School District No. 3 v. DeLano

152 P. 668, 96 Kan. 499, 1915 Kan. LEXIS 419
CourtSupreme Court of Kansas
DecidedNovember 6, 1915
DocketNo. 19,515
StatusPublished
Cited by15 cases

This text of 152 P. 668 (School District No. 3 v. DeLano) is published on Counsel Stack Legal Research, covering Supreme Court of Kansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
School District No. 3 v. DeLano, 152 P. 668, 96 Kan. 499, 1915 Kan. LEXIS 419 (kan 1915).

Opinion

[501]*501The opinion of the court was delivered by

Johnston, C. J.:

This was an action brought by School District No. 3 of Ford county against The United States Fidelity and Guaranty Company of Baltimore, Maryland, and C. W. DeLano to recover for the failure of DeLano to complete a contract for the erection of a schoolhouse. On June 25, 1909, DeLano contracted with the board of education to furnish the necessary labor and material and complete by December 15, 1909, an eight-room school building in Spearville for the sum of $15,000 upon the condition that he would pay $5 a day as liquidated damages if the building should not be completed within the agreed time, and the guaranty company gave bond in the sum of $5000 conditioned upon the faithful performance of the contract. It was an ordinary building contract and provided for the payment of ninety per cent of the contract price in installments upon estimates made by the architect and general superintendent. It also provided that work mentioned or shown in either the specifications or plans only should be considered as if in both. Provision was also made for additions or deductions and for alterations deemed to be proper or necessary. DeLano entered upon the work. He was paid, upon the architect’s estimates, the sum of $12,595.73 and $1458.73 additional was paid by the board to claimants upon DeLano’s orders. The time for completion of the building was extended by agreement to April 1, 1910, and notice of the extension was given the guaranty company, but in a letted dated December 21, 1909, the company advised that such a notice was unnecessary. DeLano continued work upon the school building until July 1, 1910, when he abandoned the work, locked the door and turned the key over to a member of the school board. The school board notified the guaranty company of DeLano’s abandonment of the work when they learned that he was not coming back, and on October 6,1910, attorneys for thje board wrote the company in detail giving an estimate that the cost of completing the building would be from $1500 to $2000 and advising of a mechanic’s lien of nearly $2000. The company took no steps to complete the building, and in fact made no response to the notices of the contractor’s default, and the board engaged the architect to get some one to oversee the completion of the build[502]*502ing. Work was not begun by the board until November 21, 1910, and it was.finally completed on February 1, 1911. The case was tried without a jury and the court found the total sum due the school district to be $6379.84, including $1594.35 for liquidated damages for the delay, and rendered judgment against DeLano for that sum and against the guaranty company for $5868.08. The company appeals.

The defendant asks to be released from liability upon its bond because more than ninety per cent of the work done and material furnished had been paid to the contractor as the work progressed. The only provisions in the contract respecting the time and manner of payment were that ninety per cent of the estimates made by the architect should be paid to the contractor on or about every thirty days and all extras and the contract price were to be paid within ten days after the contract was fulfilled and accepted. It appears that payments were not made directly to the contractor in excess of ninety per cent of the estimates of the architect, but the board did pay legal claims for work done and material furnished in the erection of the building to the extent of $1458.73, which added to that paid to the contractor made a sum in excess of ninety per cent of the estimates. The stipulation requiring the owner to pay ninety per cent of the estimates as the building progressed is available to the surety where it is specifically provided for in the bond given by the surety. The contract did not stipulate for the retention of any part of the contract price until the building was completed and accepted, and there was no provision in the bond given by the surety company which specifically provided that a percentage of the estimates should be retained by the owner until the contract was carried out. As the company was insuring for profit it was not entitled to insist on the withholding of a final payment or that a particular percentage of the contract price should be retained since it was not specifically provided for in the bond which it gave. (The Y. M. C. A. v. Ritter, 90 Kan. 332, 133 Pac. 894.) Aside from this consideration it appears that the claims paid by the board to others than the contractor were for material furnished and work done in.the erection of the building. They were reasonable and proper charges which had to be paid' and which might have become liens upon the building if payment had not been made. [503]*503Being valid claims it was immaterial to the company whether they were paid when due or withheld until the end, as the company had obligated itself to the owner to pay all legal claims for material and labor up to the penalty in its bond, and therefore it sustained no loss because of the time and manner in which the payments were made. In any event it has no right to complain of the time and manner of payments unless it has been damaged by a departure from the terms of the contract and of the obligation which it assumed. (The Y. M. C. A. v. Ritter, supra; School District v. McCurley, 92 Kan. 53, 142 Pac. 1077; Republic County v. Guaranty Co., ante, p. 255, 150 Pac. 590; Lumber Co. v. Peterson & Sampson, 124 Iowa, 599, 100 N. W. 550; Schrieber v. Worm, 164 Ind. 7, 72 N. E. 852; United States F. & G. Co. v. Trustees of Baptist Church [Ky. 1907] 102 S. W. 325.)

Another ground upon which the company claims a release front liability is that alterations were made and some extra work was provided for which was not mentioned in the original contract. It is true that alterations were made which provided for the finishing of the basement and the plastering of a room, amounting to between $500 and $600, but these changes appear to have been such as were within the contemplation of the contracting parties when they agreed that the board might make such alterations as it deemed proper without invalidating the contract. It expressly provided for deviation from the plans and specifications either by additions or omissions, and as the contract the performance of which the company insured authorized alterations, it, in effect, consented in advance to reasonable changes. In view of this provision the company as a compensated surety can not claim: a release from its obligation because the changes mentioned were made. (McLennan v. Wellington, 48 Kan. 756, 30 Pac. 183; Risse v. Planing Mill Co., 55 Kan. 518, 40 Pac. 904.) There was no demand for arbitration of these additions nor did the absence of it prevent a determination of the necessity and value of them in the trial.

The next complaint is of the allowance of liquidated damages to the extent of $1594.35. The contract, as we have seen, provided for the payment of $5 a day, exclusive of Sundays, as liquidated damages for each day the building was incomplete after the agreed time for completion. The time first fixed [504]*504for completion was December 15, 1909, but it was extended by agreement until April 1, 1910, and of this extension the guaranty company was given notice. The contractor abandoned the building on July 1, 1910. Early notice of the abandonment was given to the guaranty company, but it did not respond to the notice nor afterwards take any steps towards the completion of the building.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In re the Conservatorship of Huerta
41 P.3d 814 (Supreme Court of Kansas, 2002)
Austin-Griffith, Inc. v. Goldberg
79 S.E.2d 447 (Supreme Court of South Carolina, 1953)
Farmers Union Elevator Co. v. Johnson-Sampson Construction Co.
258 P.2d 268 (Supreme Court of Kansas, 1953)
Gibbs v. Hartford Accident & Indemnity Co.
62 So. 2d 599 (Supreme Court of Florida, 1952)
Six Companies of California v. Joint Highway Dist. No. 13
24 F. Supp. 346 (N.D. California, 1938)
Fritz v. Western Light & Power Corp.
36 P.2d 90 (Supreme Court of Kansas, 1934)
Southern Pac. Co. v. Globe Indemnity Co.
21 F.2d 288 (Second Circuit, 1927)
Roberts v. Security Trust & Savings Bank
238 P. 673 (California Supreme Court, 1925)
City of Portsmouth v. Nicola Building Co.
106 Ohio St. (N.S.) 550 (Ohio Supreme Court, 1922)
Collins v. Tarrant County
242 S.W. 1105 (Court of Appeals of Texas, 1922)
Southern Real Estate & Financial Co. v. Bankers Surety Co.
207 S.W. 506 (Supreme Court of Missouri, 1918)

Cite This Page — Counsel Stack

Bluebook (online)
152 P. 668, 96 Kan. 499, 1915 Kan. LEXIS 419, Counsel Stack Legal Research, https://law.counselstack.com/opinion/school-district-no-3-v-delano-kan-1915.