Carter v. A. I. Root, Inc.

121 N.W. 952, 84 Neb. 723, 1909 Neb. LEXIS 250
Nebraska Supreme Court·Decided June 11, 1909·No. No. 15,272·Published·Cited by 12 cases

Opinion

Epperson, C.

July 14, 1904, the • plaintiff, a contractor and builder, and the defendant, A. I. Root, Incorporated, entered into a written contract whereby the plaintiff for a stipulated compensation agreed to construct a certain building for the defendant. Said agreement contained the following [724] provision: “No alterations shall he made in the work shown or described by the drawings and specifications except upon a written order of the architect, and when so made the value of the work added or omitted shall be computed by the architect and the amount so ascertained shall be added to or deducted from the contract price.” The contract provided that the building was to be completed on or before October 15, 1904, and that the contractor should pay to the owner $10 for each day thereafter that the work remained in an incomplete condition as liquidated damages sustained by the owner; the same to be deducted from the contract price. But it was further provided: “Should the contractor be obstructed or delayed in the prosecution or completion of his work by the act, neglect, delay or default of the owner, or the architect, or of any other contractor employed by the owner upon the work, then the time herein fixed for the completion of the work shall be extended for a period equivalent to the time lost by reason of any or all of the causes aforesaid; but no such allowance shall be made unless a claim therefor is presented in writing to the architect' within 24 hours of the occurrence of such delay. The duration of such extension shall be certified to by the architect, but appeal from his decision may be made to arbitration, as provided in article 3 of this contract.” The construction of the building by the plaintiff was to be under the direction and to the satisfaction of the architect, who by the express provisions of the contract was made the agent of .said owner. The specifications, which were referred to in the contract and which are necessarily a part thereof, contained the following provision: “At any time the architect directed by the owner may require alterations, additions or omissions from the contract and the same shall not affect the validity of the contract, but the price of such work shall be added to or deducted from the contract price as the case may be. * * * But extra work will be paid for only when the price has been agreed upon and affixed to [725] the order given by the architect in writing and countersigned by the owner previous to the performance of the same. Such order for work must be produced and surrendered at the final settlement or no payment for such work will be made.” Provisions were made for the arbitration of Avhatever disputes might arise as to compensation for extras. After the completion of said building, and within the time authorized by law, the plaintiff filed his lien against the defendant’s property, claiming that there was due upon the original contract the sum of $4,712, and that there was due to him for extras $4,026.22, and that he had been damaged by the defendant in the sum of $1,500 for delays in the construction of said building caused by the defendant. The claim for damages was subsequently abandoned, and no further reference will be made thereto in this opinion.

This action was instituted to foreclose the plaintiff’s lien. Defendant admitted the written contract, and also admitted liability for some of the extras pleaded by plaintiff, and denied others. He pleaded a counterclaim, which included an item of $1,500 damages for plaintiff’s delay in the construction of the building. The lovver court rejected defendant’s claim for damages, and found that the plaintiff was entitled to credit for the original contract price, $18,821, and for extras, $1,772.02, and that he was chargeable with the following: Cash paid during the construction of building, $14,385.15; for small items of defendant’s counterclaim, $174.10; for amount paid by defendant to subcontractors upon liens by them filed, $6,823.01. The difference being in favor of the defendant, the trial court gave him ■ j udgment therefor, which, with allowances for interest, amounted to $681.61. The defendant, contending that he is entitled to a larger judgment, has appealed to this court.

Two questions are presented for determination: First, is the plaintiff entitled to recover for the disputed extras claimed? Second, is the defendant entitled to recover damages for 'the delay in completing the building? Of [726] the extras alloAved to the plaintiff by the trial court, the defendant admits $771.39. Liability for other extras are admitted, but the amounts disputed. Such items aggregate $392.33 as allowed by the trial court. The evidence as to the value of these extras is conflicting. A discussion of it is unnecessary. We adopt the findings of the trial court and give credit therefor to the plaintiff. This leaves in controversy $608.30 allowed by the lower court.

Free access — add to your briefcase to read the full text and ask questions with AI

Carter v. A. I. Root, Inc., 121 N.W. 952, 84 Neb. 723, 1909 Neb. LEXIS 250 (Neb. 1909).

121 N.W. 952 (Carter v. A. I. Root, Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Gesell v. Reeves
429 N.W.2d 363 (Nebraska Supreme Court, 1988)
Fauss Construction, Inc. v. City of Hooper
249 N.W.2d 478 (Nebraska Supreme Court, 1977)
Abel Construction Co. v. School District of Seward
195 N.W.2d 744 (Nebraska Supreme Court, 1972)
Abel Construction Co. v. School District
195 N.W.2d 744 (Nebraska Supreme Court, 1972)
Parsons Construction Co. v. Metropolitan Utilities District
104 N.W.2d 272 (Nebraska Supreme Court, 1960)
Robinson Outdoor Advertising Co. v. Wendelin Baking Co.
15 N.W.2d 388 (Nebraska Supreme Court, 1944)
Olson Construction Co. v. Commercial Building & Investment Co.
256 N.W. 22 (Nebraska Supreme Court, 1934)
Nathan Elson & Co. v. H. Beselin & Son
218 N.W. 753 (Nebraska Supreme Court, 1928)
Rutherford v. Kahler
298 S.W. 9 (Supreme Court of Arkansas, 1927)
Jobst v. Hayden Bros.
129 N.W. 992 (Nebraska Supreme Court, 1911)