Roscoe-Ajax Construction Co. v. United States

458 F.2d 55, 198 Ct. Cl. 133, 1972 U.S. Ct. Cl. LEXIS 63
CourtUnited States Court of Claims
DecidedApril 14, 1972
DocketNo. 199-68
StatusPublished
Cited by12 cases

This text of 458 F.2d 55 (Roscoe-Ajax Construction Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Roscoe-Ajax Construction Co. v. United States, 458 F.2d 55, 198 Ct. Cl. 133, 1972 U.S. Ct. Cl. LEXIS 63 (cc 1972).

Opinion

Per Curiam:

This case was referred to Trial Commissioner Saul Richard Gamer with directions to prepare and file his opinion on the issues of plaintiffs’ motion and defendant’s cross-motion for summary judgment under the order of reference and Rule 166 (c). The commissioner has done so in an opinion and report filed on May 20, 1971, wherein such facts as are necessary to the opinion are set forth. Defendant filed a request for review by the court of the commissioner’s opinion as it relates to plaintiffs’ sixth and seventh causes of action and the case has 'been submitted to the court on the briefs of the parties and oral argument of counsel. Since the court agrees with the commissioner’s opinion and recommended conclusion, as hereinafter set forth, it hereby adopts the same as the basis for its judgment in this case. Accordingly, further proceedings on plaintiffs’ motion and defendant’s cross-motion for summary judgment on the sixth and seventh causes of action are, under Rule 167 (a) and (e), stayed for a period of six months to enable plaintiffs to obtain from the General Services Board of Contract Appeals determinations of (a) whether, in connection with the sixth cause of action, plaintiffs encountered such a changed condition as would entitle them to an equitable adjustment under Article 4 of the contract, and (b) whether, in connection with the seventh cause of action, plaintiffs are, on the basis of the proper interpretation of the specifications, entitled to an equitable adjustment under Article 3 of the contract with respect to the installation of the glass involved in this claim.

[137]*137OPINION OF COMMISSIONER

Gamee, Commissioner: Plaintiff entered into a $32,512,000 contract with, defendant, acting through the Public Buildings Service, General Services Administration, for the construction of the United States Courthouse and. Federal Office Building in San Francisco, California.1

The petition herein sets forth seven causes of action in which plaintiff seeks the total amount of $5,480,547, with respect to disputes growing out of its performance of the contract. The first five of these causes are based upon alleged breaches of the contract and are to be tried. However, the sixth and seventh causes are of a nature that would permit administrative adjustment under the contract. These claims were presented to, and denied by, the contracting officer and the General Services Board of Contract Appeals. The Board decisions are here contested by plaintiff’s motion for summary judgment, which seeks review under the Wunderlich Act.2

The pertinent facts here set forth are as found by the Board.

Sixth Came of Action

Under the contract plaintiff was required, by the installation of a dewatering system, to keep all excavated areas free of water.3

Prior to the letting of the contract, defendant had made site borings and had prepared logs therefrom. Section 7 of the specifications contained the provisions concerning “Excavation, Filling and Grading,” and Paragraph 7-3 thereof, headed “Subsoil Information,” stated that “[t]he existing subsurface soil data logs are shown on the [contract] draw[138]*138ings.” 4 The drawings disclosed soil data based on nine test borings which were classified in accordance with the “Unified Soil Classification System.” The boring data was prepared by the firm of Dames & Moore, soil mechanics engineers.

Plaintiff commenced its dewatering program by sinking a deepwell. However, since it began pumping sand instead of water (indicating soil of low water filtration) it was abandoned. Plaintiff then sank a second deepwell but the same trouble developed and it too was abandoned.

Thereupon, plaintiff employed Dames & Moore, the same firm that had prepared the boring data for defendant, to advise it concerning its dewatering problem. This firm stated that, in its opinion, it would take ten to twenty deepwells, depending on depth, to dewater the site. This was a greater number than plaintiff had anticipated installing.

Plaintiff then changed its dewatering system from deep-wells to well-points. Plaintiff commenced the installation of the well-points by jetting but found soil penetration by this process difficult and time-consuming. Accordingly, plaintiff obtained (from Houston, Texas) a special drill. Thereafter, plaintiff was able to proceed with the installation of the well-points in a normal manner.

The contract contained the usual Changed Conditions clause providing for an equitable adjustment if the contractor encountered (a) subsurf ace conditions differing materially from those indicated in the contract, or (b) physical conditions at the site differing materially from those ordinarily encountered in work of the kind covered by the contract.

While plaintiff was in the process of installing the well-points, it notified the contracting officer it had encountered clay deposits at a certain elevation during its deepwell drilling operations, and that this constituted a soil condition that differed materially from those indicated in the contract. The letter further advised that such deposits had also been encountered during the installation of the well-points. Plain[139]*139tiff claimed that these changed conditions had increased its dewatering costs.

Upon denial of its claim by the contracting officer, plaintiff, pursuant to the Disputes clause of the contract, appealed to the Board, which conducted a hearing lasting four days, and during which 14 witnesses testified, including experts.5 Plaintiff claimed entitlement to an equitable adjustment under either alternative set forth in the Changed Conditions clause. As to its increased costs, it contended that the well-point system it was obliged to use was more expensive than the deepwell system it had contemplated using, and that the cost of installing the well-point system was, by the conditions encountered, in itself increased over what such costs would normally have been.

At the commencement of the hearing, the presiding Board member inquired as to whether plaintiff had calculated its increased costs and presented them to defendant, but plaintiff’s counsel responded that it had not. He stated that the presentation “would have come at the second phase, if they found the changed condition. But they immediately denied that there was a changed condition, so that we never got to the question of additional cost.” Counsel further stated that plaintiff’s costs due to the alleged changed condition were “still accumulating” (since excavation operations were still taking place) so that it was not then in a position to submit its final costs.6 The presiding Board member thereupon stated, “Well, I wanted to make that clear to both sides, that in view of that situation the only question before the Board is whether or not there does exist a changed condition. Of course, subsequently, if we decide in your favor, you will present your costs to the Public Buildings Service. * * * [140]*140And they will review it and determine whether or not it is a reasonable cost.”7

By decision of December 27, 1963, the Board denied the <4aim which is the subject of this cause of action.8

Free access — add to your briefcase to read the full text and ask questions with AI

Related

LRV Environmental, Inc.
Armed Services Board of Contract Appeals, 2015
Transamerica Insurance ex rel. Stroup Sheet Metal Works v. United States
38 Cont. Cas. Fed. 76,518 (Federal Claims, 1993)
Town Center Management Corp. v. United States
35 Cont. Cas. Fed. 75,696 (Court of Claims, 1989)
North Slope Technical Ltd. v. United States
34 Cont. Cas. Fed. 75,430 (Court of Claims, 1988)
Weeks Dredging & Contracting, Inc. v. United States
34 Cont. Cas. Fed. 75,356 (Court of Claims, 1987)
Truong Xuan Truc v. United States
22 Cont. Cas. Fed. 80,065 (Court of Claims, 1976)
McKee v. United States
500 F.2d 525 (Court of Claims, 1974)
Dale Ingram, Inc. v. United States
475 F.2d 1177 (Court of Claims, 1973)
Tapper & Associates v. United States
458 F.2d 66 (Court of Claims, 1972)

Cite This Page — Counsel Stack

Bluebook (online)
458 F.2d 55, 198 Ct. Cl. 133, 1972 U.S. Ct. Cl. LEXIS 63, Counsel Stack Legal Research, https://law.counselstack.com/opinion/roscoe-ajax-construction-co-v-united-states-cc-1972.