Associated Engineers & Contractors, Inc. v. State

567 P.2d 397, 58 Haw. 187, 1977 Haw. LEXIS 100
CourtHawaii Supreme Court
DecidedJuly 7, 1977
DocketNO. 5595
StatusPublished
Cited by37 cases

This text of 567 P.2d 397 (Associated Engineers & Contractors, Inc. v. State) is published on Counsel Stack Legal Research, covering Hawaii Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Associated Engineers & Contractors, Inc. v. State, 567 P.2d 397, 58 Haw. 187, 1977 Haw. LEXIS 100 (haw 1977).

Opinion

*189 OPINION OF THE COURT BY

KIDWELL, J.

This case arises out of a contract made between Plaintiffs-Appellees, Cross-Appellants (Contractor) and Defendant-Appellant, Cross-Appellee (State) for the construction by the Contractor of an observatory building at the top of Mauna Kea. The contract was entered into on September 8, 1967 and required final completion of the work (after extensions granted by the State) on July 17, 1968. The work was substantially completed on December 19, 1969, and was finally inspected by the State on January 30, 1970. The contract price, as specified in the contract, was $2,049,500, and by agreed change orders was adjusted to $2,052,938.97. This action was bought by the Contractor for unpaid portions of the contract price, together with additional compensation claimed in the amount of $1,554,610.65. The State counterclaimed for liquidated damages and for additional costs incurred under a telescope installation contract and an engineering consultant contract by reason of the Contractor’s delay. After an extended trial, judgment was entered as follows:

*190 1. Defendant shall pay to Plaintiffs the following amounts:
(a) $32,797.09 as and for the increased cost of welding the dome skin joints;
(b) $17,584.28 as and for the deletion of “Alternate No. 2” ;
(c) $60,432.75 as and for the increased cost of welding the dome structural connections with double Vee welds instead of single Vee welds;
(d) $52,173.00 as and for reimbursement of all jobsite and other indirect expenses incurred by Plaintiffs during the extended period of 51 calendar days required to perform the work described in paragraphs 1(a), (b), and (c) above.
2. Plaintiffs shall pay to Defendant the following amounts:
(a) $154,000.00 as and for liquidated damages for tardy completion of the project;
(b) $48,229.00 as and for reimbursement for damages paid to Perkin-Elmer;
(c) $1,000.00 for deletion of the position encoders;
(d) $1,451.06 as and for reimbursement for expenses incurred by Defendant in locating Inspector Race.

The agreed performance period embraced the winter months and the Contractor encountered cold, winds, snow and ice. It was claimed that the State knew or should have known that completion of the work during the contract period would be impossible because of weather conditions, that relevant weather information was withheld from the Contractor, and that the State represented or warranted that the weather would be mild enough to permit completion during the contract period. These circumstances were relied on by the Contractor both as relieving it from liability for liquidated damages during the portion of the delay in performance attributable to weather conditions and as entitling it to reimbursement of its extra costs resulting from the same cause. The Contractor was required by the State to perform *191 welding and other work in the construction of the observatory dome in accordance with interpretations of the specifications which the Contractor disputed, and claim was made for the cost of such work together with relief from liquidated damages during the period of delay so occasioned. The claim also included miscellaneous items in a relatively small amount, together with claim preparation costs and interest.

The trial court allowed a portion of the Contractor’s claim for increased costs of dome construction resulting from the State’s interpretation of the specifications and denied the claim in all other respects. The State’s counterclaim for liquidated damages was allowed, except with respect to that part of the delay period attributable to dome construction for which the Contractor was awarded compensation. The State was allowed its increased costs of the telescope installation contract. Both parties have appealed. However, the Contractor has raised no question with respect to items 2(c) and (d) of the judgment.

On the Contractor’s appeal, we affirm the judgment in favor of the State (Paragraph 2(a) to 2(d), inclusive). On the State’s appeal, we reverse the judgment in favor of the Contractor (Paragraphs 1(a) to 1(d), inclusive) and remand the case for further proceedings.

During the trial, the Contractor assisted a material witness for the State to obtain mainland employment and to travel to the mainland, in order to make him unavailable to the State. By item 2(d) of the judgment the State was reimbursed its expenses of locating the witness on the mainland. The State sought to amend its answer to assert, as an affirmative defense against the claim, that the Contractor had attempted to practice fraud in the proof of the claim. The amendment was denied and the trial court refused to consider this defense. We direct that this amendment be allowed in further proceedings on remand.

The State incurred expenses in taking the deposition of an employee of the Contractor, for which it sought reimbursement as costs of proving a fact which the Contractor had failed to admit on request. The application for reim *192 bursement was denied by the trial court. We affirm this action of the trial court.

To avoid lengthy repetition, the facts relevant to each of the issues on this appeal will be stated in the part of this opinion devoted to the particular issue.

I

The claim, for damages from delay in performance caused by adverse weather conditions.

The Contractor computes its claim for weather delay damages by attributing to this cause 376 of the 554 calendar days which elapsed between the contract completion date of July 25, 1968 and the final inspection by the State on January 30, 1970. Assessing its jobsite and other indirect expenses at the rate of $1,023 per calendar day, the Contractor arrives at the sum of $384,648 as the amount which it is entitled to recover from the State as weather delay damages. 1 No findings were made by the trial court with respect to the period of delay in completion of the contract caused by adverse weather conditions. We assume arguendo that the Contractor’s computations are correct and turn to the question whether the evidence sustained the alleged liability of the State to indemnify the Contractor for its costs attributable to adverse weather conditions. The Contractor advances the following legal propositions in support of its claim:

*193 (a) The State has an affirmative duty to disclose its superior knowledge where it possesses special knowledge, not shared by the contractor, which is vital to the performance of the contract.
(b) Where the State in inviting bids discloses certain facts regarding site conditions, it may not conceal other facts within its knowledge which materially qualify those stated.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Pacific Stock, Inc. v. Pearson Education, Inc.
927 F. Supp. 2d 991 (D. Hawaii, 2013)
Sung v. Hamilton
710 F. Supp. 2d 1036 (D. Hawaii, 2010)
Fisher v. Grove Farm Co., Inc.
230 P.3d 382 (Hawaii Intermediate Court of Appeals, 2009)
Tokuhisa v. Cutter Management Co.
223 P.3d 246 (Hawaii Intermediate Court of Appeals, 2009)
SON-GI HAN v. Kang
220 P.3d 1052 (Hawaii Intermediate Court of Appeals, 2009)
Baldonado v. Way of Salvation Church
185 P.3d 913 (Hawaii Intermediate Court of Appeals, 2008)
Tri-S Corp. v. Western World Insurance Co.
135 P.3d 82 (Hawaii Supreme Court, 2006)
Office of Hawaiian Affairs v. State
133 P.3d 767 (Hawaii Supreme Court, 2006)
Matsuura v. EI Du Pont De Nemours and Co.
73 P.3d 687 (Hawaii Supreme Court, 2003)
Federal Home Loan Mortgage Corp. v. Transamerica Insurance Co.
969 P.2d 1275 (Hawaii Supreme Court, 1998)
Fong v. Hashimoto
994 P.2d 569 (Hawaii Intermediate Court of Appeals, 1998)
Krohnert v. Yacht Systems Hawaii, Inc.
664 P.2d 738 (Hawaii Intermediate Court of Appeals, 1983)
Park v. Esperanza
662 P.2d 214 (Hawaii Intermediate Court of Appeals, 1983)
Rodriguez v. Nishiki
653 P.2d 1145 (Hawaii Supreme Court, 1982)
Application of Hawaiian Telephone Co.
651 P.2d 475 (Hawaii Supreme Court, 1982)
Mf Williams v. City and Cty. of Honolulu
650 P.2d 599 (Hawaii Intermediate Court of Appeals, 1982)

Cite This Page — Counsel Stack

Bluebook (online)
567 P.2d 397, 58 Haw. 187, 1977 Haw. LEXIS 100, Counsel Stack Legal Research, https://law.counselstack.com/opinion/associated-engineers-contractors-inc-v-state-haw-1977.