Austin-Griffith, Inc. v. Goldberg

79 S.E.2d 447, 224 S.C. 372, 42 A.L.R. 2d 1123, 1953 S.C. LEXIS 113
CourtSupreme Court of South Carolina
DecidedDecember 21, 1953
Docket16808
StatusPublished
Cited by12 cases

This text of 79 S.E.2d 447 (Austin-Griffith, Inc. v. Goldberg) is published on Counsel Stack Legal Research, covering Supreme Court of South Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Austin-Griffith, Inc. v. Goldberg, 79 S.E.2d 447, 224 S.C. 372, 42 A.L.R. 2d 1123, 1953 S.C. LEXIS 113 (S.C. 1953).

Opinion

Oxner, Justice.

This is a statutory proceeding to establish and foreclose two liens for labor and materials furnished by Austin-Griffith, Inc. in the erection of a building for Dorothy R. Goldberg and her husband, M. M. Goldberg.

On March 15, 1949, Austin-Griffith, Inc. entered into a contract with the Goldbergs, who then operated a tourist court in Clarendon County, near Summerton, to erect, according to certain plans and specifications, an additional building on the premises for $32,200.00. The contract price was to be paid in installments based on a certain percentage of the value of the labor and materials incorporated in the work and of the materials stored at the site, as estimated by the architect. Upon substantial completion o'f the entire work, the contractor was to receive a sum sufficient to increase the total payments to 90% of the contract price. The remaining 10% was to be paid upon a final certificate of the architect that the contract had been fully completed and the work was acceptable.

The job was to be completed on or before July 15, 1949, and the contractor agreed that for each day thereafter that the contract remained uncompleted, the owner could deduct and retain from the contract price as liquidated damages the sum of $50.00. It was further provided, “that if the completion of this contract is delayed by the owner, an act of God, or casualty beyond the control of the contractor then in such event, the time of completion of this contract shall be extended for such additional time as should be considered (caused) by such delay, provided, however, that the con *376 tractor herein shall at the time of such delay, if any, demand of the owner in writing such additional time within which to complete the performance of this contract.”

The provision as to alterations and extra work was as follows:

“The owner shall have the right at any time to make changes, additions, or omissions that he may desire and the same shall be executed by the contractor as a part of this contract, without impairing its validity, and the changes, and the value of the changes are to be agreed upon in writing to the architect and added or deducted from the contract price as the case may be.
“No claim for work will be allowed unless the same is ordered in writing by the owner through the architect, and the cost agreed upon, and stated in the order.
“No alteration shall be made in the work except upon written order of the architect, the amount to be paid by the owner or allowed by the contractor by virtue of such alteration to ,be stated in said order.”

It was agreed that if the contractor neglected to supply sufficient materials or workmen or abandoned the contract, the owner could, after first giving three days’ notice in writing by registered mail, provide the necessary materials and workmen to complete the job and charge the costs thereof to the contractor. The contractor further agreed to make good any defects arising from faulty materials or workmanship, which appeared within three months after the completion of the building.

Finally, it was stated that “should any dispute arise respecting the true construction or meaning of the drawings or specifications, the same shall be decided by the architect, whose decision shall be final and conclusive.”

The other terms and conditions of the contract are not material to this controversy.

*377 Construction was commenced immediately after the execution of the contract. During the progress of the work, the contract was twice amended. The first amendment, executed on May 26, 1949, provided that the owner, instead of the contractor, would furnish and install the heating system and certain window and door screens. The agreed value of these eliminations was $3,155.00, thereby reducing the contract price to $29,045.00. Under the second amendment, executed on August 24, 1949, the contractor was relieved of the responsibility of furnishing and installing the kitchen sink and cabinets, the agreed value of which was $250.00, thereby further reducing the contract price to $28,795.00.

During the course of construction, the sum of $18,519.18 was paid to the contractor. On July 15, 1949, the time fixed in the contract for completion of the building, the job was far from finished. Finally, on September 10, 1949, the contractor, claiming that the owners had breached the contract in several particulars, ceased work, and on September 20th filed two mechanics’ liens against the premises, one for an alleged balance due on the contract, and the other for alleged extra work. On September 22, 1949, Goldberg notified the contractor by letter that unless work was resumed by September 28th, he would take over the job and finish the building, charging the costs thereof, to the contractor. Work was not resumed and on October 4, 1949, Goldberg notified the contractor that the owners would proceed immediately to complete the building.

On February 16, 1950, this action was commenced for the foreclosure of the two mechanics’ liens which had been filed. It was alleged in the contractor’s petition that subsequent to the execution of the contract on March 15, 1949, from time to time the parties entered into oral agreements for work in addition to that stipulated in the contract; that all terms and conditions of the contract were duly performed by the contractor until September 10, 1949, when it was forced to discontinue construction because of the failure of *378 the owners (1) to make payments as provided by the contract, (2) to make selection of materials as they were required to do, and (3) to allow the workmen on the job to continue with construction in accordance with the agreements between the parties. It was further alleged that the contractor was entitled to a lien for $7,055.82, representing the balance due on the contract, and for the further sum of $4,763.25, representing extra work done at the request of the owners.

An answer was duly filed by the Goldbergs. They denied entering into any agreement for extra work and further denied any breach of contract on their part. They alleged that the contractor failed to construct the building in accordance with plans and specifications; that it finally abandoned the contract, necessitating the job being completed by the owners; and that on account of the unsatisfactory condition of the building when abandoned, due to failure to carry out specifications and faulty workmanship, it was worth no more than had been already paid on the contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Twin River Construction Co. v. Public Water District No. 6
653 S.W.2d 682 (Missouri Court of Appeals, 1983)
City of Boston v. New England Sales & Manufacturing Corp.
438 N.E.2d 68 (Massachusetts Supreme Judicial Court, 1982)
Boston v. NEW ENGLAND SALES & MANUFACTURING CORP.
438 N.E.2d 68 (Massachusetts Supreme Judicial Court, 1982)
Medema Homes, Inc. v. Lynn
647 P.2d 664 (Supreme Court of Colorado, 1982)
Keith v. Burzynski
621 P.2d 247 (Wyoming Supreme Court, 1980)
Quin Blair Enterprises, Inc. v. Julien Construction Co.
597 P.2d 945 (Wyoming Supreme Court, 1979)
J. R. Graham & Son, Inc. v. Randolph County Board of Education
212 S.E.2d 542 (Court of Appeals of North Carolina, 1975)
Flour Mills of America, Inc. v. American Steel Building Co.
449 P.2d 861 (Supreme Court of Oklahoma, 1969)
Peter Kiewit Sons' Co. v. Pasadena City Junior College District
379 P.2d 18 (California Supreme Court, 1963)
Nash v. GARDNER
101 S.E.2d 283 (Supreme Court of South Carolina, 1957)

Cite This Page — Counsel Stack

Bluebook (online)
79 S.E.2d 447, 224 S.C. 372, 42 A.L.R. 2d 1123, 1953 S.C. LEXIS 113, Counsel Stack Legal Research, https://law.counselstack.com/opinion/austin-griffith-inc-v-goldberg-sc-1953.