Olson Construction Co. v. Commercial Building & Investment Co.

256 N.W. 22, 127 Neb. 609, 1934 Neb. LEXIS 84
CourtNebraska Supreme Court
DecidedJuly 17, 1934
DocketNo. 28933
StatusPublished
Cited by9 cases

This text of 256 N.W. 22 (Olson Construction Co. v. Commercial Building & Investment Co.) is published on Counsel Stack Legal Research, covering Nebraska Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Olson Construction Co. v. Commercial Building & Investment Co., 256 N.W. 22, 127 Neb. 609, 1934 Neb. LEXIS 84 (Neb. 1934).

Opinion

Eberly, J.

The nature of this case is a suit in equity. The Olson Construction Company sued to foreclose a mechanic’s lien for a balance due for construction of a commercial building, and encountered a conventional cross-petition for damages caused by faulty construction filed by the Commercial Building & Investment Company, which will hereinafter be referred to as the building company. The pleadings made up more than 50 pages of the transcript, and the evidence adduced at the trial consists of three large volumes embracing 1,335 pages. To abstract either the pleadings or the evidence would unduly extend this opinion. At the end of the trial occupying several weeks the court found for the plaintiff in the sum of $4,724.96, [610]*610balance due by the terms of its contract for the construction of the building, which amount included claimed extras. But the trial court also found for the defendant building company in the sum of $5,920 and directed that such defendant recover the difference between said accounts, or the sum of $1,195.04, with interest at 7 per cent. A motion for a new trial was filed by plaintiff, and from the order overruling the same it appeals. The defendants, including the building company, filed no motion for new trial, and neither have they perfected a cross-appeal.

The sole matters presented for our consideration relate to the correctness of the judgment of the trial court in favor of the defendant building company for the following items: Owner’s loss of rent on the first floor of the building in the sum of $250, and on the second and third floors in the sum of $i,100, due to failure to complete the building on or before May 1, 1930, as required by the contract; damages for failure to comply with terms of the contract relating to the painting of the “waiting room, etc.,” $370; damages for failure to properly complete construction of the second and third floors, $4,200. But, in many respects, these questions as here presented will have to be determined from disputed evidence, detailed from the witness-stand by witnesses appearing and testifying in person before the trial court. A number of (Witnesses, properly to be designated as expert witnesses, so testified at length. The trial court saw them, heard them, and observed them when testifying. Preponderance of evidence is not necessarily determined by the number of opposing witnesses.

Where the evidence on material questions of fact is in irreconcilable conflict, this court will, in determining the weight of the evidence, consider the fact that the trial court observed the witnesses and their manner of testifying, and must have adopted one view of the facts rather .than the opposite. Magill v. Magill, 114 Neb. 636; Peterson v. Winkelmann, 114 Neb. 714; Enterprise Planing Mill Co. v. Methodist Episcopal Church, 100 Neb. 29; Greusel [611]*611v. Payne, 107 Neb. 84; Shafer v. Beatrice State Bank, 99 Neb. 317; Jones v. Dooley, 107 Neb. 162.

The first item of counterclaim permitted by the trial court is referred to in its decree in the following language:

“That the plaintiff when painting and decorating the waiting room, etc., in the said building, did not permit the plastering to dry sufficiently before applying the paint and did not perform the work in a proper and acceptable manner; and in consequence thereof the work did not stand up, but almost immediate^ became blotched and unsightly and not up to the requirements of the plans and specifications; that by reason of the premises the owner was damaged by the plaintiff in the sum of $370 and that the owner is entitled to recover such sum from the plaintiff upon his cross-petition.”

We find the evidence fully sustains this determination and the same is approved.

The next item for consideration is $1,350 in damages, allowed for failure to complete the building within the time as specified by the contract. That the building was not completed within the time specified is conclusively established. The actual damages occasioned thereby are amply proved. However, appellant claims that it was entitled to certain extensions of this time and that the building was completed within such time if credit is allowed, for extensions to which it was entitled. Obviously, the contract provisions govern. The form of contract is one: issued by the American Institute of Architects, being,. “The standard form of agreement between contractor and owner for construction of buildings, * * * when a stipulated sum forms the basis of payment.” Among its provisions are the following: (a) “That the contractor' and' the owner * * * agree as follows * * * and shall do everything required by this agreement, the general conditions of the contract. * * * (b) The work to be performed under-this contract shall be * * * completed May 1, 1930.”

The following appear in “The general conditions of the contract”:

[612]*612“Art. 1 * * * (f) All time limits stated in the contract documents are of the essence of the contract.”
'“Art. 15. Changes in the work. The owner, without invalidating the contract, may order extra work or make changes by altering, adding to or deducting from the work, the contract sum being adjusted accordingly. All such work shall be executed under the conditions of the original contract except that any claim for extension of time caused thereby shall be adjusted at the time of ordering such change.”
“Art. 18. Delays and extension of time. If the contractor be delayed at any time in the progress of the work by any act or neglect'"■'of the owner or the architect, or of any employee of either, or by any other contractor employed by the owner, or by changes ordered in the work, or by strikes, lockouts, fire, unusual delay in transportation, unavoidable casualties or any causes beyond the contractor’s control, or by delay authorized by the architect pending arbitration, or by any cause which the architect shall decide to justify the delay, then the time of completion shall be extended for such reasonable time as the architect may decide. No such extension shall be made for delay occurring more than seven days b.efore claim therefor is made in writing to the architect. In the case of a continuing cause of delay, only one claim is necessary.”

While a real dispute appears in the evidence as to the extent of the delays occasioned by the owners, and as to whether certain delays were occasioned by causes which would entitle the contractor to an extension of time, there is no dispute that the contractor wholly failed to conform to the provisions of article 18 above quoted, and never made an application for an extension of time as therein required, nor has due waiver thereof been established by competent proof.

In the decision of a similar question the following language was employed by this court in Carter v. Root, 84 Neb. 723, 731, viz.: “We come now to the second ques- » [613]*613tion presented: Is the defendant herein entitled to recover damages for the delay in the completion of said building? There was a delay of 150 days. The contract itself provided for some contingencies which might operate to delay the completion of the building, such as the act, neglect, or default of the owner, or the architect, or of any other contractor, or delays occasioned by fire, lightning, earthquake, or cyclone or abandonment of work by employees.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Abel Construction Co. v. School District of Seward
195 N.W.2d 744 (Nebraska Supreme Court, 1972)
Abel Construction Co. v. School District
195 N.W.2d 744 (Nebraska Supreme Court, 1972)
Parsons Construction Co. v. Metropolitan Utilities District
104 N.W.2d 272 (Nebraska Supreme Court, 1960)
Eastover Stores, Inc. v. Minnix
150 A.2d 884 (Court of Appeals of Maryland, 1959)
Austin-Griffith, Inc. v. Goldberg
79 S.E.2d 447 (Supreme Court of South Carolina, 1953)
Dier v. Dier
4 N.W.2d 731 (Nebraska Supreme Court, 1942)
United States v. Cunningham
125 F.2d 28 (D.C. Circuit, 1941)
Helfrich v. Baxter
267 N.W. 922 (Nebraska Supreme Court, 1936)

Cite This Page — Counsel Stack

Bluebook (online)
256 N.W. 22, 127 Neb. 609, 1934 Neb. LEXIS 84, Counsel Stack Legal Research, https://law.counselstack.com/opinion/olson-construction-co-v-commercial-building-investment-co-neb-1934.