Griffiths v. Sanitary District

174 Ill. App. 100, 1912 Ill. App. LEXIS 248
CourtAppellate Court of Illinois
DecidedOctober 22, 1912
DocketGen. No. 17,125
StatusPublished
Cited by1 cases

This text of 174 Ill. App. 100 (Griffiths v. Sanitary District) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Griffiths v. Sanitary District, 174 Ill. App. 100, 1912 Ill. App. LEXIS 248 (Ill. Ct. App. 1912).

Opinion

Mr. Presiding Justice Clark

delivered the opinion of the court.

This controversy arises out of a contract entered into by the appellants with the appellee, hereinafter referred to respectively as the plaintiffs and defendant, for the excavation of the rock and earth in a portion of the main drainage canal of the Sanitary District of Chicago, described as section one, and for the construction of certain work incident thereto. The action was assumpsit, the declaration containing the common counts and an additional count which alleges:

“That the defendant being a body politic and corporate, organized under an act of the legislature, entitled ‘An Act to create Sanitary Districts and to remove obstructions from the Desplaines and Illinois Rivers/ approved and in force July 1, 1889, having duly advertised for bids as required by law for the work contemplated by the agreement in said count mentioned, and having made and entered into a certain written agreement with plaintiffs in and by which plaintiffs were employed to do all the work and to furnish all the materials, tools, explosives, labor and all appliances required by said agreement in the manner and under the directions therein stipulated that should be necessary for the complete excavation and entire removal of earth, rock, glacial drift and other material from section 1 of defendant’s Main Drainage Channel; to construct certain retaining walls at the sides of said channel, to be laid in cement mortar, to lay certain slope paving and to deliver certain material for the construction of a certain levee adjacent to said channel, agreed in and by said contract to pay the plaintiffs 80 cents per cubic yard for such rock excavation, 0.429 per cubic yard for such glacial drift excavation, $2.90 per cubic yard for such retaining wall, 20 cents per cubic yard for such levee material, and 60 cents per cubic yard for such slope paving, from time to time as said work progressed; that plaintiffs promptly entered upon the performance, of said work and completed the same on or about November 1, 1897, to the satisfaction of the defendant and its chief engineer; and defendant on or about November 24, 1897, by a resolution of its Board of Trustees accepted the said work upon the report and certificate of the chief engineer, that the same had been completed and performed to the satisfaction of said chief engineer.
“That, in order to induce plaintiffs to enter into said agreement and to perform the work required therein, defendant, well knowing that plaintiffs would not be required to excavate to exceed 1,160,801 cubic yards of earth from said channel, nevertheless represented to plaintiffs in and by its advertisement for bids and by the terms of said agreement that plaintiffs would be required in the performance of said agreement to excavate approximately 1,662,476 cubic yards of such earth or glacial drift from said channel; that plaintiffs believing that defendant had ascertained the approximate quantity of earth to be so excavated refrained from making any independent investigation in regard thereto, and being ignorant of the actual or approximate quantity of glacial drift to be so excavated, but relying upon and believing in the truth of said representation of the defendant, in consideration thereof, entered into said agreement with defendant and agreed to perform the several classes of work at the various prices set out in the first count; that plaintiffs thereupon purchased a large plant, tools, and machinery for the excavation of the aforesaid 1,662,476 cubic yards of earth or glacial drift at a cost to them of $65,000, which was the fair and reasonable value of said plant, tools and machinery; that said work was performed to the satisfaction of the defendant and accepted by resolution of its Board of Trustees November 24, 1897; that plaintiff excavated all of the solid rock and glacial drift in said channel required to be excavated, to wit.: 1,160,801 cubic yards of earth or glacial drift, and 554,326 cubic yards of solid rock and constructed certain masonry slope paving, etc., as required by said contract; that defendant, though often requested, has refused and still refuses to pay plaintiffs for the excavation of the additional 501,601 cubic yards required to be excavated under said agreement, by means whereof the cost of the plaintiffs of the work required of and performed by plaintiffs under the terms of said agreement was increased by the addition thereto of the proportion of the cost of said plant, tools and machinery apportionable to 501,601 cubic yards of unexcavated earth, in the sum of $17,750.”

Other counts were added but abandoned. Fotir pleas were filed by the defendant, the first of which alleges payment; the second pleads the five year statute of limitations to all the alleged causes of action in the declaration; the third the ten year statute of limitations, and the fourth satisfaction and discharge.

The damages to the plaintiffs, as alleged in the declaration, were $150,000, the actual amount claimed being about $65,000. There was a trial before the court and a jury and a verdict rendered for the plaintiffs in the sum of $6,000. Motion for a new trial made by the plaintiffs was overruled and judgment entered upon the verdict, from which judgment this appeal has been prosecuted by the plaintiffs.

Errors are alleged in the admission and rejection of testimony; in the giving of certain instructions; in refusing to give instructions tendered by plaintiffs and in the modification of certain instructions tendered by the plaintiffs.

Work under the contract was completed about November 16, 1897. Suit was brought February 16, 1898, and a declaration consisting of the common counts filed on the same day. The one additional count relied upon, heretofore set forth, was filed November 15, 1907.

On November 29, 1897, a release was executed by the plaintiffs as follows:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Opinion No. 68-103 (1968) Ag
Oklahoma Attorney General Reports, 1968

Cite This Page — Counsel Stack

Bluebook (online)
174 Ill. App. 100, 1912 Ill. App. LEXIS 248, Counsel Stack Legal Research, https://law.counselstack.com/opinion/griffiths-v-sanitary-district-illappct-1912.