The Boldt Company v. Black & Veatch Construction, Inc.

District Court, N.D. Illinois·Decided October 2, 2023·No. 1:19-cv-08383·Unknown

Opinion

IN THE UNITED STATES DISTRICT COURT FOR THE NORTHERN DISTRICT OF ILLINOIS EASTERN DIVISION THE BOLDT COMPANY, ) ) Plaintiff ) and Counter-Defendant, ) ) No. 19-cv-08383 v. ) ) Judge Andrea R. Wood BLACK & VEATCH CONSTRUCTION, ) INC., ) ) Defendant ) and Counter-Plaintiff. )

MEMORANDUM OPINION AND ORDER Defendant and Counter-Plaintiff Black & Veatch Construction, Inc. (“BVCI”) served as the contractor for the construction of a 60-turbine wind farm in Good Hope, Illinois (“Project”). BVCI then subcontracted with Plaintiff and Counter-Defendant The Boldt Company (“Boldt”) to offload and erect the Project’s wind turbines. When the Project fell significantly behind schedule, BVCI terminated Boldt for cause. Boldt claimed that BVCI wrongfully blamed it for delaying the Project when BVCI and the Project’s wind turbine vendor were actually to blame for the Project getting off schedule. Boldt therefore brought this lawsuit, alleging that BVCI breached its subcontract with Boldt when it terminated Boldt from the Project. In turn, BVCI filed a counterclaim against Boldt, also for breach of contract. Recently, the Court granted BVCI summary judgment as to Boldt’s claim for because it found that there was no dispute of material fact that BVCI properly terminated Boldt for cause due to its schedule default. It also denied Boldt’s motion for summary judgment as to BVCI’s counterclaim. Now, Boldt moves for reconsideration of both rulings. (Dkt. Nos. 199, 201.) For the reasons that follow, both motions are denied. BACKGROUND A more detailed summary of the facts relevant to BVCI’s motion for summary judgment may be found in the Court’s memorandum opinion addressing BVCI and Boldt’s respective motions for summary judgment. (Mar. 30, 2023 Mem. Op. and Order (“Summ. J. Ruling”), Dkt. No. 190.) The Court assumes familiarity with those facts.

To summarize briefly, in its complaint, Boldt alleges multiple breaches of BVCI and Boldt’s subcontract (“Subcontract”). Broadly, Boldt’s breach of contract claim asserts that BVCI wrongfully terminated Boldt from the Project for cause based on delays to the Subcontract’s baseline construction schedule (“Construction Schedule”) that were, in fact, attributable to both BVCI and the turbine vendor for the Project. According to Boldt, BVCI’s failure to provide suitable crane pads, access roads, and site laydown areas consistent with its obligations under the Subcontract was one of the true contributing factors to a portion of the delay to the Construction Schedule. Boldt then blamed the turbine vendor’s delayed and incomplete deliveries of turbine parts for the remainder of the delay. On the other hand, BVCI contended that Boldt was the sole cause of delay to the Project and therefore asserted a counterclaim alleging that Boldt was

properly terminated for cause due to its failure to complete its work on the Project in a timely and safe manner. BVCI and Boldt each moved for summary judgment as to their opponent’s claim. In its motion, BVCI asserted three grounds that it claimed entitled it to summary judgment as to the entirety of Boldt’s breach of contract claim. First, BVCI argued that Boldt’s claims based on alleged breaches predicated on issues with the BVCI-supplied crane pads, access roads, and site laydown areas were barred by two exculpatory clauses in the Subcontract. Second, BVCI contended that Boldt could not recover for any breach related to the turbine vendor’s delayed and incomplete deliveries of turbine parts because it failed to properly give notice of a Turbine Vendor-Caused Delay as required by the Subcontract. Third, BVCI contended that Boldt’s material breach of its obligations under the Subcontract to perform its work on the Project timely and safely precluded Boldt’s claim that it was wrongfully terminated for cause. Ultimately, the Court found in favor of BVCI with respect to each of the three grounds and entered summary judgment for BVCI as to Boldt’s breach of contract claim. At the same

time, the Court denied summary judgment to Boldt on BVCI’s counterclaim. Following the Court’s decision on the two motions for summary judgment, Boldt filed separate motions asking the Court to reconsider both its grant of summary judgment to BVCI on Boldt’s claim and its denial of summary judgment to Boldt on BVCI’s counterclaim. Together, Boldt’s two motions span over 50 pages and challenge nearly every aspect of the Court’s decision as to the two summary judgment motions. Given the length and scope of the combined motions and the limited circumstances in which motions for reconsideration are warranted, the Court instructed the parties to brief only issues relating to the Court’s grant of summary judgment to BVCI based on the Subcontract’s exculpatory clauses.

DISCUSSION Under Federal Rule of Civil Procedure 54(b), a district court may reconsider its interlocutory orders at any time before entry of a final judgment. Fed. R. Civ. P. 54(b); e.g., Wiegel v. Stork Craft Mfg., Inc., 891 F. Supp. 2d 941, 944 (N.D. Ill. 2012). “Motions for reconsideration serve a limited function: to correct manifest errors of law or fact or to present newly discovered evidence.” Caisse Nationale de Credit Agricole v. CBI Indus., Inc., 90 F.3d 1264, 1269 (7th Cir. 1996) (internal quotation marks omitted). The Seventh Circuit has recognized that a motion for reconsideration “performs a valuable function where the Court has patently misunderstood a party, or has made a decision outside the adversarial issues presented to the Court by the parties, or has made an error not of reasoning but of apprehension.” Bank of Waunakee v. Rochester Cheese Sales, Inc., 906 F.2d 1185, 1191 (7th Cir. 1990) (internal quotation marks omitted). As discussed above, Boldt’s two motions for reconsideration challenge nearly every basis of the Court’s decision on the two motions for summary judgment. It is well recognized, however, that issues warranting reconsideration “rarely arise and the motion to reconsider should

be equally rare.” Id. at 1191 (internal quotation marks omitted). Accordingly, a motion for reconsideration “is not an appropriate forum for rehashing previously rejected arguments or arguing matters that could have been heard during the pendency of the previous motion.” Caisse Nationale, 90 F.3d at 1270. Indeed, a district court’s decisions “are not intended as mere first drafts, subject to revision and reconsideration at a litigant’s pleasure.” Beezley v. Fenix Parts, Inc., No. 1:17-cv-7896, 2019 WL 666754, at *1 (N.D. Ill. Feb. 13, 2019) (internal quotation marks omitted). For the most part, Boldt’s motions for reconsideration assert arguments that either were made or could have been made in their summary judgment briefs. The Court informed Boldt that

Free access — add to your briefcase to read the full text and ask questions with AI

The Boldt Company v. Black & Veatch Construction, Inc., (N.D. Ill. 2023).

The Boldt Company v. Black & Veatch Construction, Inc. (The Boldt Company v. Black & Veatch Construction, Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Costello v. Grundon
651 F.3d 614 (Seventh Circuit, 2011)
United States v. Herbert Marvin Feinberg
89 F.3d 333 (Seventh Circuit, 1996)
Abel Construction Co. v. School District of Seward
195 N.W.2d 744 (Nebraska Supreme Court, 1972)
Stone v. City of Arcola
536 N.E.2d 1329 (Appellate Court of Illinois, 1989)
Whalen v. K Mart Corp.
519 N.E.2d 991 (Appellate Court of Illinois, 1988)
BP Amoco Chemical v. Flint Hills Resources, LLC
489 F. Supp. 2d 853 (N.D. Illinois, 2007)
Credit Union 1 v. Carrasco
2018 IL App (1st) 172535 (Appellate Court of Illinois, 2018)
Olson Construction Co. v. Commercial Building & Investment Co.
256 N.W. 22 (Nebraska Supreme Court, 1934)
Wiegel v. Stork Craft Manufacturing, Inc.
891 F. Supp. 2d 941 (N.D. Illinois, 2012)