MacArthur Brothers Co. v. United States

258 U.S. 6, 42 S. Ct. 225, 66 L. Ed. 433, 1922 U.S. LEXIS 2231
CourtSupreme Court of the United States
DecidedFebruary 27, 1922
Docket97
StatusPublished
Cited by35 cases

This text of 258 U.S. 6 (MacArthur Brothers Co. v. United States) is published on Counsel Stack Legal Research, covering Supreme Court of the United States primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
MacArthur Brothers Co. v. United States, 258 U.S. 6, 42 S. Ct. 225, 66 L. Ed. 433, 1922 U.S. LEXIS 2231 (1922).

Opinion

*7 Me. Justice McKenna

This is an action to recover damages for a breach of contract growing out of an alleged misrepresentation.

The appellant essayed recovery upon a petition to which a demurrer was sustained; it then filed an amended petition which was subjected to a like disposition, and then a second amended petition. Demurrer by the Government being sustained to that, appellant declined to amend again, and judgment was entered dismissing the petition. From the ruling this appeal is prosecuted.

The last petition is, as the others were, a very volumiious paper. It is enough to say that it sets forth a cause of action based upon a contract entered into by appellant with the United States, September 23, 1910,- for the construction of the west end of the new canal at Sault Ste. Marie, Michigan, which was authorized by the River and Harbor Act of March 2, 1907, c. 2509, 34 Stat. 1073, 1098. The petition details the specifications, but the misrepresentation is alleged to be that they and the contract represented that a portion of the work would be done in the “ dry ” and a portion in the wet ”, whereas it was impossible to do any of the work in the dry ”, arid it was all done in the wet ” at a cost greatly exceeding what it would have been had it been done the other way.

For. the purposes of permitting the work to be done in the dry, it was necessary to construct certain cofferdams and this was especially provided for by the specifications. One of the cofferdams was known as the West Cofferdam, and was to be built as a contract item and connected the rock spoil bank (extending along the north side of the work) with the old North West Pier. The latter pier was constructed by another contractor partly before and partly after the date the Company entered into its contract with the United States-. The Company was a bidder *8 for the work the specifications of which were published and accessible. When the contract in suit was entered into, that prior contract was in progress but not completed, and was not completed until after the Company-had begun work on its contract.

The Company, it alleges, made all reasonable inquiries and investigations upon the site of the contract between the date of advertisement and the date of submitting its bid, and, by its president and chief engineer, inspected the conditions. The work under the previous contract of March 23, 1908, was then in progress.

The Company estimated and believed, as it had a right to do, is its allegation, that the specifications of that contract had been and were being duly and properly performed. If they had been so performed, is the further allegation, the Company would have been able to perform, under its own contract in the dry, such portions of the work as were required by the contract to be done in the dry.

It was only during the progress of the work that the Company discovered that the previous contract had not been carried out and that the work was defective. In consequence, extraordinary and expensive means had to be resorted to for a continuance of the work, and the work was greatly delayed beyond the time that the Company would have had to take if the conditions had been as shown by the specifications of the previous contract and had the work been performed by the previous contractor according to the specifications.

This expense continued until July 3, 1913, and the de- . scription as dry work in the specifications was, by reason of the conditions existing at the site of the work, a misrepresentation of the character of the work to be done, and induced on the part of the Company a lower bid than would have been made if the conditions had been properly described.

*9 Owing to th& leakage coming through the old North West Pier, it was not practicable for excavation to be made in the dry. Notwithstanding, the engineer in charge compelled the work to be done as contracted for, and the Company sustained damages in the sum of |366,052.67 for which it prayed judgment.

It is contended that the circumstances detailed amount to a representation by the United States that the work could be done in the dry, but that it was impossible to so perform it and that, therefore, the resulting expense should be discharged by the Government and that the Court of Claims erred in dismissing the petition.

To these assertions the Government opposes denials: (1) There was no misrepresentation. (2) If there were it is not available to the Company since it had investigated conditions before, entering into the contract. (3) There was no misrepresentation as to the method by which the excavating could be done.

In considering the opposing contentions there must be taken into account certain provisions of the contract. It is therein provided that “ it is understood and agreed that the quantities given in these specifications are-approximate only, and that no claim shall be made against the United States on account of any excess or deficiency, absolute or relative, in the same. No allowance will be made for the failure of a bidder or of the contractor to estimate correctly the difficulties attending the execution of the work.”

“ It is expected that each bidder will, prior to submitting his bid, visit the site of the' work, examine the local conditions, inform himself as to the accessibility of the work, ascertain the character of the material to be excavated, consult the plats on file at the U. S. Engineer Office at Sault Ste. Marie, Mich., and obtain such available information as will assist him to make an intelligent bid, and the failure of a bidder to make such examina *10 tion may be held to be sufficient reason for rejecting his bid.”

“ The contractor must construct and maintain all necessary cofferdams, furnish suitable and adequate pumping plant, and do all the pumping required to unwater all areas where work is to be done in the dry, and no special payment will be made therefor, the above work and expense being considered as incident to the general work covered by the contract prices of other items. . . .”

“ The United States assumes no responsibility whatsoever for loss of life, property or contractors’ time, due to the failure of any part of the cofferdams, dikes, or the pumping plant.”

In supplement of these provisions of the contract, the following provision of the Company’s proposal upon which the contract was awarded is pertinent: “We make this proposal with' a full knowledge of the kind, quantity, and quality of the plant, work and materials required. ...”

The repellent effect of those provisions and the contentions of the Company, would seem to need no comment, and the effect is reinforced by other considerations. The contract of the Company was made September 23, 1910, and at that time, according to the averments of the petition, work on the prior contract was in progress and-had been in progress two years.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States v. Pescatore
Second Circuit, 2011
Codell Construction Co. v. Commonwealth
566 S.W.2d 161 (Court of Appeals of Kentucky, 1977)
Broome Construction, Inc. v. United States
492 F.2d 829 (Court of Claims, 1974)
Frederickson & Watson Construction Co. v. Department of Public Works
28 Cal. App. 3d 514 (California Court of Appeal, 1972)
L. J. McNulty, Inc. v. Village of Newport
187 N.W.2d 616 (Supreme Court of Minnesota, 1971)
J. A. Thompson & Son, Inc. v. State
465 P.2d 148 (Hawaii Supreme Court, 1970)
ASHTON COMPANY, INC., CONTR. & ENG'RS v. State
454 P.2d 1004 (Court of Appeals of Arizona, 1969)
EH Morrill Co. v. State of California
423 P.2d 551 (California Supreme Court, 1967)
Banks Construction Company, Inc. v. The United States
364 F.2d 357 (Court of Claims, 1966)
Archie and Allan Spiers, Inc. v. United States
296 F.2d 757 (Court of Claims, 1961)
Ellis Bros. v. United States
197 F. Supp. 891 (S.D. California, 1961)
Construction Aggregates Corp. v. State
170 A.2d 274 (Supreme Court of Connecticut, 1961)
City of East Peoria v. Colianni & Dire Co.
78 N.E.2d 806 (Appellate Court of Illinois, 1948)
Furton v. City of Menasha
71 F. Supp. 568 (E.D. Wisconsin, 1947)
United States v. Johnson
153 F.2d 846 (Ninth Circuit, 1946)
Benjamin Foster Co. v. Commonwealth
61 N.E.2d 147 (Massachusetts Supreme Judicial Court, 1945)
Webb-Boone Paving Co. v. State Highway Commission
173 S.W.2d 580 (Supreme Court of Missouri, 1943)
Triest & Earle, Inc. v. United States
95 Ct. Cl. 209 (Court of Claims, 1941)

Cite This Page — Counsel Stack

Bluebook (online)
258 U.S. 6, 42 S. Ct. 225, 66 L. Ed. 433, 1922 U.S. LEXIS 2231, Counsel Stack Legal Research, https://law.counselstack.com/opinion/macarthur-brothers-co-v-united-states-scotus-1922.