Housing Authority v. E. W. Johnson Construction Co.

573 S.W.2d 316, 264 Ark. 523, 1978 Ark. LEXIS 2148
CourtSupreme Court of Arkansas
DecidedNovember 6, 1978
Docket78-86
StatusPublished
Cited by16 cases

This text of 573 S.W.2d 316 (Housing Authority v. E. W. Johnson Construction Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Arkansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Housing Authority v. E. W. Johnson Construction Co., 573 S.W.2d 316, 264 Ark. 523, 1978 Ark. LEXIS 2148 (Ark. 1978).

Opinion

George Howard, Jr., Justice.

The paramount issue for resolution in this appeal is whether the trial court committed reversible error in awarding a judgment, sitting without a jury, to appellee-contractor in the sum of $12,938.12, including interest at the rate of 10%, predicated upon the following findings:

1. Appellant breached its contract with appellee in requiring a duplicate bond prior to releasing the retainage.
2. Appellant breached the warranty of the plans and specifications submitted to the appellee resulting in cardinal changes in the contract, causing a delay of sixty-eight days in the completion of the job, although the work to be performed was completed five days ahead of the scheduled completion date contained in the contract.

Stated another way, we are to decide if the holding of the trial court is supported by substantial evidence. An affirmative response to this question requires an affirmance, while a negative response imposes a duty to reverse.

THE FACTS

On March 12, 1973, appellant, the Housing Authority of the City of Texarkana, Arkansas, hereafter referred to as owner, entered into a contract with appellee, E. W. Johnson Construction Company, Inc., hereafter referred to as contractor, whereby the owner would pay to the contractor the sum of $620,000.00, subject to additions and deductions as provided in the specifications, for the following services:

“The contractor shall furnish all labor, material, equipment and services, and perform and complete all work required for the Modernization of 80 Low Rent Housing Units ... as defined by the name of Ozane Courts located in Texarkana, Arkansas in strict accordance with the Specifications for modernization . . . and, the Drawings referred to herein ...”

Essentially, the work to be performed by the contractor consisted of remodeling the interior of the housing units with a small amount of sidewalk work, refurbishing some porches, installing some parking blocks in the parking area, and constructing a few planters. The major outside work consisted of the construction of a day care center, after the contractor had demolished two existing apartments down to the floor level in order to make way for the day care center, which was regarded by the parties as virtually a new construction. Testimony offered by the contractor specified that 90 to 95% of the total construction work to be performed by him involved the remodeling of the interior of the housing units.

Under the terms of the original contract, the owner was to repair, what was assumed to be minor in nature, leaky water lines, broken windows, deteriorated floors and doors under its own auspices.

On March 12, 1973, the contractor called a preconstruction conference with all of his subcontractors and although the contract designated March 5, 1974, as the completion date, the contractor and the subcontractors projected November 21, 1973, as the completion date, allowing time for slippage and weather problems. Crews were set up for sheet rock, electrical, carpentry and plumbing work. The only roofing work to be performed by the contractor was a roof in connection with the construction of the day care center. Construction commenced on March 21, 1973, in accordance with the terms of the contract, which contains standard government contract provisions granting the owner the right to make changes in the job specifications within the general scope of the contract and as necessitated by changed conditions. 1

On April 20, 1973, the contractor discovered leaks in the roofs of the units under repair and between April 20, 1973, and May 4, 1973, there were consultations between the contractor and the owner regarding the amount of work and cost involved in the repairs required to stop the leaks. On May 3, 1973, the contractor received a change order from the owner, in accordance with the terms of the contract, calling upon the contractor to make the necessary roofing repairs which the contractor rejected because there was no provision for extension of time for the completion of the contract in view of the fact the contractor’s subcontractors indicated that a minimum of six weeks, with perfect weather, would be required for the completion of the roofing work; that there was no allowance for extra labor or materials and that the proposed work, under the change order, would create a financial hardship on the contractor which he could not absorb and, consequently, he could not waive his rights for damages. 2

On or about June 4, 1973, the owner’s architect advised the contractor that until a decision had been reached regarding the roofing work, the contractor would have to cease work under the contract in order to avoid damage to the interior that was being performed by his various crews. Consequently, the contractor was unable to proceed with the sheet rock, trim, painting, cabinet and floor work in accordance with the pre-construction schedule agreed upon by contractor and his subcontractors. Moreover, the contractor was compelled to release approximately one-half of his work force which he never recouped.

As a further consequence of the delay caused by the roofing defects and other change orders received from the owner either adding or deleting certain items of repair and the failure of the owner to make timely decisions involving changes and corrections in the defective plans and specifications, the contractor alleges that he experienced a sixty-eight day delay resulting in the completion of the job on February 28, 1974, instead of the projected date of November 21, 1973.

The contractor testified that the total dollar amount of net changes after additions and deductions to the contract, amounted to $49,000.00, while the percentage of the change overall was approximately 37%.

HOLDING OF THE TRIAL COURT

The trial court, in rendering a judgment in behalf of the appellee-plaintiff, made the following findings:

“That Defendant, Housing Authority of the City of Texarkana, Arkansas, breached its contract with the plaintiff in two particulars: First, in requiring a duplicate bond prior to releasing the retainage, said requirement being outside the terms of the contract to Plaintiff’s damage in the amount of Seven Hundred Fifty-Two Dollars ($752.00), for which Plaintiff is entitled to judgment; and, secondly, Defendant breached the contract made the subject to this cause by breach of warranty of the plans and specifications submitted to the contractor resulting in cardinal changes to the contract consisting of changes in the roof, floors, and plumbing which were not within the scope of the original contract and which forced the contractor to more costly operations and forced the contractor into an undertaking different from the original contract. Defendant further breached the contract in failing to make timely decisions concerning changes and corrections to the defective plans and specifications.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Furnas v. Kimbrell
2015 Ark. 148 (Supreme Court of Arkansas, 2015)
Hartford Casualty Insurance v. City of Marathon
825 F. Supp. 2d 1276 (S.D. Florida, 2011)
Hartford Cas. Ins. Co. v. CITY OF MARATHON
825 F. Supp. 2d 1276 (S.D. Florida, 2011)
Graham Const. Co., Inc. v. Earl
208 S.W.3d 106 (Supreme Court of Arkansas, 2005)
Dalrymple v. Dalrymple
47 S.W.3d 920 (Court of Appeals of Arkansas, 2001)
LK Comstock & Co., Inc. v. Becon Const. Co., Inc.
932 F. Supp. 906 (E.D. Kentucky, 1993)
Carroll-Boone Water District v. M. & P. Equipment Co.
661 S.W.2d 345 (Supreme Court of Arkansas, 1983)
American Sheet Metal Works, Inc. v. Con-Ark Builders, Inc.
635 S.W.2d 241 (Supreme Court of Arkansas, 1982)
State, Department of General Services v. Cherry Hill Sand & Gravel Co.
443 A.2d 628 (Court of Special Appeals of Maryland, 1982)
Dep't of Gen. Serv. v. CHERRY HILL S & G CO.
443 A.2d 628 (Court of Special Appeals of Maryland, 1982)
Downey v. May
619 S.W.2d 614 (Supreme Court of Arkansas, 1981)
Northwestern National Insurance v. Stanley
598 S.W.2d 439 (Court of Appeals of Arkansas, 1980)

Cite This Page — Counsel Stack

Bluebook (online)
573 S.W.2d 316, 264 Ark. 523, 1978 Ark. LEXIS 2148, Counsel Stack Legal Research, https://law.counselstack.com/opinion/housing-authority-v-e-w-johnson-construction-co-ark-1978.