Gibbs v. Hartford Accident & Indemnity Co.

62 So. 2d 599, 1952 Fla. LEXIS 1918
CourtSupreme Court of Florida
DecidedDecember 19, 1952
StatusPublished
Cited by21 cases

This text of 62 So. 2d 599 (Gibbs v. Hartford Accident & Indemnity Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Florida primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Gibbs v. Hartford Accident & Indemnity Co., 62 So. 2d 599, 1952 Fla. LEXIS 1918 (Fla. 1952).

Opinion

62 So.2d 599 (1952)

GIBBS
v.
HARTFORD ACCIDENT & INDEMNITY CO.

Supreme Court of Florida, Division A.

December 19, 1952.
Rehearing Denied February 5, 1953.

Turnbull & Pepper, Tallahassee, for appellant.

LeRoy Collins, of Ausley, Collins & Truett, Tallahassee, for appellee.

HOBSON, Justice.

Appellant, Robert Louis Gibbs, being desirous of building a home on a lot which he owned in Betton Hills, Tallahassee, Florida, entered into a contract with one Boyd L. Jones, Jr., a building contractor. Jones agreed, for a consideration of $27,000, to construct a dwelling house for Gibbs according to certain designated plans and specifications and Gibbs agreed to make payment to Jones for his services under the contract in the following manner:

"The owner shall make the payment of $1,500.00 upon the completion of the footings, foundation, and the brickwork to floor level, balance of the $27,000.00, that is the remaining $25,500, to be paid after the said house has been fully and completely constructed and has been approved and accepted by the owner and has been approved by the Federal Housing Authority and *600 upon closing of the loan to the owner; it being the intention of the parties that the contract shall be paid from the proceeds of the loan."

The contract between the owner and the contractor further provides:

"Article 10. Owner's Right To Terminate the contract should the Contractor neglect to prosecute the work properly, or fail to perform any provision of the contract, the Owner, after seven days' written notice to the Contractor, may without prejudice to any other remedy he may have, make good the deficiencies and may deduct the cost thereof from the payment then or thereafter due the Contractor or, at his option, may terminate the contract and take possession of all materials, tools, and appliances and finish the work by such means as he sees fit, and if the unpaid balance of the contract price exceeds the expense of finishing the work, such excess shall be paid to the contractor, but if such expense exceeds such unpaid balance, the Contractor shall pay the difference to the Owner."

Upon Gibbs' demand, Jones furnished appellant with a contract performance bond. Hartford Accident & Indemnity Company, appellee herein, is the compensated surety upon said bond. The bond expressly provides that the building contract is a part thereof by reference.

The obligation of said performance bond is,

"* * * if the Principal shall faithfully perform the contract on his part, and shall fully indemnify and save harmless the Obligee from all cost and damage which the Obligee may suffer by reason of failure so to do and shall fully reimburse and repay the Obligee all outlay and expense which the Obligee may incur in making good any such default, and shall pay all persons who have contracts directly with the Principal for labor or materials, then this obligation shall be null and void, otherwise it shall remain in full force and effect."

Within less than a month after Jones had started construction of the one-family dwelling he reported to Gibbs that he was unable to proceed with the construction unless he were given financial assistance, whereupon Gibbs secured a loan of $20,000 from the Lewis State Bank of Tallahassee and executed a mortgage in which he pledged the property, upon which construction of the dwelling house was in progress, as security for the repayment of said loan. Thereafter, as work progressed on the building disbursements were made by the Bank to Jones. The Bank made such investigation and inspection of the progress of construction as it deemed necessary for its own protection. Payments were made by the Bank at the following times and in the amounts stated:

  Feb.  11, 1950    $3,000.00
  Feb.  24, 1950    $2,000.00
  March  3, 1950    $4,500.00
  March 28, 1950    $1,500.00
  April  1, 1950    $3,000.00
  April 10, 1950    $1,000.00
  April 14, 1950    $3,000.00
  April 25, 1950    $1,937.00
                   __________
                   $19,937.00

Jones was paid by Gibbs $4,000 in addition to the above sums of money.

Subsequently, after Jones had failed properly to perform the contract and correct the work which allegedly was not properly done, Gibbs paid out $10,863 to laborers and materialmen who had liens against his home and then completed the construction of the building without the services of Jones.

Extras amounting to $1,428.25 were agreed upon by Jones and Gibbs after construction had been commenced and in accordance with the provisions of the construction contract. Before the owner took over and completed the construction he expended $23,937.20. It became necessary for the owner to pay out an additional $22,812 which made the total cost, in order to make the building conform with the contract, the sum of $46,749.20. Thus it may be seen that a loss was sustained either by appellant or appellee of $18,320.85.

*601 Appellant sued appellee and as a basis for such suit alleged that the principal (Jones) failed properly to perform the contract. Appellee defended upon the ground that appellant's failure to make payments as provided for in the construction contract and in making a new arrangement whereby he made prepayments departed so materially from the original contract as to completely relieve and discharge appellant as surety on the performance bond.

Defendant filed a motion for summary judgment. Affidavits were filed by both parties litigant. After a hearing upon the motion the learned Circuit Judge decided:

"This is an appropriate case for the determination of the issues on this defense by a motion for summary judgment because there is no material controversy over the facts, and the issue is primarily one of law."

He further determined that he should, and he did, enter a judgment in favor of appellee.

In a scholarly thesis the able Circuit Judge traced the history of the law, as it has been applied to sureties under circumstances similar to those in the instant case, from the early days of the common law down to the current period of modernity. It is true that under the common law a surety was considered to be a favorite of the law and even minor changes in, or departures from, the principal contract were held to discharge the surety. We need not dwell at length upon the rule of strictissimi juris because it has been discarded by most American Courts and certainly it is no longer applied in this jurisdiction. Moreover, counsel for appellee state in their brief, "We do not need or seek the shelter of a rule of strictissimi juris in the denial of liability * * *." It appears that the theory underlying this strict rule of construction was primarily the fact that in olden days a compensated surety was almost unknown. Consequently, the law was lenient toward and inclined to favor a surety who was an accommodation party.

However, along about the turn of the century, individuals, and later corporations formed for profit, began the business of becoming compensated sureties. Because of such mutation it became advisable, if not necessary, to change the philosophy of the law in order to keep pace with ever-changing conditions and thereby accomplish substantial justice.

There is a lack of unanimity of opinion, however, among the courts of today with reference to the question what conditions and circumstances attendant upon premature payment to the contractor will discharge the surety upon the latter's performance bond.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hartford Casualty Insurance v. City of Marathon
825 F. Supp. 2d 1276 (S.D. Florida, 2011)
Hartford Cas. Ins. Co. v. CITY OF MARATHON
825 F. Supp. 2d 1276 (S.D. Florida, 2011)
Armstrong Business Services, Inc. v. AmSouth Bank
817 So. 2d 665 (Supreme Court of Alabama, 2001)
United States v. Continental Casualty Company
512 F.2d 475 (Fifth Circuit, 1975)
United Bonding Ins. Co. v. Southeast Reg. Bldrs., Inc.
236 So. 2d 460 (District Court of Appeal of Florida, 1970)
EE Rabalais & Son, Inc. v. United Bonding Ins. Co.
226 So. 2d 528 (Louisiana Court of Appeal, 1969)
Equitable Fire & Marine Insurance Co. v. Tiernan Building Corporation
190 So. 2d 197 (District Court of Appeal of Florida, 1966)
Southern Gulf Utilities, Inc. v. United Benefit Fire Insurance
179 So. 2d 618 (District Court of Appeal of Florida, 1965)
Harrison v. American Fire & Casualty Co.
163 So. 2d 324 (District Court of Appeal of Florida, 1964)
Sproul Construction Co. v. St. Paul Fire & Marine Insurance
389 P.2d 194 (New Mexico Supreme Court, 1964)
Maule Industries, Inc. v. Gaines Construction Co.
157 So. 2d 835 (District Court of Appeal of Florida, 1963)
Gruman v. Sam Breedon Construction Co.
148 So. 2d 759 (District Court of Appeal of Florida, 1963)
Rowe v. Stufflebeam
89 N.W.2d 875 (Supreme Court of Iowa, 1958)
Pan American Surety Co. v. Board of Public Instruction
99 So. 2d 890 (District Court of Appeal of Florida, 1958)

Cite This Page — Counsel Stack

Bluebook (online)
62 So. 2d 599, 1952 Fla. LEXIS 1918, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gibbs-v-hartford-accident-indemnity-co-fla-1952.