Public Service Electric & Gas Co. v. Technology for Energy Corp. (In Re Technology for Energy Corp.)

140 B.R. 214, 1992 Bankr. LEXIS 732, 1992 WL 103621
CourtUnited States Bankruptcy Court, E.D. Tennessee
DecidedMay 12, 1992
DocketBankruptcy No. 3-85-00455, Adv. No. 1-89-0266
StatusPublished
Cited by4 cases

This text of 140 B.R. 214 (Public Service Electric & Gas Co. v. Technology for Energy Corp. (In Re Technology for Energy Corp.)) is published on Counsel Stack Legal Research, covering United States Bankruptcy Court, E.D. Tennessee primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Public Service Electric & Gas Co. v. Technology for Energy Corp. (In Re Technology for Energy Corp.), 140 B.R. 214, 1992 Bankr. LEXIS 732, 1992 WL 103621 (Tenn. 1992).

Opinion

MEMORANDUM

RALPH H. KELLEY, Chief Judge.

The plaintiffs, Bechtel and Public Service, needed a radiation monitoring system for a nuclear power plant in New Jersey. Technology for Energy Corporation (TEC) agreed to build the system. The contract is made up of two purchase orders. For each purchase order, TEC obtained a payment and performance bond from American Insurance. Bechtel and Public Service brought this suit primarily to recover from American under the bonds.

The court and the parties agreed to divide the issues for trial. The first issue is whether American can be liable for more than the penal sums stated in the bonds. This is the court’s second opinion on this question. In an earlier opinion the court rejected all the arguments made by Bechtel and Public Service except one. This opinion deals with the remaining argument.

For convenience, the court will refer to the two purchase orders as one contract and the two bonds as one bond. The bonds are the same except that they refer to different purchase orders and have different penal sums. The court will refer to Bechtel and Public Service as Bechtel.

For the purpose of argument, the court assumes that TEC defaulted in its performance of the purchase orders. This brings the court to Bechtel’s remaining argument.

The penal sum equals the original contract price of about $3,900,000. Changes in the contract made the contract price increase to about $6,950,000. The bond waives notice of changes in the contract and provides that changes will not release American Insurance from liability under the bond. Bechtel argues that there is a custom of the trade under which the penal sum automatically increased from the original contract price to the much larger contract price that resulted from the changes.

Two kinds of evidence could be used to prove the alleged custom: (1) evidence that the surety business in general follows the alleged custom, and (2) evidence that American Insurance, until it denied liability, dealt with TEC and Bechtel as if the custom exists.

The court begins with basic rules and practices in the surety business. After that, the court takes up the testimony of individual witnesses.

Why does a contractor obtain a payment or performance bond from a surety company, and how does the contractor obtain it? The owner will require the contractor to *216 obtain a bond. The owner decides whether it wants the amount of the bond (the penal sum) to be 100% or 50% or some other percentage of the original contract price. Bonds on some government contracts are commonly 50% bonds.

The contractor will go to an insurance agent to obtain the bond. The insurance agent’s job is to help convince a surety company to issue the bond. The insurance agent gathers information a surety company will need to decide whether to issue the bond. For example, a surety needs to know whether the contract involves the kind of work the contractor has done in the past, whether the contractor has the capacity to do the amount of work called for by the contract, the present and past financial condition of the contractor, and the character and personal financial condition of the principals in the business. With this kind of information, the agent attempts to obtain the bond from a surety company.

The surety company’s underwriters use the information to decide whether the company should take the risk of issuing the bond. Underwriters consider a wide variety of information about the contractor and the contract.

When a surety issues a bond for a contractor, the contractor becomes one of the surety’s accounts. The surety may or may not make a separate underwriting decision on each contract for which the contractor requests a bond. The contractor’s account means all the bonds already issued for the contractor and its standing with the surety with regard to obtaining new bonds.

If the surety company decides to issue the bond, the surety company or the agent must collect the premium. A surety company must file its premium rates with the state insurance commission. In simplified terms, the surety calculates the original premium by multiplying the original contract price by the appropriate premium rate.

If the contract price goes up during the contractor’s performance of the contract, the surety is entitled to collect an additional premium from the contractor. The surety is entitled to more premium because the increase in the contract price indicates an increase in the surety’s risk of loss.

If the surety collects an additional premium when the contract price increases, the insurance agent is entitled to an additional commission.

The surety usually makes a final adjustment of the premium after the contract is completed. The surety is entitled to more premium if the final cost is more than the original contract price, and the contractor is entitled to a refund if the final cost is less than the original contract price. Small adjustments may be ignored. For example, the surety may not charge or refund a premium of less than $50.

The bond itself does not say anything about the premium. It does not tell how the original premium is calculated. It does not say that the contractor will be liable for more premium if the contract price goes up. It does not say that the contractor will be entitled to a refund if the final contract price is less than the original contract price.

The contractor generally does not submit a written bond application that might include a promise to pay the premium.

There appear to be two sources for the surety’s right to collect the premium. First is the bond rate manual. Second is the indemnity agreement between the surety and the contractor.

The bond rate manual is a standard manual used by sureties to calculate premiums. It explains how to calculate the original premium and how the premium is affected by increases and decreases in the contract price.

The indemnity agreement requires more explanation. Between the surety and the contractor, the bond is a credit transaction, not insurance. If the contractor defaults and surety pays the owner or completes the contract, the surety has a claim against the contractor. In legal jargon, the surety has a right to indemnity from the contractor. The surety may also have an indemnity agreement with third-party indemnitors, that is, indemnitors other than the contractor.

*217 One witness, who has many years experience in the business, testified that the general indemnity agreement between the surety and the contractor includes an agreement by the contractor to pay the bond premium.

The penal sum of the bond is usually 100% of the contract price, but this does not mean the premium is calculated on the penal sum. It is still calculated on the contract price. The premium for a bond is the same if the penal sum is 50% or 100% of the contract price.

The premium may be based on the penal sum when it is a small percentage of the contract price. For example, if the penal sum is only 20% of the contract price, then the penal sum may be used to calculate premium instead of the contract price.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hartford Casualty Insurance v. City of Marathon
825 F. Supp. 2d 1276 (S.D. Florida, 2011)
Hartford Cas. Ins. Co. v. CITY OF MARATHON
825 F. Supp. 2d 1276 (S.D. Florida, 2011)
Colorado Structures, Inc. v. Insurance Co. of the West
161 Wash. 2d 577 (Washington Supreme Court, 2007)

Cite This Page — Counsel Stack

Bluebook (online)
140 B.R. 214, 1992 Bankr. LEXIS 732, 1992 WL 103621, Counsel Stack Legal Research, https://law.counselstack.com/opinion/public-service-electric-gas-co-v-technology-for-energy-corp-in-re-tneb-1992.