Aeroground, Inc. v. CenterPoint Properties Trust

738 F.3d 810, 2013 WL 6731478, 2013 U.S. App. LEXIS 25572
CourtCourt of Appeals for the Seventh Circuit
DecidedDecember 23, 2013
Docket13-1956
StatusPublished
Cited by25 cases

This text of 738 F.3d 810 (Aeroground, Inc. v. CenterPoint Properties Trust) is published on Counsel Stack Legal Research, covering Court of Appeals for the Seventh Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Aeroground, Inc. v. CenterPoint Properties Trust, 738 F.3d 810, 2013 WL 6731478, 2013 U.S. App. LEXIS 25572 (7th Cir. 2013).

Opinion

FLAUM, Circuit Judge.

In 2007, two companies — Menzies and CenterPoint — entered into a ten-year lease for a warehouse near O’Hare Airport. CenterPoint, the lessor, owns the warehouse; Menzies, the lessee, operates an air cargo handling business, which includes the use of 15,000- and 30,000-pound fork *812 lifts. It did not take long for these heavy forklifts to severely damage the concrete slab on which the machines operated. The parties dispute who is responsible for fixing the damage, at a cost of about $1 million. Under the lease, Menzies is responsible for repairing the warehouse’s “floor,” while CenterPoint is responsible for repairing its “foundation.” Menzies sued. After a bench trial, the district court concluded that the damage affected only the surface of the concrete slab — i.e., it affected the slab’s function as a floor, not its function as a foundation. Therefore, Menzies was not entitled to recover. We affirm.

I. Background

Aeroground Inc., which does business as Menzies Aviation (“Menzies”), operates an air cargo handling business. CenterPoint Properties Trust (“CenterPoint”) is a real estate investment trust that owns a warehouse near O’Hare Airport. The facility is a single-story structure — a 185,280 square-foot warehouse built in 1998 or 1999, plus a large addition built in 2007. Another company used the building to store airplane parts from 1999 until 2006.

In February 2007, Menzies and Center-Point entered into a lease for the building. After a dispute, the parties mutually terminated that lease and signed a new, ten-year lease in November 2007. Between February and November, CenterPoint constructed various improvements to the building, at Menzies’ request, including increasing the number of dock doors from two to thirty-eight and installing 45,000-pound dock levelers. These improvements cost CenterPoint about $1.4 million.

When Menzies began moving its air cargo handling operations into the building in November 2007, the six-inch concrete sláb did not exhibit any visible damage. By January 2009, the concrete slab had begun to deteriorate. The damage — “cracking, scaling of the concrete surface, and raveling along contraction joints” — was not consistent with typical wear and tear. The slab could not support Menzies’ heavy forklifts, which were typical of its field. Menzies told CenterPoint. about these problems in January 2009. CenterPoint paid for some repairs (at a cost of about $92,000), but then stopped doing so. Cen-terPoint did not submit an insurance claim. The parties agree that the concrete slab is so damaged that it must be replaced, at an estimated cost of between $966,000 (the cost of a new, identical floor) and $1.28 million (the cost of a new floor that would permit heavy forklift operation).

As relevant here, Menzies sued Center-Point for breach, and CenterPoint counterclaimed. Both parties contended that the other was responsible for replacing the concrete slab and had breached the lease by failing to replace the slab. After a bench trial, the federal district court held that neither party was entitled to recover. The court found that the concrete slab had a “dual nature as both floor and foundation,” but “the damage at issue was related to the slab’s function as a floor.” The damage was therefore Menzies’ responsibility since Menzies is responsible for the “floor” — not CenterPoint’s responsibility, which includes the “foundation.” However, CenterPoint lost on its counterclaim, because the lease required that it give timely notice to Menzies if Menzies allegedly breached, and CenterPoint did not do so. Only Menzies appeals.

II. Discussion

In an appeal from a bench trial, we review for clear error the district court’s findings of fact and its applications of law to those findings of fact. Egan Marine Corp. v. Great Am. Ins. Co. of New York, 665 F.3d 800, 811 (7th Cir.2011). A finding is “clearly erroneous” *813 when, even though there is evidence to support it, “the reviewing court on the entire evidence is left with the definite and firm conviction that a mistake has been committed.” Winforge, Inc. v. Coachmen Indus., 691 F.3d 856, 868 (7th Cir.2012) (quoting United States v. United States Gypsum Co., 333 U.S. 364, 395, 68 S.Ct. 525, 92 L.Ed. 746 (1948)). “The party alleging error bears the burden of demonstrating that particular factual findings were clearly erroneous.” Id. We review de novo the district court’s interpretation of a contract as well as its conclusion that a contract is ambiguous. BKCAP, LLC v. CAPTEC Franchise Trust 2000-1, 572 F.3d 353, 358 (7th Cir.2009). If we find the contract ambiguous, then the district court’s interpretation is a factual one, reviewed for clear error. Wikoff v. Vanderveld, 897 F.2d 232, 238 (7th Cir.1990).

Where, as here, our jurisdiction is based on diversity, the resolution of substantive issues is determined by the applicable state law. LaSalle Nat. Bank v. Serv. Merch. Co., 827 F.2d 74, 78 (7th Cir.1987). The parties agree that Illinois law applies. Under Illinois law, the interpretation of a lease “is governed by the rules which govern contracts.” Midland Mgmt. Co. v. Helgason, 158 Ull.2d 98, 103, 196 Ill.Dec. 671, 630 N.E.2d 836 (1994). We therefore apply Illinois principles of contract interpretation. The goal of contract interpretation is to ascertain the parties’ intent, and in so doing, we first look to “the plain and ordinary meaning” of the contract language. Gallagher v. Lenart, 226 Ill.2d 208, 233, 314 Ill.Dec. 133, 874 N.E.2d 43 (2007). We must construe the contract “as a whole, viewing each part in light of the others.” Id. We also must seek to give effect to “each clause and word used,” without rendering any terms meaningless. Hufford v. Balk, 113 Ill.2d 168, 172, 100 Ill.Dec. 564, 497 N.E.2d 742 (1986). The more specific provision of a contract governs where it arguably conflicts with a more general provision. Grevas v. U.S. Fidelity & Guar. Co., 152 Ull.2d 407, 411, 178 Ill.Dec. 419, 604 N.E.2d 942 (1992).

A. The terms of the lease

We begin by summarizing the lease’s terms.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
738 F.3d 810, 2013 WL 6731478, 2013 U.S. App. LEXIS 25572, Counsel Stack Legal Research, https://law.counselstack.com/opinion/aeroground-inc-v-centerpoint-properties-trust-ca7-2013.