Sanitary District of Chicago v. McMahon & Montgomery Co.

110 Ill. App. 510, 1903 Ill. App. LEXIS 652
CourtAppellate Court of Illinois
DecidedOctober 9, 1903
StatusPublished
Cited by20 cases

This text of 110 Ill. App. 510 (Sanitary District of Chicago v. McMahon & Montgomery Co.) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sanitary District of Chicago v. McMahon & Montgomery Co., 110 Ill. App. 510, 1903 Ill. App. LEXIS 652 (Ill. Ct. App. 1903).

Opinion

Mr. Justice Stein

delivered the opinion of the court.

First. In contemplation of law Green’s Dredging Company was not a bidder, because its bid did not conform to the advertised requirements. The contract was let to the next lowest bidder, McMahon & Montgomery Company, at a price less than its bid, without any re-advertising, and it is now claimed that this avoided the contract. Ho authorities are cited to sustain the contention. If (so far as this point is concerned) it was lawful to let the company have the contract at the price (twenty-three cents) bid. by it—and this is not denied—then it was not contrary to the statute, or to public policy, or to the duty appellant owed to the public, for its trustees, by persuasion, to induce that company to consent to a reduction of the price from twenty-three to twenty-one cents. Mor was there anything unlawful in the permission given by the trustees to the successful bidder to associate with itself in the work other contractors and to let them sign the contract. In this way appellant only obtained additional security for its due execution, and for that purpose no further advertising or bidding was required.

Second. As appears from the foregoing statement, there was no advertising or bidding in respect of the work involved in the building of the collateral channel and the paragraph in the contract relating to it was omitted from the special count. It is therefore insisted that a fatal variance exists between the proof and the declaration, and that the instrument sued on is void as an entirety. As both these objections rest upon the same foundation, they will be considered together. Before doing so, it is proper to state that if the contract was not admissible under the special count, it was not admissible at all. It conld not be received under the common counts. It does not in express terms obligate appellant to furnish the right of way. If such obligation exists it arises by implication of law from the expressed terms. Hence it was for the pleader either to declare upon the instrument, according to its alleged legal effect, or to set it forth in Jiaec verba to enable the court to determine whether the obligation existed. The rule is that the common counts are sufficient when nothing remains to be done under the contract, i. e., when it is completely executed. Here, so far as the cause of action upon which a recovery was sought is concerned, the contract was and is wholly unexecuted. Appellees do not sue for the price of work done and materials furnished; that has all been paid. They sue for damages resulting from the non-performance of an implied covenant.

That an agreement, such as the one at bar, if entered into without the preliminary advertising and bidding prescribed by the statute, is void and affords no basis for a recovery, is the settled law of the state. (Dement v. Rokker, 126 Ill. 194; Littler v. Jayne, 124 Ill. 123; Sanitary District v. Lee, 79 Ill. App. 159.) The case of Johnson v. Sanitary District, 163 Ill. 285, cited by appellees, is not in conflict with these decisions, and lays down no contrary rule. There it was sought by a mandatorjr injunction to compel the awarding of a contract to one of several bidders. The application was denied on the ground that “ the discretion vested by the statute in a municipal board to let a contract for public work to the lowest responsible bidder, and to re ject any and all bids, is judicial in its nature, and will not be controlled by the courts.” The case does not hold and can not be construed as holding that if such a contract were sued on and it appeared that it had been made without advertising for bids, it would not be declared void.

It is urged, however, that the provisions relating to the collateral channel are severable from the rest of the instrument, and that in substance and effect it embodies two separate and independent contracts. By clause 7 of section B the price for excavating the collateral channel was fixed at 19.9 cents per cubic yard, whereas for doing the same work on the main channel appellees were to be paid twenty one cents for each cubic yard. As required by the contract, the engineer in preparing his progress certificates and final certificate, kept the number of; yards excavated in the one channel separate and apart from the number of yards excavated in the other, and separate vouchers were issued. All the provisions relating to either are easily separable from those relating to the other. Indeed, one would expect this to be the case when it is remembered that the building of the collateral channel was an afterthought, and not contemplated or referred to in the original advertisement and bids. The first mention of this channel appears in the proceedings of appellant’s board of trustees had on May 2,1894, the very day of the date of the instrument in suit. In Keeler v. Clifford, 165 Ill. 544, the court say:

“ Whether a contract is entire or severable, can not be determined by any precise rule, but must depend upon the intention of the parties, to be ascertained in each case from the language employed and the subject-matter of the contract.”

They then cite with approval from 2 Parsons on Contracts, marg. p. 517:

“ If the part to be performed by one party consists of several distinct and separate items, and the price to be paid by the other is apportioned to each item to be performed, or is left to be implied by law, such a contract will generally be held to be severable. And the same rule holds where the price to be paid is clearly and distinctly apportioned to different parts of what is to be performed, although the latter is in its nature single and entire.” .

Applying these rules, we have here two distinct contracts, as to one of which the requirements of the statute in the matter of advertising and receiving bids were complied with, and as to the other they were not. No recovery is sought in respect of the latter. If the parties, instead of putting both in the same paper, had executed and signed two, one relating to the main channel and the other to the collateral, and had complied with the statute as to the main channel and not as to the collateral, no one would contend that the failure in respect of the latter would taint or in anywise affect the validity of the former. In legal effect the situation is the same.

Third. The work contemplated by the contract could not be done without the right of way being procured by somebody. From the very first the attitude of appellant was that this duty rested upon it, and such seems to be the opinion of its counsel; for they argued with much force that paragraph 7c and the last sentence of paragraph 7 in section D of the contract were put into it for the express purpose of allowing appellant the necessary time for procuring the right of way. In its instructions tendered to but refused by the court, notably numbers 19 and 20, appellant conceded its obligation to procure the right of,way. That this construction of the contract by appellant, whose interest lay in precisely the other direction, is correct, admits of no doubt.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Smith v. Intergovernmental Solid Waste Disposal Ass'n
605 N.E.2d 654 (Appellate Court of Illinois, 1992)
Leo Michuda & Son Co. v. Metropolitan Sanitary District
422 N.E.2d 1078 (Appellate Court of Illinois, 1981)
Keeshin v. Levin
334 N.E.2d 898 (Appellate Court of Illinois, 1975)
Inc. Town of Bono v. Universal Tank & Iron Works
395 S.W.2d 330 (Supreme Court of Arkansas, 1965)
State Ex Rel. Russell County v. Fourth National Bank
117 So. 2d 145 (Supreme Court of Alabama, 1959)
Township of Hillside v. Sternin
136 A.2d 265 (Supreme Court of New Jersey, 1957)
Sutton v. City of St. Paul
48 N.W.2d 436 (Supreme Court of Minnesota, 1951)
Biddison v. Whitman
39 A.2d 800 (Court of Appeals of Maryland, 1944)
Belding v. State
12 Ill. Ct. Cl. 438 (Court of Claims of Illinois, 1943)
Iowa Electric Co. v. Town of Cascade
288 N.W. 633 (Supreme Court of Iowa, 1939)
Spelina v. Sporry
279 Ill. App. 376 (Appellate Court of Illinois, 1935)
Worthington v. Cleveland Lumber Co.
80 So. 688 (Alabama Court of Appeals, 1918)
Illinois Life Insurance v. Beifeld
184 Ill. App. 582 (Appellate Court of Illinois, 1914)
Griffiths v. Sanitary District
174 Ill. App. 100 (Appellate Court of Illinois, 1912)
Winslow Bros. v. Robinson
173 Ill. App. 84 (Appellate Court of Illinois, 1912)
Strobel Steel Construction Co. v. Sanitary District of Chicago
160 Ill. App. 554 (Appellate Court of Illinois, 1911)
J. E. Salfisberg & Co. v. City of St. Charles
154 Ill. App. 531 (Appellate Court of Illinois, 1910)
Carter v. A. I. Root, Inc.
121 N.W. 952 (Nebraska Supreme Court, 1909)
Baltimore & Ohio Railroad v. Jolly Bros. & Co.
71 Ohio St. (N.S.) 92 (Ohio Supreme Court, 1904)

Cite This Page — Counsel Stack

Bluebook (online)
110 Ill. App. 510, 1903 Ill. App. LEXIS 652, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sanitary-district-of-chicago-v-mcmahon-montgomery-co-illappct-1903.