Reliance Insurance Company of Philadelphia, Pennsylvania v. Malcolm B. Colbert

365 F.2d 530, 124 U.S. App. D.C. 339, 1966 U.S. App. LEXIS 5478
CourtCourt of Appeals for the D.C. Circuit
DecidedJuly 18, 1966
Docket19680_1
StatusPublished
Cited by13 cases

This text of 365 F.2d 530 (Reliance Insurance Company of Philadelphia, Pennsylvania v. Malcolm B. Colbert) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Reliance Insurance Company of Philadelphia, Pennsylvania v. Malcolm B. Colbert, 365 F.2d 530, 124 U.S. App. D.C. 339, 1966 U.S. App. LEXIS 5478 (D.C. Cir. 1966).

Opinions

McGOWAN, Circuit Judge:

The District Court, after trial without a jury, gave judgment for $18,374 against a defaulting contractor and the surety upon a completion bond. Only the surety has appealed, contending that material alterations were made in the construction contract without its knowledge and consent. We disagree with the District Court’s conclusion that these alterations were of such a nature as to have no ponderable impact upon the surety’s undertaking; and we reverse and remand for a determination of what that impact was.

I

Appellees are a group of church trustees who decided to build a Sunday School Annex. They executed a contract with a builder on October 20, 1962, and, on November 3 following, two addenda, the first enlarging the scope of the work to be done and the second fixing a total contract price and a payment schedule. Addendum No. 2 obligated the owner to reimburse the contractor for the full cost of a completion bond “at the time of delivery” of such bond. The contractor thereafter went to appellant surety company which, on November 21, 1962, issued and turned over to the contractor a completion bond. The bond remained in the possession of the contractor until after the execution of Addendum No. 3 on February 4, 1963.1 Addendum No. 3 altered the payment schedule in several respects. Construction was eventually abandoned before the building was fin[532]*532ished. Appellant surety refused the demand to complete, and this suit followed.

The District Court found, among other things, that the church had in substance been victimized by the contractor; that the architect employed by the church had been grossly negligent in giving his approval to the work performed by the contractor; and that the value of the materials and labor contributed by the contractor did not exceed $6,251. It arrived at its judgment of damages by this formula:

Amount of Contract $57,450.00

Deduct value of work done 6,251.00 Cost to complete $51,199.00

Deduct unpaid contract price 32,825.00

$18,374.00

The District Court both found as a fact and concluded in law that the changes in the contract wrought by Addendum No. 3 “were not so substantial vis-a-vis the Bonding Company as to affect its security”; and that the surety “must be held to a strict accounting,” since there had “been no changes in the contract which materially changed its position vis-a-vis the obligee * * *.” The District Court also appeared to conclude that the surety was, in essence, es-topped from relying upon Addendum No. 3 as constituting an alteration in the contract to which its bond was addressed. This latter position is embodied in a finding “that whatever obligation to give notice to the Bonding Company may have existed rested only upon the defendant Construction Company which had received but had failed to deliver the bond to the church until it had secured the signature of the Church to Addendum No. 3. The Church in other words had no knowledge of the bond until after Addendum No. 3 was signed.”

II

We turn first to the justification for the judgment derived from the estoppel alternative. The Church Trustees argued to us in this regard that “the bonding company made possible the overreaching of the Church by placing in the hands of the Construction Company an executed bond, and the bonding company must have known that that bond would cause the Trustees of the Church to feel secure * * This argument is curiously at odds with the District Court’s purported finding of fact that the Church “had no knowledge of the bond until after Addendum No. 3 was signed.” We have examined the record ourselves and we think the testimony does not support the finding literally.2 The finding may perhaps be interpreted to mean that appellees did not actually see the bond, as distinct from knowing of its existence, at the time they executed Addendum No. 3; and the testimony was not adduced with such clarity as to ex-[533]*533elude this possibility. Indeed, the finding must be read in this non-literal way in order to make it at all compatible with the theory of estoppel argued to us by appellees, namely, that the surety should not have given the bond to the contractor for ultimate delivery to the Church; and that, by doing so, the surety made it possible for the contractor to overreach the trustees by representing its possession of the bond to the trustees as an inducement to sign Addendum No. 3.

In our view of the estoppel argument, it is hot critical whether appellees actually saw the bond or merely knew of its existence. Had appellees been given, or had they insisted upon, an opportunity to look at the bond, they would have found nothing in it authorizing future changes in the contract without notice to the obligor.3 But, even if they had not seen the bond itself, they tell us in so many words that, because they knew of its availability in the contractor’s hands, they could safely rely upon his representations that they would be protected by it even though they were to go ahead with a material alteration in the contract without notice to the surety. Although appellees, unfortunately, appear not to have been sophisticated men of business, they cannot reasonably have assumed that bonding companies customarily issue substantial completion bonds which are open-ended in relation to the terms of the contracts guaranteed. All that appellees were entitled to assume from bare knowledge of the existence of the bond was that it covered the contract in the form the latter was in as of the time the bond was issued, and not as it was about to be changed. The mere fact that the bond was in the contractor’s possession does not enlarge the range of that assumption to include an apparent authority in the contractor to extend the bond’s coverage to any new and different contract that might be made. Actual authority to bind the surety was, accordingly, necessary, and none has been proved.

Thus, even if appellees did not see the bond, such overreaching as caused them to execute Addendum No. 3 flowed from their readiness to rely upon whatever the contractor told them. But the coverage of the bond in fact is not to be defined by reference to those representations, absent an adequate basis for regarding them as binding upon appellant. Mere possession of the bond by the contractor affords no such basis, particularly where, as here, the contract provisions relating to the bond are not inconsistent with a conclusion that appellees contemplated that the bond would be procured in the first instance by the contractor. Thus, appellant was not es-topped from showing what the coverage of the bond actually was.4

Ill

We return to the first — and primary— ground advanced by the District Court, i. e., its conclusion that the alterations made by Addendum No. 3 were not material in relation to the risk assumed by the surety. The payment schedule con[534]*534tained in the contract before the advent of Addendum No. 3 called for an initial deposit of $7,450, and for successive payments of $12,500 upon completion of certain described phases of the construction. The comparative payment schedules provided by Addendum No. 2 and Addendum No. 3 are as follows:

Addendum No. 2 Addendum No. 3
Initial Deposit $ 7,450 $ 7,500
Completion of first floor shell to joists 12,500 10,000

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lumbermens Mutual Casualty Co. v. United States
654 F.3d 1305 (Federal Circuit, 2011)
John T. Callahan & Sons, Inc. v. Dykeman Electric Co.
266 F. Supp. 2d 208 (D. Massachusetts, 2003)
Mergentime Corp. v. Washington Metropolitan Area Transit Authority
775 F. Supp. 14 (District of Columbia, 1991)
Zuni Construction Co. v. Great American Insurance
468 P.2d 980 (Nevada Supreme Court, 1970)
The Len Company and Associates v. The United States
385 F.2d 438 (Court of Claims, 1967)

Cite This Page — Counsel Stack

Bluebook (online)
365 F.2d 530, 124 U.S. App. D.C. 339, 1966 U.S. App. LEXIS 5478, Counsel Stack Legal Research, https://law.counselstack.com/opinion/reliance-insurance-company-of-philadelphia-pennsylvania-v-malcolm-b-cadc-1966.