M Enterprises, Inc. to construct the District’s administrative building and related facilities. (Docket Entry No. 1-2 at ¶ 8; see also Docket Entry Nos. 32-4, 32-5). The agreements required E&M to provide the District with a payment bond and a performance bond issued by a surety company. (Docket Entry No. 1-2 at ¶ 9). Philadelphia Indemnity Insurance Company agreed to issue both bonds, naming E&M as principal and the District as obligee. (Id. at ¶¶ 10, 12; see also Docket Entry Nos. 32-4, 32-5). On September 18, 2015, E&M signed a “NOTICE OF AWARD” from the District to construct the “WCID 89” administration building for $1,380,055.16. (Docket Entry No. 32-4).

This Notice of Award, according to Philadelphia, was accompanied by a “SECTION 005100 AGREEMENT” for the “WCID 89 Administration Building.” (Docket Entry No. 32-5). The 2015 SECTION 00510 Agreement stated that “the form of agreement to be used for the contract for construction shall be AIA A-105-2007” and “AIA A-201-2007,” both standard documents issued by the American Institute of Architects. (Id.).1 The 2015 Agreement also stated that that these “two [AIA] documents, together with the Bid Documents consisting of the Project Manual and the drawings shall make up the Contract for Construction.” (Id.). In March 2016, the District and E&M executed another “SECTION 00510 AGREEMENT.” (Docket Entry No. 32-7 at 1). The March 2016 Agreement was “binding upon all parties hereto” and required E&M to finish the project in 270 calendar days. (Id.). Although

the total cost remained $1,380,055.16, the 2016 Agreement did not require E&M to use specific standard documents, including the AIA A-105-2007 and AIA A-201-2007. (Id.). The 2016 Agreement named both E&M and the District, but, also unlike the 2015 Agreement, it did not name or mention Philadelphia, surety agreements, or the performance bond. In July 2017 and after alleged construction mishaps, the District sent a “Notification of non-compliance” to E&M and Philadelphia. (Docket Entry No. 32-12 at 2). In April 2018, the District informed E&M and Philadelphia by letter that E&M had “failed to make any substantial

1 The American Institute of Architects “publishes industry standard documents for design and construction projects . . . to establish a common basis for the primary and secondary relationships on the typical construction project.” In re D. Wilson Constr. Co., 196 S.W.3d 774, 777 (Tex. 2006) (citations omitted). progress on the project” and complained that “[t]he site has been abandoned since the last payment was made in February 2018.” (Docket Entry No. 32-12 at 3–4). The letter stated that “E&M does not have the resources or manpower to complete this project as bid.” (Id. at 4). E&M responded by a letter stating that it “ha[d] not abandoned this project,” and that it “had a project manager on

site meeting with subcontractors.” (Docket Entry No. 34-6 at 3). E&M claimed that it had “completed 75[ ]percent of the project.” (Id.). In August 2018, the District terminated E&M under the 2016 Agreement for default, alleging that E&M had failed to perform. (Docket Entry No. 1-2 at ¶ 16). The District sued in state court in April 2019, alleging that E&M had failed to make adequate progress on the project and had failed to properly perform its contractual duties. (Docket Entry No. 1-2). The District asserted breach-of-contract and breach-of-warranty claims against E&M, and breach-of-contract and performance-bond claims against Philadelphia. (Id. at ¶¶ 25–26). While E&M consented to Philadelphia’s removal to federal court, it did not file an answer or otherwise defend, and this court granted the District’s request for entry of default against E&M in July 2019. (Docket Entry No.

14). The District then moved for default judgment, (Docket Entry No. 18), which this court denied. (Docket Entry No. 23).2 Both the District and Philadelphia later filed motions for summary judgment. (Docket Entry Nos. 31, 32). The District argues that Philadelphia failed to offer or point to record evidence supporting its affirmative defenses of assumption of the risk, contributory negligence, damages not recoverable under the bonds, and release. (Docket Entry No. 31). Philadelphia argues that it was not bound by the District’s 2016 Agreement with E&M because, as a surety, it did not consent

2 The court found that the District has not submitted evidence showing that E&M had been properly served with the default judgment motion by certified as required by Local Rule 5.5. (Docket Entry No. 23 at 3).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Duffie v. United States
600 F.3d 362 (Fifth Circuit, 2010)
In Re D. Wilson Const. Co.
196 S.W.3d 774 (Texas Supreme Court, 2006)
Kendziorski v. Saunders
191 S.W.3d 395 (Court of Appeals of Texas, 2006)
Geters v. Eagle Insurance Co.
834 S.W.2d 49 (Texas Supreme Court, 1992)
Capitol Steel & Iron Co. v. Standard Accident Insurance Co.
299 S.W.2d 738 (Court of Appeals of Texas, 1952)
New Amsterdam Casualty Co. v. Bettes
407 S.W.2d 307 (Court of Appeals of Texas, 1966)
Scalise v. McCallum
700 S.W.2d 682 (Court of Appeals of Texas, 1985)
State v. Alpha Oil and Gas, Inc.
747 S.W.2d 378 (Texas Supreme Court, 1988)
Gregory Willis v. Cleco Corporation
749 F.3d 314 (Fifth Circuit, 2014)
Tolan v. Cotton
134 S. Ct. 1861 (Supreme Court, 2014)
Pioneer Exploration, L.L.C. v. Steadfast Insurance
767 F.3d 503 (Fifth Circuit, 2014)
Randy Austin v. Kroger Texas, L.P.
465 S.W.3d 193 (Texas Supreme Court, 2015)

Cite This Page — Counsel Stack

Bluebook (online)
Harris County Water Control and Improvement District No. 89 v. Philadelphia Indemnity Insurance Company, Counsel Stack Legal Research, https://law.counselstack.com/opinion/harris-county-water-control-and-improvement-district-no-89-v-philadelphia-txsd-2020.