The Boldt Company v. Black & Veatch Construction, Inc.

CourtDistrict Court, N.D. Illinois
DecidedMarch 30, 2023
Docket1:19-cv-08383
StatusUnknown

This text of The Boldt Company v. Black & Veatch Construction, Inc. (The Boldt Company v. Black & Veatch Construction, Inc.) is published on Counsel Stack Legal Research, covering District Court, N.D. Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
The Boldt Company v. Black & Veatch Construction, Inc., (N.D. Ill. 2023).

Opinion

IN THE UNITED STATES DISTRICT COURT FOR THE NORTHERN DISTRICT OF ILLINOIS EASTERN DIVISION THE BOLDT COMPANY, ) ) Plaintiff ) and Counter-Defendant, ) ) No. 19-cv-08383 v. ) ) Judge Andrea R. Wood BLACK & VEATCH CONSTRUCTION, ) INC., ) ) Defendant ) and Counter-Plaintiff. )

MEMORANDUM OPINION AND ORDER Defendant and Counter-Plaintiff Black & Veatch Construction, Inc. (“BVCI”) served as the contractor for the construction of a 60-turbine wind farm in Good Hope, Illinois (“Project”). BVCI then subcontracted with Plaintiff and Counter-Defendant The Boldt Company (“Boldt”) to offload and erect the wind turbines. About two months after work began, the Project was significantly behind schedule and not a single wind turbine had been fully erected. For that reason, BVCI terminated Boldt for cause. Boldt contends that BVCI wrongfully blamed Boldt for delaying the Project when BVCI and the Project’s wind turbine vendor were actually to blame for the Project getting off schedule. Boldt therefore brought this lawsuit, alleging that BVCI breached its subcontract with Boldt when it terminated Boldt from the Project. In response, BVCI filed a counterclaim against Boldt for breach of contract. Now before the Court are BVCI’s and Boldt’s cross-motions for summary judgment. (Dkt. Nos. 124, 126.) For the reasons that follow, BVCI’s motion is granted and Boldt’s motion is denied. BACKGROUND While Boldt and BVCI have numerous factual disputes relevant to their respective motions for summary judgment, the following facts establish the sequence of events giving rise to the present action and are undisputed unless otherwise noted.1 On February 8, 2019, BVCI, an engineering and construction company, entered into a

contract (“Prime Contract”) with Cardinal Point LLC (“Owner”) under which BVCI agreed to serve as the engineering, procurement, and construction contractor in connection with the Project. (BVCI’s Resp. to Boldt’s Statement of Material Facts in Supp. of its Mot. for Summ. J. (“BVCI’s RSOF”) ¶ 1, Dkt. No. 154; Boldt’s Resp. to BVCI’s Statement of Material Facts in Supp. of its Mot. for Summ. J. (“Boldt’s RSOF”) ¶¶ 1–2, Dkt. No. 160.) In addition, the Owner entered into a separate contract with General Electric Renewables North America, LLC (“GE”) in which GE agreed to supply and deliver wind turbine parts to the site where the wind turbines would be built. (BVCI’s RSOF ¶ 3; Boldt’s RSOF ¶ 2.) To erect the wind turbines, BVCI subcontracted with Boldt, a construction company that performs general contracting services in the power and utilities sector. (BVCI’s RSOF ¶ 4;

Boldt’s RSOF ¶ 4.) Specifically, BVCI and Boldt’s subcontract (“Subcontract”) required, among other things, that Boldt offload the wind turbine parts delivered to the Project site by GE and

1 Both BVCI and Boldt contend that their opponent has committed violations of the Northern District of Illinois’s Local Rule 56.1, which governs summary judgment practice. Although each party, at times, identifies minor, technical violations of Local Rule 56.1, those violations pose no obstacle to the Court’s ability to discern whether a fact is admitted or genuinely disputed. The Court therefore declines to strike any factual assertions on Local Rule 56.1 grounds. BVCI also filed a separate motion pursuant to Federal Rule of Evidence 408(a), which asks the Court to strike from Boldt’s summary judgment submissions all references to what BVCI claims are its confidential settlement documents. (Dkt. No. 174.) The Court has determined that it can resolve the motions for summary judgment without reliance on the documents that BVCI seeks to strike and expresses no opinion on their admissibility. Instead, the Court denies BVCI’s motion without prejudice to BVCI renewing any arguments concerning the challenged evidence’s admissibility by way of a pretrial motion in limine, if necessary. then erect the 60 wind turbines in accordance with the specified construction schedule. (Id.) Prior to beginning work on the Project, Boldt sub-subcontracted with TNT Crane & Rigging, Inc. (“TNT”),2 a crane rental company, for the rental of cranes and to prepare lift plans for the Project’s critical lifts (i.e., lifts associated with the erection of the major components of each wind turbine).3 (Boldt’s RSOF ¶¶ 6, 32, 36, 45.) Pursuant to the Subcontract, Boldt remained

liable for any failure of its sub-subcontractors in fulfilling Boldt’s obligations under the Subcontract. (Id. ¶ 31.) The Subcontract included a baseline construction schedule that was developed by Boldt (“Construction Schedule”). (BVCI’s RSOF ¶ 8; Boldt’s RSOF ¶ 19.) That schedule set out the planned sequence of construction activities using the critical path methodology.4 (Boldt’s RSOF ¶ 19.) The Subcontract specifically stated that “[p]erformance of the Work as scheduled in the Construction Schedule . . . is a material provision of the Subcontract.” (Id. ¶ 20; see also BVCI’s Statement of Material Facts in Supp. of Mot. for Summ. J., Ex. B, Subcontract § 00552.5.1, Dkt. No. 128-3.) Further, the Subcontract set construction milestone dates under which the first 10

wind turbines were scheduled for completion by August 31, 2019 and guaranteed by September 27, 2019. (Boldt’s RSOF ¶ 22.) For erection of all 60 wind turbines, the Subcontract set November 5, 2019 as the planned completion date and November 8, 2019 as the guaranteed completion date. (Id.)

2 Boldt filed a third-party complaint in this action asserting claims against TNT (Dkt. No. 19), but it ultimately voluntarily dismissed those claims. (Dkt. No. 114.) 3 BVCI explains that “[a] lift plan is a detailed plan identifying how Boldt personnel will execute lifts of turbine component parts during the offloading and erection activities. Lift plans include key information necessary to safely perform a lift.” (Boldt’s RSOF ¶ 42.) 4 The critical path methodology refers to a technique commonly used to develop a schedule for complex construction projects. Boldt began work on erecting the wind turbines in early August 2019. (Id. ¶¶ 22, 47, 50.) Under the Construction Schedule, Boldt gave itself until August 16, 2019 to complete work on erecting the first wind turbine. (Id. ¶ 48.) However, Boldt almost immediately encountered difficulties in its work on the Project. First, under the Subcontract, Boldt could not perform any critical lifts without first preparing a lift plan, having that plan stamped by a professional

engineer, and submitting the lift plan to BVCI at least 24 hours prior to the critical lift. (Id. ¶¶ 43–44.) Yet Boldt was unable to begin critical lifts for the first wind turbines as scheduled because TNT had failed to timely prepare adequate lift plans. (Id. ¶¶ 54, 67.) By August 21, 2019, Boldt had replaced TNT with a new sub-subcontractor tasked with preparing lift plans. (Id. ¶¶ 32, 54.) It was not until August 23, 2019, that Boldt submitted the first lift plans that BVCI could approve. (Id. ¶ 67.) Further, the cranes necessary to perform the erection work were not delivered to the Project and set up in accordance with the Construction Schedule. (Id. ¶¶ 85–86.) One crane that was necessary to “top out” (i.e., install the final components) certain of the first ten turbines was not assembled until September 7, 2019, even though the Construction Schedule

called for that crane’s first lifts to begin on August 12, 2019. (Id. ¶¶ 87, 90, 92.) During this time, Boldt’s work was delayed by conditions that it contends were outside of its control, such as unsuitable soil conditions at the Project site and issues with the crane pads5 designed and installed by BVCI. (Boldt’s RSOF ¶¶ 8, 67, 88; BVCI’s Resp. to Boldt’s Statement of Additional Facts (“BVCI’s RSAF”) ¶ 2, Dkt. No.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Dynegy Marketing and Trade v. Multiut Corp.
648 F.3d 506 (Seventh Circuit, 2011)
In Re Michael J. KRUEGER, Debtor-Appellant
192 F.3d 733 (Seventh Circuit, 1999)
Kirkpatrick v. Strosberg
894 N.E.2d 781 (Appellate Court of Illinois, 2008)
Countryman v. Industrial Commission
686 N.E.2d 61 (Appellate Court of Illinois, 1997)
Mohanty v. St. John Heart Clinic, S.C.
866 N.E.2d 85 (Illinois Supreme Court, 2006)
Dolezal v. Plastic & Reconstructive Surgery, S.C.
640 N.E.2d 1359 (Appellate Court of Illinois, 1994)
Shorr Paper Products, Inc. v. Aurora Elevator, Inc.
555 N.E.2d 735 (Appellate Court of Illinois, 1990)
Rogers v. Balsley
608 N.E.2d 1288 (Appellate Court of Illinois, 1993)
Gallagher v. Lenart
874 N.E.2d 43 (Illinois Supreme Court, 2007)
AAR International, Inc. v. Vacances Heliades S.A.
202 F. Supp. 2d 788 (N.D. Illinois, 2002)
DeGeer v. Gillis
707 F. Supp. 2d 784 (N.D. Illinois, 2010)
Aeroground, Inc. v. CenterPoint Properties Trust
738 F.3d 810 (Seventh Circuit, 2013)
Lima Lake Drainage District v. Hunt Drainage District
561 N.E.2d 1351 (Appellate Court of Illinois, 1990)
Bank of Commerce v. Hoffman
829 F.3d 542 (Seventh Circuit, 2016)

Cite This Page — Counsel Stack

Bluebook (online)
The Boldt Company v. Black & Veatch Construction, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/the-boldt-company-v-black-veatch-construction-inc-ilnd-2023.