Hartford Casualty Insurance v. City of Marathon

825 F. Supp. 2d 1276, 2011 U.S. Dist. LEXIS 133511
CourtDistrict Court, S.D. Florida
DecidedNovember 18, 2011
DocketCase No. 10-10077-CV
StatusPublished
Cited by1 cases

This text of 825 F. Supp. 2d 1276 (Hartford Casualty Insurance v. City of Marathon) is published on Counsel Stack Legal Research, covering District Court, S.D. Florida primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hartford Casualty Insurance v. City of Marathon, 825 F. Supp. 2d 1276, 2011 U.S. Dist. LEXIS 133511 (S.D. Fla. 2011).

Opinion

DECLARATORY DECREE GRANTING FINAL SUMMARY JUDGMENT TO HARTFORD CASUALTY INSURANCE COMPANY

JAMES LAWRENCE KING, District Judge.

THIS MATTER comes before the Court upon Plaintiff Hartford Casualty Insurance Company’s and Defendant City of Marathon’s cross motions for summary judgment. (Marathon’s Mo. for Sum. J., DE # 31; Hartford’s Mo. for Sum. J., DE #42). The Court is fully briefed,1 and proceeds with the benefit of extensive oral argument.2 Upon careful consideration of the arguments set forth in the Motions and at oral argument, the Court finds that Plaintiff Hartford Casualty Insurance Company is entitled to summary judgment.

I. Background3

In or around 2007, the Defendant City of Marathon (“Marathon”), a municipality located in Monroe County, Florida, planned and initiated the construction of a series of wastewater treatment facility projects at various geographic locations throughout the city, referred to as the Marathon advanced wastewater treatment system (“AWTS”). The AWTS was divided into seven “service areas.” The above-styled action concerns the service areas known as Service Area 3 and Service Area 7.

[1279]*1279On February 12, 2009, Defendant Intrastate Construction Corp. (“Intrastate”), a construction company incorporated under the laws of Florida, submitted its bid for the Area 3 Project. (Intrastate Area 3 Bid, DE #37-3). Intrastate submitted a total bid of $4,609,000, which incorporated Intrastate’s unique construction base bid of $2,061,000.00, as well as the set third-party base equipment bid of $2,548,00.00. (Thomas Dep., at 11:14-25, DE #39-1). Intrastate’s $2,061,000.00 construction bid was recommended and determined to be the lowest responsive and responsible bidder for the Area 3 Project. (Thomas Dep., at 12:4-15, DE # 39-1).

On or about April 14, 2009, Intrastate and Marathon entered into a contract for the construction of the Area 3 Wastewater Treatment Facility in the amount of $2,061,000.00, entitled the City of Marathon Service Area 3 Wastewater and Stormwater Project (“Area 3 Construction Contract” or “underlying construction contract”). (Area 3 Construction Contract ¶¶1.1, 4.1, DE #35-1). The Contract enumerates that “[t]he Work is generally described as the following: the City of Marathon Service Area 3 Wastewater Treatment Facility. The project consists of constructing tanks, buildings, and installing wastewater treatment and plumbing facilities, complete, in place, all in accordance with the construction drawings and technical specifications.” (Area 3 Construction Contract ¶ 1.1, DE # 35-1).

On or about June 3, 2009, Plaintiff Hartford Casualty Insurance Company (“Hartford”) issued statutory performance and payment bonds for the Area 3 Project under bond number 35 BCSFD 6127 (the “Bonds”). (Bonds, DE # 35-3). Hartford executed the bonds through its then-attorney-in-fact, S.P. Humenchick. (Bonds, DE #35-3, at 5). The Area 3 Performance Bond, issued in favor of Marathon, guaranteed Intrastate’s performance on the contract entitled, City of Marathon Service Area 3 Wastewater and Stormwater Project. (Area 3 Performance Bond, DE # 35-3, at 1). The Area 3 Payment Bond guaranteed payment to Intrastate’s subcontractors, sub-subcontractors, laborers, and materialmen on the contract entitled, City of Marathon Service Area 3 Wastewater and Stormwater Project. (Area 3 Payment Bond, DE # 35-3, at 7).

On August 3, 2009, Marathon issued to Intrastate its “Certification of Contractor’s Insurance and Bonding,” certifying that Intrastate had obtained insurance, and payment and performance bonds from Hartford in the amount of $2,061,000.00 for the project identified as the “Service Area 3 Wastewater Treatment Plant.” (Certification, DE # 39-2, at 13). On August 5, 2009, as a result of having received the insurance and bonding information from Intrastate, Marathon issued to Intrastate a Notice to Proceed on the Area 3 Project. (Area 3 Notice to Proceed, DE # 39-2, at 14; Thomas Dep., at 20:22-21:6, DE # 39-1).

Eight months later, in April 2010, Intrastate’s subcontractors and suppliers began filing Notices of Nonpayment with Hartford and Marathon. (Mahler Aff. ¶ 12, DE #40-1). Then, on April 14, 2010, Intrastate contacted Hartford to inform Hartford of Intrastate’s insolvency and need for financial assistance to complete various bonded projects, including the Area 3 Project. (Mahler Aff. ¶ 10, DE # 40-1).

Later that month, on or about April 27, 2010, Intrastate and Marathon executed a document entitled Change Order No. 1 to “provide the same type of services to build another treatment plant,” known as the Area 7 Wastewater Treatment Facility Project (“Area 7 Change Order”). (Area 7 Change Order, DE # 35^4; Thomas Dep., at 21:7-16, DE #39-1). The Area 7 [1280]*1280Change Order did not modify the plans for the Area 3 Project. (Thomas Dep., at 40:18-25, DE # 39-1). Rather, the Area 7 Project was to proceed under a completely separate set of plans and specifications. (Thomas Dep., at 40:18-25, DE # 39-1).

The Area 7 Project was to be constructed at a project site located on Grassy Key, approximately 5.5 miles away from the Area 3 Project. (Thomas Dep., at 41:3-5, DE # 39-1). The timeline for completing the Area 7 Project was independent of the timeline for completing the Area 3 Project. (Thomas Dep., at 44:19-45:7, DE # 39-1). In addition, the Area 7 Project came at an added cost of $2,984,487.00 to the underlying construction contract. (Area 7 Change Order, DE # 35-^4). Ultimately, the Area 7 Change Order increased the bonded contract amount from $2,061,000.00 to $5,045,-487.00 — an increase of over 144 percent of the original contract sum. (Area 7 Change Order, DE# 35-4).

For the Area 7 Project, Marathon issued a separate Notice to Proceed. (Thomas Dep., at 44:9-18, DE # 39-1; Area 7 Notice to Proceed, DE # 39-3, at 2). Pursuant to the terms of the Notice to Proceed, Intrastate was required to provide additional performance and payment surety in the amount of $2,984,487.00.4 (Area 7 Notice to Proceed, DE # 39-3, at 2).

On June 30, 2010, Hartford informed Marathon by letter that it had not and would not bond the Area 7 Change Order and thereby extend the value of its bond from $2,061,000.00 to $5,045,487.00. (DE # 35-6). Hartford, however, did not disavow that it was responsible for the $2,061,000.00 Area 3 Performance Bond. Nevertheless, on August 6, 2010, attorneys representing Marathon sent Hartford a letter titled “Notice of Default and Termination,” terminating Intrastate from its work on both the Area 3 Project and the Area 7 Project. (Aug. 6, 2010 Marathon Letter, DE #35-7). Marathon terminated Intrastate on both the Area 3 Project and the Area 7 Project because Hartford refused to bond the Area 7 Change Order. (Aug. 6, 2010 Marathon Letter, DE # 35-7; Thomas Dep., at 53:14-54:9, DE # 39-1). Intrastate performed no more work on the Area 3 Project and the Area 7 Project after the delivery of that letter.

On August 9, 2010, Hartford filed the instant action against both Marathon and Intrastate for declaratory relief seeking judgment from this Court declaring that: (i) the Area 7 Change Order was void ab initio for illegality; and (ii) that no bond issued by Hartford, including but not limited to bond number 35 BCSFH 6127, affords coverage for the Area 7 Change Order.5 (Compl., DE # 1). Hartford’s [1281]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hartford Cas. Ins. Co. v. CITY OF MARATHON
825 F. Supp. 2d 1276 (S.D. Florida, 2011)

Cite This Page — Counsel Stack

Bluebook (online)
825 F. Supp. 2d 1276, 2011 U.S. Dist. LEXIS 133511, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hartford-casualty-insurance-v-city-of-marathon-flsd-2011.