Abel Construction Co. v. School District

195 N.W.2d 744, 188 Neb. 166, 1972 Neb. LEXIS 770
CourtNebraska Supreme Court
DecidedMarch 17, 1972
DocketNo. 38075
StatusPublished
Cited by11 cases

This text of 195 N.W.2d 744 (Abel Construction Co. v. School District) is published on Counsel Stack Legal Research, covering Nebraska Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Abel Construction Co. v. School District, 195 N.W.2d 744, 188 Neb. 166, 1972 Neb. LEXIS 770 (Neb. 1972).

Opinion

Clinton, J.

This is an action by Abel Construction Company, plaintiff, to recover from the defendant, School District of Seward, $5,175 alleged to be the balance owed upon a contract for the construction of an athletic track with a rubber asphalt resilient surface and other improvements at the Seward high school. The contract provided for liquidated damages of $75 for each day completion of the construction extended beyond the specified 60-calendar day “contract period.” The defendant had withheld the liquidated damages for a claimed completion delay of 69 days. The trial judge determined as a matter of law that since the plaintiff had failed to request in writing an extension of the contract period as provided for in the construction contract the only question to be decided was, the extent of the delay, and he therefore submitted to the jury the question of whether the contract was completed September 1, 1967, or September 8, 1967. The jury returned a verdict for the plaintiff in the amount of $525. The plaintiff appealed. We affirm the verdict and the judgment.

The plaintiff in its petition pled the contract by the incorporation of a copy thereof, admitted it had not [168]*168completed the construction within the time provided in the contract, and alleged that the work was completed September 1, 1967, which was 60 days after the stipulated contractual completion date. It alleged that the delay was excusable because: (a) Rain during the period May 27, 1967, to July 3, 1967, was so far in excess of normal and in such quantity that construction could not take place during that period, (b) The defendant was responsible for a portion of the delay because a testing laboratory hired by the defendant did not complete determination of the “leveling mix” and the “rubber mix” and furnish the same to the plaintiff until June 20 and 23, 1967. (c) The rubber manufacturer’s representative was required to be present at the laying of the resilient layer and through no fault of the plaintiff he was not able to be present until July 24, 1967.

The plaintiff further pled that the contractual provision for liquidated damages was void because it constituted a penalty and alleged that the defendant suffered no actual damage because of the delay.

The defendant in its answer pled specifically various provisions of the contract upon which it relied and to which we will refer in this opinion as required, including the failure of the plaintiff to request an extension of time in accordance with contract provisions. In an amended reply filed on the day trial began plaintiff alleged an estoppel to rely upon this contract provision because an employee of the defendant’s engineer, one Charles Kemery, had told the plaintiff “not to worry about liquidated damages, as time lost would be adjusted by” the engineer.

The principal issues on appeal as raised by the assignments of error are: (1) Is the contract provision for liquidated damages void? (2) The effect, as related to the matters pled in excuse, of the contract provision requiring that the contractor request in writing extensions of the “contract period” and the effect thereon of the [169]*169statement of Kemery. All of which of course reaches the question of the propriety of the partial direction of the verdict by the trial court.

We first discuss the validity of the provision for liquidated damages. The contract provided: “Work shall be commenced within 10 days from the date of the written Notice to Proceed and shall be completed within sixty (60) calendar days after the date of the Notice to Proceed. . . . Liquidated Damages. As time is an essential element of the contract, all work shall be completed within the contract period. For each calendar day that any work remains uncompleted after the end of the contract period, the amount of Seventy Five Dollars ($75.00) per calendar day will be assessed, not as a penalty, but as a predetermined and agreed amount to be used to pay, in part, any additional engineering expenses incurred by the Owner after the end of the contract period.”

At the trial evidence was adduced by defendant to show that: Because of the delay the defendant incurred additional engineering expenses of $1,137.16; it incurred in unascertainable amounts additional expense in moving bleachers which would have been avoided had the work been completed in time so that the movement could have been made with regular employees; it was unable to use for a period of time some associated athletic facilities; there was expense and inconvenience in protecting the work while it cured which would have been avoided; and there were other items of inconvenience to the school and public to which no monetary valuation could be affixed. The total contract price was $80,896.98.

This court has had occasion previously to consider the question as to whether a liquidated damage provision similar to that here is valid. In Parsons Constr. Co. v. Metropolitan Utilities Dist., 170 Neb. 709, 104 N. W. 2d 272, the court had before it such a provision calling for liquidated damages of $150 per day. We there said: “In the case of Stanford Motor Co. v. Westman, 151 Neb. [170]*170850, 39 N. W. 2d 841, this court held: As a general rule, the question of whether a sum mentioned in a contract is to be considered as liquidated damages, or as a penalty is a question of law, dependent on the construction of the contract by the court.’ The court cited 15 Am. Jur., Damages, § 246, p. 678, as follows: Tn such cases the court must find out whether the payment stipulated is in truth liquidated damages or a penalty. The question whether it is the one or the other is a question of law and one quite independent of the agreement of the parties to call it the one or the other.’ The court further said: ‘We said in Gustin & Co. v. Nebraska Building & Investment Co., 110 Neb. 241, 193 N. W. 269: “. . . where the damages are uncertain, and not readily capable of exact ascertainment by any known rule, and the parties surveyed the whole situation at the time of contract, and agreed upon the amount of damages, in case of a breach in the contract to construct a building by a certain time, such sum, in case of a breach, is the true measure of recovery and is liquidated damages and not a penalty.” ’ The court further held: ‘If the damages arising from a breach of the contract are difficult of ascertainment or admeasurement, and if the stipulated amount is not disproportionate to the amount of damages that may be reasonably anticipated from the breach, it will usually be regarded as a provision for liquidated damages.’ See, also, Sofio v. Glissmann, 156 Neb. 610, 57 N. W. 2d 176; Edgar v. Anthes, 109 Neb. 546, 191 N. W. 682.”

At 5 Williston on Contracts (3d Ed.), § 785, p. 733, we find the following: “It is commonly provided in building and construction contracts that there shall be deducted from the contractor’s compensation a fixed sum for each day’s delay in performing the contract beyond the day fixed therein. Such damages are obviously graded according to the extent of the breach, increasing proportionately with each day’s delay. Moreover, each day’s delay, while unquestionably injurious, is in[171]*171jurious frequently in ways that are difficult to estimate. Accordingly, unless the sum fixed in the contract is very unreasonable the provision is treated as one for liquidated damages.” See, also, 5 Corbin on Contracts, § 1072, p. 402. We hold that the trial court’s determination that the contract provision for liquidated damages was not penal is correct.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Berens & Tate v. Iron Mt. Info. Mgmt.
747 N.W.2d 383 (Nebraska Supreme Court, 2008)
Bieluch v. Smith, No. Cv 91 56050 (May 26, 1993)
1993 Conn. Super. Ct. 5134 (Connecticut Superior Court, 1993)
Rohlin Construction Co. v. City of Hinton
476 N.W.2d 78 (Supreme Court of Iowa, 1991)
Vrgora v. Los Angeles Unified School District
152 Cal. App. 3d 1178 (California Court of Appeal, 1984)
Ryder Truck Rental, Inc. v. Transportation Equipment Co.
339 N.W.2d 283 (Nebraska Supreme Court, 1983)
Board of Library Trustees v. Fidelity & Deposit Co.
429 N.E.2d 203 (Appellate Court of Illinois, 1981)
Growney v. C M H Real Estate Co.
238 N.W.2d 240 (Nebraska Supreme Court, 1976)
Growney v. CMH Real Estate Co.
238 N.W.2d 240 (Nebraska Supreme Court, 1976)

Cite This Page — Counsel Stack

Bluebook (online)
195 N.W.2d 744, 188 Neb. 166, 1972 Neb. LEXIS 770, Counsel Stack Legal Research, https://law.counselstack.com/opinion/abel-construction-co-v-school-district-neb-1972.