Sanitary Dist. of Chicago v. Ricker

91 F. 833, 34 C.C.A. 91, 1899 U.S. App. LEXIS 2072
CourtCourt of Appeals for the Seventh Circuit
DecidedFebruary 7, 1899
DocketNo. 511
StatusPublished
Cited by10 cases

This text of 91 F. 833 (Sanitary Dist. of Chicago v. Ricker) is published on Counsel Stack Legal Research, covering Court of Appeals for the Seventh Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sanitary Dist. of Chicago v. Ricker, 91 F. 833, 34 C.C.A. 91, 1899 U.S. App. LEXIS 2072 (7th Cir. 1899).

Opinion

WOODS, Circuit Judge,

after stating the facts, delivered the opinion of the court.

We are of opinion that the decree under review rests upon an erroneous theory. The contract which the court ordered annulled was made hy parties dealing at arm’s length. The sanitary district stood, in no relation of trust or confidence, and owed no duty, to proposing contractors. The trustees of the district and their chief engineer, it might well be said, were bound in duty to the public to use diligence to obtain such knowledge of the conditions to be dealt with as was necessary to enable them, in letting contracts, to conserve the public interests, but there has been pointed out no provision in the statute whereby the drainage district was created and the powers of its officers defined, which required that information concerning the nature of materials to be excavated should be collected for the benefit of bidders, and for the assertion of such duty on the general principles of law or equity.there is, we believe, no foundation in authority or reason. If conceded, the proposition would mean that every representation made by public officials or trustees, appointed to obtain proposals for the execution of a public work, amounts to a warranty either that the representation is true or that experienced and skillful agents had been employed to obtain the information on which it was made, and that the agents had followed the best known methods and had been guilty of no negligence in the discharge of their duties; or, to say the least, that, if such representations are not to be regarded as warranties, either of the truth of the statements or of due diligence used to make them true, they do demonstrate, if they turn out to be untrue, a mutual mistake of the parties, by reason of which the bidder may abandon his contract, once he' discovers in the course of performance that the representations Were false or mistaken. The books would be searched in vain for precedents or principles to sustain such a doctrine. The possibilities which it would involve of peril to public interests are infinite. It would take from the contractor, and impose on the public, all undiscovered contingencies and risks, which by diligence might have been found out, incident to the construction of public works.

If in this case, the trustees or their engineer were at fault for employing unskilled men to malee the borings in section E, the breach of duty was to the public, as represented by the drainage district, and the appellees had no ground for complaint, even assuming that the profile by which they are said to have been misled had purported, to- give information full and definite enough to justify reliance upon it, unless, by somebody authorized to speak for the district, they were purposely induced to believe that the borings had been skillfully made and tabulated. The bill contains no averment of the lack of skill'or of-negligence on the part of those who were employed to conduct the borings, and it is not pretended that the appellees supposed [841]*841that they were made by the chief engineer, Williams, in person: When, therefore, he declared to them his belied that the data of the profile were reasonably reliable, they knew that he was expressing only an opinion; and, as their own testimony shows, they did not inquire how or from what the profile was made up, or how and by whom the borings were made. The only reason Williams gave for his belief, that the dala could be regarded as reliable was that the “determinations were carefully taken and tabulated”; and by that he did not mean, and was not understood to mean, that he had any knowledge of the degree of care with which (he borings had been conducted and the results first noted. That neither he nor Kicker and Weston treated the profile as affording full and satisfactory information, as it plainly did not, is shown by the fact that, when they spoke of their intention to go down the line, he declared it a good idea, and suggested that they examine the spoil bank of the Illinois and Michigan canal, which he thought would afford as good evidence as any they could find of what they would meet with in digging the canal. One of the appellees has testified, and the master has found, that in making their bid the appellees relied upon the data found on the profile which they were allowed to examine; but that finding, at best, is only partially true. The appellees were aided by and were acting upon the advice of their own engineer, who was interrogated upon the point three or more times, with the evident purpose to procure an answer like that, of his employer; but he adhered steadily to the statement, “We relied upon the information which we obtained from the engineering department of the sanitary district, and our observation of the spoil bank of the Illinois and Michigan canal.” Cooley distrusted the data furnish (id by his own borings, and it is not strange that Weston was unwilling to say that he relied alone upon the indefinite data of the profile shown him. His testimony shows that they made inquiries of two others in the engineering department: besides Williams, and that they applied to him not in his official capacity, but individually, “for such information as he had personally of this ground, outside of what he had been able to gather.” They examined the spoil bank of the canal more than once, and, finding only tractable material, were of course the more ready to believe that the material described on the profile, (hough without any statement whether it was hard or not', was also tractable; and by the same logic Williams, who presumably had examined the spoil bank, had a right to believe, and to say to the appellees that lie thought, the notations on the profile reliable. If there was a failure to examine the spoil hank of the canal with due care, the opportunity was open alike to both, and neither may complain of (he other on that score. It will not do to say that the appellees were not put upon inquiry, or that the profile caused them to refrain from inquiry. From the examination of the profile and other documents in the engineer's office, and from their talks with Williams and others in his office, (hey proceeded forthwith to make inquiry; and if not: with sufficient care, the fault was their own.

We have proceeded thus far on (he assumption that what the engineer said about the profile was in some measure binding, upon [842]*842the board of trustees or the drainage district. While we do not question that the master was right in finding, or assuming, that the engineer had authority to exhibit the profile to contractors, though it was not a part of the specification and plans referred to in the advertisement for proposals, it does not follow, and no facts or circumstances are reported from which it may be inferred, that he had authority to bind the board of trustees or the district by representations of fact outside of the papers which he was authorized to show, and certainly not by expressions of opinion and belief or the grounds thereof. If his statement that he thought the data of the profile trustworthy was in any wise binding on the board of trustees, equally binding, and, as it turned out, equally untrue, was his suggestion that the spoil bank of the canal would be as good evidence as any to be had.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

M. F. Kemper Construction Co. v. City of Los Angeles
235 P.2d 7 (California Supreme Court, 1951)
Blassingame v. Greenville County
147 S.E. 848 (Supreme Court of South Carolina, 1929)
City of Lima v. Farley
7 F.2d 40 (Sixth Circuit, 1925)
Cement Products Co. v. County of Martin
172 N.W. 702 (Supreme Court of Minnesota, 1919)
Cuyahoga Contracting Co. v. City of Port Huron
233 F. 346 (Sixth Circuit, 1916)
Griffiths v. Sanitary District
174 Ill. App. 100 (Appellate Court of Illinois, 1912)
Sells v. City of Chicago
201 F. 874 (Seventh Circuit, 1912)
Bates County v. Wiles
190 F. 522 (Eighth Circuit, 1911)
Hein v. Westinghouse Air Brake Co.
172 F. 524 (U.S. Circuit Court for the Northern District of Illnois, 1909)

Cite This Page — Counsel Stack

Bluebook (online)
91 F. 833, 34 C.C.A. 91, 1899 U.S. App. LEXIS 2072, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sanitary-dist-of-chicago-v-ricker-ca7-1899.