Blassingame v. Greenville County

147 S.E. 848, 150 S.C. 167, 1929 S.C. LEXIS 128
CourtSupreme Court of South Carolina
DecidedFebruary 19, 1929
Docket12597
StatusPublished
Cited by6 cases

This text of 147 S.E. 848 (Blassingame v. Greenville County) is published on Counsel Stack Legal Research, covering Supreme Court of South Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Blassingame v. Greenville County, 147 S.E. 848, 150 S.C. 167, 1929 S.C. LEXIS 128 (S.C. 1929).

Opinions

The opinion of the Court was delivered by

Mr. Justice Cothran.

I do not concur in the affirmance of the circuit decree as proposed in the opinion of Mr. Justice Carter for the reasons which follow.

The complaint contains two separately stated causes of action, based upon practically the same right, to1 have a certain contract entered into between the plaintiff and Green-ville County, for the construction of what is known as the Geer highway, rescinded, and that he be allowed compensation for the work done by him upon the basis of quantummeruit, which he fixes at $68,620.69.

It appears that in the fall of 1922, Greenville County decided to construct an entirely new highway, leaving the old road to Csesar’s Head near Cleveland and passing up the mountains by Caesar’s Head and on to' the North Carolina line near Cedar Mountain, connecting there with a road from the state line to Brevard, N. C. The construction of the highway, afterwards known as the Geer highway, was placed in the hands of the State Highway Department as provided by law. The County of Greenville took no active part in the work; its connection with the enterprise was to pay the bills as they were approved by the Highway Department.

The Highway department made extensive surveys of the route, prepared maps, profiles, plans, specifications, and the contract which was made in the name of Greenville County. Bids were called for the advertisement based upon the data prepared by the Department and on file in its office.

The bids were made upon various units of construction, common excavation, solid rock excavation, and many others. *203 The bid of the plaintiff Blassingame, upon its face, as a whole, appeared not to be the lowest; the lowest was that of one Jordan. Blassingame’s bid on solid rock excavation was $1.50 per cubic yard; that of Jordan, $1. Blassingame’s bid on solid rock excavation was the highest for this particular unit named by any of the bidders.

The estimated quantity of solid rock upon the entire line through the mountains, as per the survey and estimate of the engineer of the Highway Department, and upon which bids were called for and made, was 12,716 cubic yards. An excess of 20 per cent, was allowed over this estimate for which compensation was to be made at the same rate.

After the bids had been submitted and upon consideration of the two bids of Blassingame and Jordan, which were the-two lowest, the engineer suggested to Blassingame that if the quantity of rock should considerably exceed the estimate, the Jordan bid would be the lower of the two, and that if he would modify his bid by agreeing to accept 75 cents per yard for all rock excavation in excess of the estimate of 12,-716 yards plus 20 per cent., the contract would be awarded to him. Without advising with Jordan about the proposed modification the contract was awarded to Blassingame upon his acceding to the suggestion of the engineer.

Blassingame commenced work in November, 1922. No rock was encountered until February, 1923. In August, 1923, the rock equaled the estimate of 12,716 yards, and by October, 1923, it had passed 12,716, plus 20 per cent., 2,543, 15,259 yards. The final estimate, June, 1925, showed a total yardage of 41,694 yards, an excess of 28,978 yards over the original estimate of 12,716 yards.

The contention of the plaintiff is that there was a mutual mistake of the parties as to the quantity of rock to be excavated; that he relied upon the original estimate of 12,-716 yards, plus 20 per cent.; that this was the basis of the contract into which he entered and that but for that reliance he would not have entered into it; that both he and the Highway Department were mistaken in the real quantity of rock; *204 and that he is therefore entitled to have the contract rescinded and to recover upon a quantum meruit for the work actually-done, which amounted to some 81,000 yards, which after deducting payments made as the work progressed entitled him to $68,620.69.

' The defendant filed a demurrer to the complaint upon the general ground, which was sustained by his Honor, Judge Mann, at November term, 1925. Upon appeal the order was reversed. Í34 S. C., 324, 132 S. E., 616.

At September term, 1926, the case by consent was referred to the Master for the trial of all equitable issues, including the question of waiver. The Master took the testimony, and on April 30, 1927, filed his report finding in favor of the defendant and recommending that the complaint be dismissed. Upon exceptions by the plaintiff to the Master’s report, the matter was heard by his Honor, Judge Bonham, at November term, 1927. He filed a decree dated December 19, 1927, reversing the Master’s conclusions, and from that decree the defendant has appealed upon exceptions which fairly raise the questions hereinafter considered.

The burden of the plaintiff’s complaint is that both he and the department made a great mistake in the estimate of solid rock excavation, upon which estimate he made his bid. The evidence shows that he made- no estimate at all; that he relied entirely upon the estimate of the department. The estimate was made, of course, in advance of the excavation, based upon external appearances.

The printed instructions to bidders contained this clause: “Familiarity With Proposed Work. The bidder is required to examine carefully the site of and the proposal, plans, specifications and contract form for the work contemplated, and it will be assumed that he has judged for and satisfied himself as to the conditions to be encountered, as to the character, quality and quantities of work to be performed and materials to be furnished, and as to the requirements of these specifications and contract.”

*205 I think that the Master has very correctly “sized up the situation” in the following language:

“Blassingame was anxious to get the job. In order to accomplish this purpose he visited the Chief Engineer in Columbia. He was told that his bid was not the lowest, but that if he would change his price on the rock excavation so as to charge 75 cents per cu. yd. for any excess above 12,-716 cu. yds., the contract might be awarded to him. Accordingly Blassingame changed his price for the rock excavation so as to charge $1.50 for rock excavation up to 12,716 cu. yds. and 75 cents for any excess above 12,716 cu. yds. Thereupon the contract was awarded to Blassingame without giving Jordan, the lowest bidder, the opportunity to meet Blassingame’s terms.
“Neither Blassingame nor the engineers- knew what amount of rock would have to be removed. According to the testimony, Blassingame thought it would not exceed 12,-716 cu. yds. The Engineer thought-that it would exceed this amount and so told Blassingame. The contract was made in contemplation of the uncertainty on this point. Blassingame assumed whatever risk was involved. His reason .may have been that assigned by one of his witnesses, Engineer R. T. Brown, who stated that Blassingame ‘felt that with the equipment he proposed to use, he should be able to handle the overrun at that price without loss.’ ”

The contract provides:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Howard v. Cox
Court of Appeals of South Carolina, 2005
L-J, Inc. v. South Carolina State Highway Department
242 S.E.2d 656 (Supreme Court of South Carolina, 1978)
City of Austin v. Cotten
509 S.W.2d 554 (Texas Supreme Court, 1974)
Mitchum v. Mitchum
190 S.E. 104 (Supreme Court of South Carolina, 1937)
Wilson v. Wilson
150 S.E. 897 (Supreme Court of South Carolina, 1929)

Cite This Page — Counsel Stack

Bluebook (online)
147 S.E. 848, 150 S.C. 167, 1929 S.C. LEXIS 128, Counsel Stack Legal Research, https://law.counselstack.com/opinion/blassingame-v-greenville-county-sc-1929.