Carter v. A. I. Root, Inc.

121 N.W. 952, 84 Neb. 723, 1909 Neb. LEXIS 250
CourtNebraska Supreme Court
DecidedJune 11, 1909
DocketNo. 15,272
StatusPublished
Cited by12 cases

This text of 121 N.W. 952 (Carter v. A. I. Root, Inc.) is published on Counsel Stack Legal Research, covering Nebraska Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Carter v. A. I. Root, Inc., 121 N.W. 952, 84 Neb. 723, 1909 Neb. LEXIS 250 (Neb. 1909).

Opinion

Epperson, C.

July 14, 1904, the • plaintiff, a contractor and builder, and the defendant, A. I. Root, Incorporated, entered into a written contract whereby the plaintiff for a stipulated compensation agreed to construct a certain building for the defendant. Said agreement contained the following [724]*724provision: “No alterations shall he made in the work shown or described by the drawings and specifications except upon a written order of the architect, and when so made the value of the work added or omitted shall be computed by the architect and the amount so ascertained shall be added to or deducted from the contract price.” The contract provided that the building was to be completed on or before October 15, 1904, and that the contractor should pay to the owner $10 for each day thereafter that the work remained in an incomplete condition as liquidated damages sustained by the owner; the same to be deducted from the contract price. But it was further provided: “Should the contractor be obstructed or delayed in the prosecution or completion of his work by the act, neglect, delay or default of the owner, or the architect, or of any other contractor employed by the owner upon the work, then the time herein fixed for the completion of the work shall be extended for a period equivalent to the time lost by reason of any or all of the causes aforesaid; but no such allowance shall be made unless a claim therefor is presented in writing to the architect' within 24 hours of the occurrence of such delay. The duration of such extension shall be certified to by the architect, but appeal from his decision may be made to arbitration, as provided in article 3 of this contract.” The construction of the building by the plaintiff was to be under the direction and to the satisfaction of the architect, who by the express provisions of the contract was made the agent of .said owner. The specifications, which were referred to in the contract and which are necessarily a part thereof, contained the following provision: “At any time the architect directed by the owner may require alterations, additions or omissions from the contract and the same shall not affect the validity of the contract, but the price of such work shall be added to or deducted from the contract price as the case may be. * * * But extra work will be paid for only when the price has been agreed upon and affixed to [725]*725the order given by the architect in writing and countersigned by the owner previous to the performance of the same. Such order for work must be produced and surrendered at the final settlement or no payment for such work will be made.” Provisions were made for the arbitration of Avhatever disputes might arise as to compensation for extras. After the completion of said building, and within the time authorized by law, the plaintiff filed his lien against the defendant’s property, claiming that there was due upon the original contract the sum of $4,712, and that there was due to him for extras $4,026.22, and that he had been damaged by the defendant in the sum of $1,500 for delays in the construction of said building caused by the defendant. The claim for damages was subsequently abandoned, and no further reference will be made thereto in this opinion.

This action was instituted to foreclose the plaintiff’s lien. Defendant admitted the written contract, and also admitted liability for some of the extras pleaded by plaintiff, and denied others. He pleaded a counterclaim, which included an item of $1,500 damages for plaintiff’s delay in the construction of the building. The lovver court rejected defendant’s claim for damages, and found that the plaintiff was entitled to credit for the original contract price, $18,821, and for extras, $1,772.02, and that he was chargeable with the following: Cash paid during the construction of building, $14,385.15; for small items of defendant’s counterclaim, $174.10; for amount paid by defendant to subcontractors upon liens by them filed, $6,823.01. The difference being in favor of the defendant, the trial court gave him ■ j udgment therefor, which, with allowances for interest, amounted to $681.61. The defendant, contending that he is entitled to a larger judgment, has appealed to this court.

Two questions are presented for determination: First, is the plaintiff entitled to recover for the disputed extras claimed? Second, is the defendant entitled to recover damages for 'the delay in completing the building? Of [726]*726the extras alloAved to the plaintiff by the trial court, the defendant admits $771.39. Liability for other extras are admitted, but the amounts disputed. Such items aggregate $392.33 as allowed by the trial court. The evidence as to the value of these extras is conflicting. A discussion of it is unnecessary. We adopt the findings of the trial court and give credit therefor to the plaintiff. This leaves in controversy $608.30 allowed by the lower court.

It is contended that these items were not extras, but were embraced in the written contract. This evidence also is conflicting, and it is impossible for one who is not an architect or a builder to take the contract, the plans and the specifications, and from them alone to determine whether or not certain material furnished and certain work performed are contemplated and provided for by the contract, or are supplemental to or additions to the plan of the building previously arranged. It is apparent that on account of so many details it is very difficult after the work is completed to adjust the m’atters here in dispute. That the plaintiff did work in addition to what would have been required had the contract been strictly complied with is apparent; but it /is the defendant’s contention with reference to many of the items in controversy that the' additional work Avas made necessary because the plaintiff had first proceeded contrary to the contract, which necessitated the doing of the work over again in order to conform thereto. The defendant argues that he is not required to pay the same because no written order was given therefor as provided in the contract. The architect was the defendant’s agent and as such superintended the construction of the building, and it is claimed that he, acting for the defendant, ordered and directed certain alterations and changes to be made; that his directions were given orally and complied with by the plaintiff, and that the defendant, thus acting through his authorized agent, Avaived the provision of the contract requiring such alterations to be made in writing. There can be no doubt but that such a provision in a builder’s [727]*727contract is valid and that it will he enforced unless it is waived by the parties, nor is there any doubt but that the owner can waive such provisions by verbally entering into an agreement with the contractor for extras which would estop him from alleging the strict terms of the written contract for the purpose of defeating recovery for extra work performed or material furnished by the builder. Erskine v. Johnson, 23 Neb. 261. But did the verbal order of the architect in the case at bar amount to a waiver by the defendant of this provision of the written contract? A party to any contract may waive the provisions made for his benefit, but it is a rule requiring the citation of no authority for its support that an agent is bound by the terms of his agency. While tin; architect was the agent of the defendant, he was made so by the contract in controversy, and that contract expressly provided the manner in which the architect was authorized to-make any changes in the construction of the building.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Gesell v. Reeves
429 N.W.2d 363 (Nebraska Supreme Court, 1988)
Fauss Construction, Inc. v. City of Hooper
249 N.W.2d 478 (Nebraska Supreme Court, 1977)
Abel Construction Co. v. School District of Seward
195 N.W.2d 744 (Nebraska Supreme Court, 1972)
Abel Construction Co. v. School District
195 N.W.2d 744 (Nebraska Supreme Court, 1972)
Parsons Construction Co. v. Metropolitan Utilities District
104 N.W.2d 272 (Nebraska Supreme Court, 1960)
Robinson Outdoor Advertising Co. v. Wendelin Baking Co.
15 N.W.2d 388 (Nebraska Supreme Court, 1944)
Olson Construction Co. v. Commercial Building & Investment Co.
256 N.W. 22 (Nebraska Supreme Court, 1934)
Nathan Elson & Co. v. H. Beselin & Son
218 N.W. 753 (Nebraska Supreme Court, 1928)
Rutherford v. Kahler
298 S.W. 9 (Supreme Court of Arkansas, 1927)
Jobst v. Hayden Bros.
129 N.W. 992 (Nebraska Supreme Court, 1911)

Cite This Page — Counsel Stack

Bluebook (online)
121 N.W. 952, 84 Neb. 723, 1909 Neb. LEXIS 250, Counsel Stack Legal Research, https://law.counselstack.com/opinion/carter-v-a-i-root-inc-neb-1909.