Federal Surety Co. v. White

295 P. 281, 88 Colo. 238, 1930 Colo. LEXIS 323
CourtSupreme Court of Colorado
DecidedDecember 15, 1930
DocketNo. 12,153.
StatusPublished
Cited by9 cases

This text of 295 P. 281 (Federal Surety Co. v. White) is published on Counsel Stack Legal Research, covering Supreme Court of Colorado primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Federal Surety Co. v. White, 295 P. 281, 88 Colo. 238, 1930 Colo. LEXIS 323 (Colo. 1930).

Opinion

Mr. Justice Alter

delivered the opinion of the court.

R. A. White, defendant in error, hereinafter referred to as plaintiff, brought an action in the district court to recover judgment against the Federal Surety Company, a corporation, plaintiff in error, hereinafter referred to as defendant, and joined with it as codefendants, Ed. Lindsay and P. S. Dolan, doing business as Lindsay and Dolan, hereinafter referred to by name or as subcontractors. The subcontractors filed an answer admitting the allegations of the complaint, and the judgment rendered against them on their confession is not before us for review. Upon the issues being made between plaintiff and defendant, the court appointed a referee before whom the cause was heard. After many days consumed in taking testimony, the referee prepared an elaborate and detailed report containing his findings of fact, conclusions of law, orders and recommendations. The findings being generally in favor of plaintiff, defendant objected thereto, and filed its motion to set them aside, and for a new trial, specifying 108 objections to the referee’s re *240 port. The court overruled all the objections to the referee’s report, denied the motion for a new trial, and rendered judgment in favor of plaintiff and against defendant for the sum of $25,866.66, which judgment included $5,866.66 interest. To review this judgment, defendant prosecutes this writ, assigning 69 errors, which, for convenience in discussion, will be classified generally as follows: (1) The relationship of Albert W. Payne, Jr., and A. W. Payne Agency Company with defendant; (2) the release of defendant from all liability by acts of omission and commission of plaintiff and subcontractors; (3) the allowance of specific items of cost of construction against defendant; (4) the amount of the judgment.

The plaintiff was, on July 30, 1923, awarded a contract with the state of Colorado for the construction of two separate sections of concrete highway east of the city of Pueblo, which sections were officially designated as federal aid project No. 246-A; the agreed compensation to be paid plaintiff for the completed project, in accordance with the plans and specifications, was $78,431.10, which sum was payable in monthly installments upon estimates furnished by the engineer of the state highway department; it being expressly understood, and so stated in the original contract between plaintiff and the state, that only 85) per cent of the monthly estimate should be paid, and 15 per cent should be retained by the state of Colorado until the completion of the project. The plaintiff as principal, and the Aetna Casualty and Surety Company, as surety, executed a bond to the state of Colorado in accordance with the provisions of chapter 155, page 480, Session Laws of Colorado, 1923, which bond will hereinafter be referred to as the statutory bond.

The plaintiff and subcontractors, on August 10, 1923, entered into a written contract wherein the subcontractors undertook and agreed to perform some, if not all, of the work and services which plaintiff had formerly contracted with the state of Colorado to do; the contract between plaintiff and subcontractors being as follows:

*241 “Memoranda of Agreement.
“Memoranda of Agreement, by and between R. A. White of Denver, Colorado, of the first part, hereinafter designated as 'Contractor,’ and Ed Lindsay and P. S. Dolan, doing business as Lindsay & Dolan, hereinafter designated as the 'Sub-Contractors,’ Witnesseth, that:
“Whereas, the contractor has procured a contract to construct 2.5378 miles of concrete road beginning* about six miles east of Pueblo and extending* easterly via Santa Fe Trail to end near Vineland, Pueblo County, Colorado, known as Federal Aid Project No. 246-A, upon bid signed July 9, 1925, and contract signed by contractor and the State Highway Department of Colorado, and
“Whereas, the contractor is desirous of sub-letting-a portion of the work to the sub-contractors,
“Now, Therefore, in consideration of the mutual agreements hereinafter made, the sub-contractors agree to perform all of the services required of the contractor by his contract .with the State Highway Department, in full conformity with said contract, except that the subcontractors shall not be required to furnish any of the cement, but that the contractor will furnish all cement necessary for the work and deliver the same to the subcontractors f. o. b. Vineland, Colorado, at $2.74 per barrel net.
“It Is Understood and Agreed, that the said contract, which the sub-contractors agree to perform, consists of the contract proper signed by the contractor herein and by the State Highway Department, the notice to contractors, instructions to bidders, the contractors! proposals, and the plans and specifications on file in the office of the State Highway Department at Denver, Colorado, together with such alterations and modifications as may be made in accordance with the provisions thereof.
“The sub-contractors agree that they will receive any cement delivered at Vineland, Colorado, for said project and will properly care for any cement thus delivered, and in the event of the loss of cement after delivery, sub-con *242 tractors agree to replace the same; but it is distinctly understood and ag*reed that the sub-contractors assume no responsibility for the quality of cement delivered and in no way guarantee the same, but that it shall be the duty of the contractor to see that any cement delivered shall meet the full requirements of his contract with the State Highway Department.
“The estimate as to quantities by the project engineer in the employ of the State Highway Department shall be final as between the parties, hereto.
“In consideration of the services thus rendered by the sub-contractor the contractor agrees to collect from the State, from time to time, upon the estimates made by the State’s Engineer and to forthwith pay to the sub-contractors the amounts thus collected, provided that, where any such estimate shall include cement delivered on the job the contractor shall retain out of any payment made by the State Highway Department that proportion of the estimate which the cement thus delivered bears to the total amount of the estimate, the intention being that the contractor shall collect for all cement furnished by him in conformity with his contract with the State Highway Department, but that the contractor shall bear his proportionate share of any amounts withheld by the State.
“It Is Further Understood and Agreed, that the contractor is to withhold five per cent, of the total amount of the cost of the completed project to the State according' to' the contractor’s bid to the State Highway Department, as his share of the profits in said contract, but that said five per cent, shall not be withheld until final settlement with the State Highway Department is made and the final 15% paid by the State Highway Department; all other sums collected by the contractor from the State Highway Department on this project shall be paid to the sub-contractors except the amount due the contractor for cement furnished.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Brighton School District 27J v. Transamerica Premier Insurance Co.
923 P.2d 328 (Colorado Court of Appeals, 1996)
United Fireworks Manufacturing Co. v. Superior Court of Puerto Rico
96 P.R. 353 (Supreme Court of Puerto Rico, 1968)
United Fireworks Manufacturing Co. v. Tribunal Superior de Puerto Rico
96 P.R. Dec. 362 (Supreme Court of Puerto Rico, 1968)
National Union Fire Insurance v. Denver Brick & Pipe Co.
427 P.2d 861 (Supreme Court of Colorado, 1967)
Massachusetts Bonding & Insurance v. State Ex Rel. Mallin
347 P.2d 507 (Supreme Court of Colorado, 1959)
Schwartz v. District Court of Puerto Rico
73 P.R. 800 (Supreme Court of Puerto Rico, 1952)
Schwartz v. Tribunal de Distrito de Puerto Rico
73 P.R. Dec. 856 (Supreme Court of Puerto Rico, 1952)
American Surety Co. of N.Y. v. Noe
53 S.W.2d 178 (Court of Appeals of Kentucky (pre-1976), 1932)

Cite This Page — Counsel Stack

Bluebook (online)
295 P. 281, 88 Colo. 238, 1930 Colo. LEXIS 323, Counsel Stack Legal Research, https://law.counselstack.com/opinion/federal-surety-co-v-white-colo-1930.