Merritt-Chapman & Scott Corp. v. The United States

439 F.2d 185, 194 Ct. Cl. 461, 1971 U.S. Ct. Cl. LEXIS 157
CourtUnited States Court of Claims
DecidedMarch 19, 1971
Docket89-64
StatusPublished
Cited by10 cases

This text of 439 F.2d 185 (Merritt-Chapman & Scott Corp. v. The United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Merritt-Chapman & Scott Corp. v. The United States, 439 F.2d 185, 194 Ct. Cl. 461, 1971 U.S. Ct. Cl. LEXIS 157 (cc 1971).

Opinion

ON PLAINTIFF’S MOTION AND DEFENDANT’S CROSS-MOTION FOR SUMMARY JUDGMENT

DAVIS, Judge. *

The contract out of which this case arose was executed in October 1955 between the Savin Construction Corporation, wholly-owned subsidiary and predecessor in interest of plaintiff, 1 and the Government, acting through the Army Corps of Engineers. It provided for the construction of the New Cumberland Locks and Dam on the Ohio River near Stratton, Ohio, for the originally estimated price of $16,312,765.00. This project was part of a plan for the overall development of the Ohio River for navigational purposes.

Twin locks were to be built and this would involve the construction of three lock walls. Existing Ohio State Highway No. 7 ran through the contemplated construction area and in fact directly over the proposed location of the middle lock wall, for about three quarters of its length. As part of its obligation to acquire the necessary land, defendant was required to relocate a 2-mile section of this State Highway No. 7 under a contract between it and the State of Ohio. Under that agreement, defendant was to construct the subgrade for the relocated highway along the new alignment, following which the State Highway Department would have the permanent pavement placed. The new highway *187 would then be opened to traffic, and the State would transfer the right of way of existing Highway No. 7 to defendant, so that it could be excavated in furtherance of the lock and dam project involved in this case.

The defendant had further obligated itself to orchestrate these two contracts with a third one between the government and the Ohio Edison Company. The latter agreement permitted defendant to use adjacent Ohio Edison Land to dispose of the excavated material generated under this lock and dam contract, provided that disposal operations on Ohio Edison land were terminated by May 1, 1956. This was the only major area available for disposal of excavation, and the contract between defendant and Ohio Edison was made necessary by the latter’s acquisition of the land on which to construct a power plant, before the Government could complete its plans for this lock and dam contract. The termination date of May 1, 1956, for disposal on its land, was fixed by the fact that Ohio Edison planned to begin construction of its power plant at that time.

Accordingly, back in March 1955, the Government entered into two contracts for construction of the subgrade along the new alignment of Highway No. 7, relocated to run between the excavation and disposal areas, and scheduled to be completed about October 1, 1955. That work was actually finished, and accepted by defendant, on November 4, 1955. The State had previously awarded a contract for paving the relocated section of Highway No. 7, but because of slippage in the schedule for construction of the subgrade by defendant the paving contractor had to pave with a “winter mix”, which then had to be redesigned by the State, and approved. This was accomplished by November 29, 1955.

Moreover, the State on November 7, 1955, had rejected the subgrade constructed by defendant’s contractor. Relatively prolonged negotiations ensued between defendant and the State, including discussions as to which party was to blame. The result was that traffic was not diverted from existing Highway No. 7 until April 14, 1956, on which date that portion of the old roadway within the main lock area was made available to plaintiff. The entire road section within plaintiff’s work area was not made available for excavation until June 26, 1956.

The contract involved in this case had meanwhile been advertised for bids back in the late summer of 1955 and was awarded to plaintiff, as already noted, on October 24, 1955. Plaintiff was notified to proceed November 4, 1955. 2 The contract with plaintiff, as advertised and as awarded, provided in pertinent part as follows:

SC-20 ORDER OP WORK. — (a) Except as specified hereunder, the work shall be carried on in such order of precedence as best suits the Contractor’s construction schedule. The Contractor is informed that no part of existing State Highway 7 shall be removed until the relocated highway is opened to traffic, which will be about 1 December 1955. Work to be performed at the following locations shall be completed not later than the dates specified.
(b) Disposal operations in that portion of the disposal area landward of the relocated highway between approximate Highway Stations 58 + 00 and 78 + 00 shall be completed to specified grade by 1 May 1956. Disposal operations on the remainder of the area shall be completed as early as practicable, but in any event not later than 31 December 1957. [Emphasis supplied.] 3

*188 The first date emphasized above was the approximate time plaintiff was promised old Highway No. 7, which was part of its construction site, and which had to be excavated. The second date italicized was the date by which a substantial portion of the excavated material had to be disposed of on the Ohio Edison property, as explained above.

Plaintiff was required to file schedules with the contracting officer which showed the order in which it proposed to carry on the work (GC-5(a)), and which indicated the percentage of completion of a described task at any point in time. The urgency of the contractor’s adhering to these schedules is underscored by paragraph GC-5(c):

Failure of the Contractor to comply with the requirements of the Contracting Officer under the provision shall be grounds for determination by the Contracting Officer that the Contractor is not prosecuting the work with such diligence as will insure completion within the time specified. Upon such determination the Contracting Officer may terminate the Contractor’s right to proceed with the work, or any separable part thereof, in accordance with the delays-damages article of the contract.

Upon receiving the formal notice to proceed on November 4, 1955, plaintiff mobilized the men and equipment neces sary to initiate construction. It began excavation as the first order of business. As earlier mentioned, existing Highway No. 7 was not in fact made available to plaintiff on or about December 1, 1955, but rather on April 14 and June 26, 1956.

On February 24, 1956, plaintiff wrote the contracting officer as follows:

Reference is made to a statement contained in Paragraph SC-20 of the specifications reading as follows:
“The Contractor is informed that no part of existing State Highway 7 shall be removed until the relocated highway is opened to traffic, which will be about 1 December 1955.”
This completion date has not been met and it now appears that it may be an appreciable time before we will be permitted to start the removal of the existing road and embankment. The existence of this condition has already resulted in some delay and additional expense to us and we anticipate that this will be aggravated by continued delay in opening the new highway to traffic.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

GASA, Inc. v. United States
79 Fed. Cl. 325 (Federal Claims, 2007)
Titan Pacific Construction Corp. v. United States
35 Cont. Cas. Fed. 75,693 (Court of Claims, 1989)
Ceccanti, Inc. v. United States
32 Cont. Cas. Fed. 73,041 (Court of Claims, 1984)
Associated Engineers & Contractors, Inc. v. State
567 P.2d 397 (Hawaii Supreme Court, 1977)
Merritt-Chapman & Scott Corp. v. United States
528 F.2d 1392 (Court of Claims, 1976)
Roscoe-Ajax Construction Co. v. United States
458 F.2d 55 (Court of Claims, 1972)
Hoel-Steffen Construction Co. v. United States
456 F.2d 760 (Court of Claims, 1972)
Southwestern Engineering Co.
196 Ct. Cl. 782 (Court of Claims, 1971)

Cite This Page — Counsel Stack

Bluebook (online)
439 F.2d 185, 194 Ct. Cl. 461, 1971 U.S. Ct. Cl. LEXIS 157, Counsel Stack Legal Research, https://law.counselstack.com/opinion/merritt-chapman-scott-corp-v-the-united-states-cc-1971.