J. A. Thompson & Son, Inc. v. State

465 P.2d 148, 51 Haw. 529
CourtHawaii Supreme Court
DecidedFebruary 13, 1970
Docket4787
StatusPublished
Cited by7 cases

This text of 465 P.2d 148 (J. A. Thompson & Son, Inc. v. State) is published on Counsel Stack Legal Research, covering Hawaii Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
J. A. Thompson & Son, Inc. v. State, 465 P.2d 148, 51 Haw. 529 (haw 1970).

Opinion

*530 OPINION OP THE COUBT BY

ABE, J.

The plaintiff, J. A. Thompson & Son, Inc., a California corporation, was awarded a contract by the State of Hawaii to construct a four-lane divided highway over a portion of Kalanianaole Highway beginning at the Kailua junction and extending towards Waimanalo for a distance of approximately 7,000 feet. The contract price for the job was $564,989.45. Of that sum plaintiff’s bid price for the item of excavation was 54.6 cents per cubic yard for 287,000 cubic yards or a total of $156,702.00.

During construction, plaintiff encountered a subsurface condition of solid rock in the area designated on the State’s plans at about Station 49 + 50, where test hole No. 6 had been drilled. Plaintiff contends that the cost of excavation increased from the contract price of 54.6 cents per cubic yard to a unit price in excess of $1.00 per cubic yard because of the condition.

Plaintiff commenced suit against the State to recover this additional cost on the ground that the damages resulted from the State’s misrepresentation of material facts or its failure to disclose all material information in its possession. After suit was instituted against the State, the State filed a third-party complaint against Herbert A. R. Austin and R. M. Towill, the engineers responsible for the plan.

After a trial without a jury, the trial court rendered its findings of fact and conclusions of law; judgment was *531 entered against the plaintiff in accordance therewith; and plaintiff appealed.

The plaintiff states three points upon which it relies on this appeal as follows:

“1. Is the State liable for damages resulting from its misrepresentation of material facts and/or its failure to disclose all material information in its possession where the same is necessary to make other information furnished not misleading?
“2. Do the exculpatory clauses contained in the State’s Standard Specifications for Bridge and Roadway Construction (Def. Ex. A) insulate the State against liability for a misrepresentation of material fact or failure to disclose a material information which, if disclosed, would prevent a bidder from being misled?
“3. Is the policy and practice of the State of passing all risks of loss to a contractor-bidder, including the risk of misrepresentation and non-disclosure of material information by the State, consistent with the purposes and intent of § 9-21, Revised Laws of Hawaii 1955, as amended, relating to bidding on public contract?”

Accordingly the basic issue before us is whether the trial court’s finding that the State did not misrepresent facts and did not fail to disclose material information is clearly erroneous.

The plaintiff claims that the State misrepresented material facts and failed to disclose all material information in connection with test hole No. 6 drilled at station 49 + 50. The plaintiff contends that this is shown by the following comparison between the log shown on the plans and the actual boring log:

Actual Boring Log Log as Shown on Plans 0-15 ft. Hard dry red clay with Red clay with decomdecomposed lava rock posed lava rock
*532 15-30 ft. Hard red and yellow gray black clay slightly plastic with decomposed lava rock Slightly plastic red and yellow gray black clay with decomposed lava rock
30-32 ft. Brown, yellow slightly plastic damp clay with medium hard decomposed lava rock and little red and black clay Slightly plastic brown yellow clay with decomposed lava rock and red and black clay
32-40 ft. Little hard red clay with hard basalt boulders Red clay with basalt boulders
40-80 ft. Firm brown clay with hard basalt boulders or cracked basalt strata mixed with very red clay Brown clay with basalt boulders or cracked basalt strata with red
Cored hole from 40-80' samples in bags marked Hole No. 6 40-80' (No entry at all)

The plaintiff contends that “It is clear from undisputed testimony at the trial that the State misrepresented because it:

“(a) Neglected to transcribe parts of the driller’s boring log regarding Hole No. 6 to the State’s plans— it left out such adjectives as ‘hard’, ‘firm’, etc., * * * in describing the material encountered by the driller.
“(b) Represented on its plans that the material to be excavated would have shrinkage factor of 23% when in fact the material had a swell factor of 25.4% — a 48.4% difference (PI. Ex. 5, Tr. 39).
“(c) Failed to disclose in transposing to the plan *533 information contained on the driller’s log that the driller had ‘cored hole from 40-80'’ (PI. Exs. 5 and 7).”

The trial court in its findings of fact had found that the discrepancy between the actual driller’s boring log and the log as shown on the plans, as contended by the plaintiff, did not constitute misrepresentation of facts or failure to disclose material information on the part of the State.

We believe that any reasonable contractor or engineer should have been aware that he would encounter a subsurface condition of rock from the log on the plans for Hole No. 6 which disclosed the presence of basalt boulders or strata because the word “basalt”, commonly called “blue rock”, denotes very hard rock and we agree with the trial court that the failure to use the adjectives “hard” and “firm” in connection with basalt boulders or cracked basalt strata did not constitute misrepresentation or a failure to disclose material facts on the part of the State.

The log on the plans showed the presence of “brown clay with basalt boulders or cracked basalt strata with red clay” at the 40-80 foot depth and though the words “cored hole from 40-80 feet” were omitted, plaintiff as a reasonable engineer or contractor should have been aware that samples of basalt boulder or cracked basalt strata could not have been obtained except by coring. 1

The plaintiff cites Potashnick v. United States, 105 F. Supp. 837 (1952); Christie v. United States, 237 U.S. 234 (1915); United States v. Atlantic Dredging Co., 253 U.S. 1 (1920); and Pat G. Murphy, Inc. v. Drummond Dolomite, Inc., 232 F. Supp. 509 (E.D. Wis. 1964) for the proposition that omission of the adjectives “firm” and *534 “hard” and the words “cored from 40-80'” constituted misrepresentation or a failure to disclose material facts on the part of the State.

In Potashnick,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Midwest Dredging Co. v. McAninch Corp.
424 N.W.2d 216 (Supreme Court of Iowa, 1988)
Mf Williams v. City and Cty. of Honolulu
650 P.2d 599 (Hawaii Intermediate Court of Appeals, 1982)
Sasso Contracting Co. v. State
414 A.2d 603 (New Jersey Superior Court App Division, 1980)
Golomore Associates v. NJ State Highway Auth.
413 A.2d 361 (New Jersey Superior Court App Division, 1980)
Codell Construction Co. v. Commonwealth
566 S.W.2d 161 (Court of Appeals of Kentucky, 1977)
Associated Engineers & Contractors, Inc. v. State
567 P.2d 397 (Hawaii Supreme Court, 1977)

Cite This Page — Counsel Stack

Bluebook (online)
465 P.2d 148, 51 Haw. 529, Counsel Stack Legal Research, https://law.counselstack.com/opinion/j-a-thompson-son-inc-v-state-haw-1970.