Graham Const. Co., Inc. v. Earl

208 S.W.3d 106, 362 Ark. 220, 2005 Ark. LEXIS 274
CourtSupreme Court of Arkansas
DecidedMay 5, 2005
Docket04-769
StatusPublished
Cited by9 cases

This text of 208 S.W.3d 106 (Graham Const. Co., Inc. v. Earl) is published on Counsel Stack Legal Research, covering Supreme Court of Arkansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Graham Const. Co., Inc. v. Earl, 208 S.W.3d 106, 362 Ark. 220, 2005 Ark. LEXIS 274 (Ark. 2005).

Opinions

Jim Gunter, Justice.

Appellant, Graham Construction Co., Inc., appeals an order from the Carroll County Circuit Court entering judgment in favor of appellee, Roscoe T. Earl, in a construction case involving express and implied warranties. We affirm the trial court’s rulings.

In November 1999, Earl met with Graham’s representative, Lonnie Graham (jointly “Graham”), to discuss a construction project involving the installation of a roof with skylights over appellee’s indoor pool area. Earl told Graham that he would supply the skylights and stainless steel borders, and Graham told Earl that he would supply additional roofing material and the labor. In October 1999, one month prior to their meeting, Earl consulted with two engineers on how to put on the roofing, and based upon the recommendations of the engineers, he chose a six-millimeter Lexan plastic panel for the skylight. Earl also conducted research on the Lexan product, and drafted his own set of installation procedures based in part upon six bulletins that he gathered from the University of Arkansas. Earl requested that Graham use his installation procedures. Graham represented to Earl that the roof would not leak.

On March 2, 2000, based upon an estimate provided by Graham, Earl entered into a verbal agreement with Graham for the price of $3,481.00 to replace the existing roofing material over Earl’s enclosed pool area with new roofing material, including new skylights and frames for the skylights. Earl paid appellant the full of sum of $3,481.00 prior to the commencement of the work.

Graham began work on March 6, 2000, and the construction was completed within a reasonable time. During the work, Graham followed Earl’s set of installation procedures. However, Earl discovered that the roof leaked in several places approximately twelve days after the completion of the roof work. Graham sent two men to make repairs to the roof. However, the roof leaked again the next time it rained. Earl called Graham, who sent someone to repair the roof and to caulk around the skylights. Several weeks later, the roof leaked a third time after a heavy rain. Earl documented the leaks and made diagrams of the locations of the leaks to give to Graham’s workers. After four to six attempts, Graham made no further efforts to repair the roof. According to Earl, the leaks did not stop, and the roof was never adequately repaired.

On September 18, 2002, Earl filed a complaint in the Eureka Springs District Court, seeking judgment of $4750.00 against Graham. Graham answered, and the district court awarded Earl a judgment of $3,481.00, plus costs and interest. Graham timely appealed to the Carroll County Circuit Court.

On September 29, 2003, Earl amended his complaint, alleging that Graham contracted to replace a roof over Earl’s pool area. Earl alleged that Graham expressly represented to him that the new roof would not leak. Earl further asserted an implied warranty that the new roof would not leak and that the work would be performed in a workmanlike manner. Earl further averred that there was a “complete and total failure of consideration.” Thus, he requested the full refund of the $3,481.00 paid to Graham. Additionally, he requested the following incidental and consequential damages: (1) $750.09 for the cost of the skylights; (2) $334.73 for flashing and metal for the skylights; (3) $72.48 for lumber; (4) $125.00 for the replacement of a pool cover that was stained as a result of the leaking roof; (5) $3,000.00 for replacement of a pool liner as a result of stains due to a leaking roof; and (6) $300.00 for Earl’s fifty hours of labor in scrubbing the pool deck and cleaning the stains as a result of a leaking roof

On October 13, 2003, Graham answered, raising the defenses of estoppel and waiver and stating that Earl’s cause of action was a direct result of his action or inaction regarding both the design of the skylights in question and the materials provided to be used in accordance with Earl’s design.

The parties waived a jury trial, and a bench trial was held before the Carroll County Circuit Court on January 26, 2004, and February 25, 2004. At trial, Earl testified that he would supply the windows above the skylights and the stainless steel borders around them. He testified that Graham did not make any express warranties about the work, but Graham “guaranteed me it [the roof] wouldn’t leak.” According to Earl’s testimony, the roof leaked after the first rain. He repeatedly called Graham’s workers to repair the roof, but it continued to leak after each rain.

Graham testified that he told Earl that the roof would not leak. Graham further testified that he never represented to Earl that the roof would not leak as a result of the product that Earl supplied or the procedures that Earl furnished.

Graham put on an expert witness, Darrell Wolf, who has been a builder for over thirty-five years. Wolf testified that the Lexan product was installed improperly “every which way it could be installed improperly.” Wolf testified that the skylights were installed horizontally, rather than vertically with the pitch of the roof, which is essential for allowing the water to run out. In reviewing the photographs of the skylights, Wolf testified that he saw gaps in the flashing. He further testified that the skylights were not the proper thickness to withstand Arkansas weather.

The trial court found that Graham gave an express warranty that the roof would not leak. The trial court also found that Earl gave an implied warranty of the adequacy and suitability of the materials, plans, and specifications that he supplied. The trial court stated that Graham was a “competent and experienced contractor” and “should have been aware that the plans and specifications could not produce the proposed results.” The trial court further found that evidence was not sufficient to prove that the leaks resulted from the inadequacy of Earl’s materials or plans. Based upon these findings, the trial court ruled in favor of Earl and found that he was entitled to judgment against Graham for $3,200.00 plus attorneys’ fees and costs. From this order, Graham brings its appeal.

We have said that findings of fact of a trial court sitting as a jury will not be reversed on appeal unless clearly against a preponderance of the evidence. Sharp County v. Northeast Arkansas Planning & Consulting Co., 269 Ark. 336, 602 S.W.2d 627 (1980). Since the question of the preponderance of the evidence turns largely on the credibility of the witnesses, we defer to the superior position of the trial court. Id.

For his first point on appeal, Graham argues that the trial court erred in determining that Graham knew or should have known about the unsuitability ofEarl’s plans. Specifically, Graham contends that Earl impliedly warranted that his installation plans and specifications were fit for the purpose of constructing a skylight over his indoor pool. Graham maintains that he did not know or should not have known that Earl’s installation plans and specifications were unfit.

In response, Earl argues that the trial court correctly ruled that Graham’s representative, Lonnie Graham, was a competent and experienced contractor, and that he should have been aware that Earl’s installation plans could not have produced the desired results.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hartness v. Nuckles
2015 Ark. 444 (Supreme Court of Arkansas, 2015)
Crumpacker v. Gary Reed Construction, Inc.
374 S.W.3d 162 (Court of Appeals of Arkansas, 2010)
Save Energy Reap Taxes v. Shaw
288 S.W.3d 601 (Supreme Court of Arkansas, 2008)
C. A. R. Transportation Brokerage Co. v. Seay
255 S.W.3d 445 (Supreme Court of Arkansas, 2007)
Graham Const. Co., Inc. v. Earl
208 S.W.3d 106 (Supreme Court of Arkansas, 2005)

Cite This Page — Counsel Stack

Bluebook (online)
208 S.W.3d 106, 362 Ark. 220, 2005 Ark. LEXIS 274, Counsel Stack Legal Research, https://law.counselstack.com/opinion/graham-const-co-inc-v-earl-ark-2005.