Roberts v. Security Trust & Savings Bank

238 P. 673, 196 Cal. 557, 1925 Cal. LEXIS 340
California Supreme Court·Decided July 31, 1925·No. Docket No. L.A. 7909.·Published·Cited by 52 cases

Opinion

WASTE, J.

This is a companion appeal to that already considered by the court in Roberts v. Spires et al., 195 Cal. *561 267 [232 Pac. 708], It is therefore unnecessary to restate the facts set forth in that opinion. The lien claimants in the ease were awarded personal judgments against Roberts, the contractor, and the United States Fidelity & Guaranty Company, his surety upon the materialmen’s bond, for the full amounts of their respective claims, aggregating $40,791.41, which were adjudged to be liens upon the property of the owner. The judgment directed that the owner pay this sum of $40,791.41 to the lienholders out of the unpaid balance of the contract price due Roberts, amounting to $52,-295.56, and apply the balance of $11,504.15 toward the payment of her judgment in the sum of $36,211.35 for damages against Roberts, caused by his delay in completing the building and that she have and recover of and from the contractor and his surety the unpaid balance of her damages, amounting to $24,707.20, plus certain costs.

Mrs. Spires appealed from that portion of the judgment which required her to pay the lien claimants in full before deducting the whole amount'of her judgment for damages from the amount due the contractor. That judgment was affirmed. {Roberts v. Spires, supra.)

The United States Fidelity & Guaranty Company, as surety on the contractor’s bonds, appealed from the judgment upon the ground that the court erred (1) in awarding to the owner, and against it, any damages caused by the delay of the contractor in completing the building, and (2) in decreeing that the laborers and materialmen have direct judgments against the surety for the respective amounts of their claims, notwithstanding such claims were found to be a lien upon the owner’s property, when there remained in the hands of the owner more than enough of the contract price due to the contractor to pay and discharge all of such liens. The surety company, by an amendment to its answer to the cross-complaint of the owner, Mrs. Spires, who sought to recover damages caused by the delay of the contractor in completing the building, took the position that it had been released from all liability to the owner for the reason that during the progress of the work material provisions of the contract were disregarded and set at naught in that extra labor and materials were ordered and furnished by the contractor without the knowledge or consent of the surety company, and that no extension of time to be granted to *562 the contractor for completing the work in consequence of such extra work and materials was ever established, as required by the contract. It also alleged that a substantial 'part of such extra work and material was ordered and performed without any agreement having been reached between the owner and the contractor as to the amount to be paid therefor, and that the actual value of such extra labor and material was in excess of the sum of $11,000. It was also claimed that delays in the construction of the building, due to and caused by such extra and additional work, exceeded 120 days. Roberts, the contractor, in his answer to the cross-complaint of the owner, also alleged that he was delayed in the completion of his contract by extra and additional work required and ordered by the owner, but that the provisions of the contract invoked by appellant were waived by the owner and himself.

At the trial Roberts and appellant each sought to introduce evidence of the delay in the completion of the building, resulting from and necessitated by the performance of extra and additional work, beyond the time originally required by the contract. The owner objected, and the court sustained the objection. The contractor is not here on appeal, and we need consider the ruling of the court only in its effect on the cause of the surety. As to it, the objection to the introduction of the evidence was twofold: First, that the contractor and the owner had waived certain of the contract requirements, and, second, that the condition of the undertaking given by the surety company constituted an assent in advance to a departure from the terms of the building agreement, for the reason that the bond, by its terms, guaranteed the provisions of the contract, “or any modification thereof. ’ ’ Both views were adopted by the trial court. It construed the contract together with the bond, and held that the surety for the contractor must be deemed to have assented to a provision in the contract that, should the owner at any time during the progress of the work request any alterations, deviations, additions, or omissions from the contract, she should be at liberty to make such change or changes without in any way affecting or making void its terms. As a result of the court’s view, the judgment against the appellant surety company followed.

*563 The faithful performance bond executed by the appellant refers to the contract between Mrs. Spires, as owner, and Roberts, as contractor, and briefly describes the work to be done to complete the building in accordance with the plans and specifications “referred to in said contract, to which contract reference is” had. The contract, by reference having been made a part of the bond, the two instruments must be read together in order to determine the scope of appellant’s undertaking. (Smith v. Molleson, 148 N. Y. 241, 246 [42 N. E. 669, 671].) In consideration of the letting of the contract by Mrs. Spires to Roberts, appellant is, by the terms of the bond, held and firmly bound unto the owner in the sum of $47,500, or twenty-five per cent of the contract price. The condition of the obligation is that if the contractor shall well and faithfully keep and perform all of the covenants and agreements of the contract by him to be kept and performed, and shall turn over and deliver the structure according to the contract, free from all liens that may be filed or asserted by any and all persons who perform labor upon or furnish materials to be used in the work described in the contract, or in any modification thereof, and shall save and hold harmless the owner from any and all loss or damage arising out of the failure of the contractor to fulfill his contract, then the obligation to be void; otherwise to remain in full force and effect. There is a provision in the contract that, should the owner at any time during the progress of the work, require any alteration, deviation, addition to, or omission from, the contract, plans, or specifications, she should have the right and power to make such change or changes, and the same should “in no way injuriously affect or make void the contract,” but the difference for work omitted should be deducted from the amount of the contract by a fair and reasonable valuation, and for additional work required, the amount, based upon the market value of labor and material, should be agreed upon before commencing such additions, which agreement should state also the extension of time, if any, which was to be granted the contractor by reason thereof.

Free access — add to your briefcase to read the full text and ask questions with AI

Roberts v. Security Trust & Savings Bank, 238 P. 673, 196 Cal. 557, 1925 Cal. LEXIS 340 (Cal. 1925).

238 P. 673 (Roberts v. Security Trust & Savings Bank) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

St. Paul Fire & Marine Insurance v. City of Green River
93 F. Supp. 2d 1170 (D. Wyoming, 2000)
Cates Construction, Inc. v. Talbot Partners
980 P.2d 407 (California Supreme Court, 1999)
Pacific Employers Insurance v. City of Berkeley
158 Cal. App. 3d 145 (California Court of Appeal, 1984)
General Insurance Co. of America v. Commerce Hyatt House
5 Cal. App. 3d 460 (California Court of Appeal, 1970)
Frank Curran Lumber Co. v. Eleven Co.
271 Cal. App. 2d 175 (California Court of Appeal, 1969)
Flour Mills of America, Inc. v. American Steel Building Co.
449 P.2d 861 (Supreme Court of Oklahoma, 1969)
United States Leasing Corp. v. duPont
444 P.2d 65 (California Supreme Court, 1968)
Superior Wholesale Electric Co. v. Cameron
264 Cal. App. 2d 488 (California Court of Appeal, 1968)
J.A. Payton v. Kuhn-Murphy, Inc.
253 Cal. App. 2d 278 (California Court of Appeal, 1967)
R. D. Reeder Lathing Co. v. Allen
425 P.2d 785 (California Supreme Court, 1967)
Gordy v. United Pacific Insurance Group
243 Cal. App. 2d 445 (California Court of Appeal, 1966)
Verdugo Highlands, Inc. v. Security Insurance
240 Cal. App. 2d 527 (California Court of Appeal, 1966)
Neptune Gunite Co. v. Monroe Enterprises, Inc.
229 Cal. App. 2d 439 (California Court of Appeal, 1964)
Rogers v. Whitson
228 Cal. App. 2d 662 (California Court of Appeal, 1964)
Distefano v. Hall
218 Cal. App. 2d 657 (California Court of Appeal, 1963)
Peter Kiewit Sons' Co. v. Pasadena City Junior College District
379 P.2d 18 (California Supreme Court, 1963)
Flora v. Aetna Casualty & Surety Co.
207 Cal. App. 2d 376 (California Court of Appeal, 1962)
Powers Regulator Co. v. Seaboard Surety Co. of New York
204 Cal. App. 2d 338 (California Court of Appeal, 1962)