Town Center Management Corp. v. United States

35 Cont. Cas. Fed. 75,696, 17 Cl. Ct. 531, 1989 U.S. Claims LEXIS 144, 1989 WL 81647
CourtUnited States Court of Claims
DecidedJuly 21, 1989
DocketNo. 720-87C
StatusPublished
Cited by1 cases

This text of 35 Cont. Cas. Fed. 75,696 (Town Center Management Corp. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Town Center Management Corp. v. United States, 35 Cont. Cas. Fed. 75,696, 17 Cl. Ct. 531, 1989 U.S. Claims LEXIS 144, 1989 WL 81647 (cc 1989).

Opinion

OPINION

SMITH, Chief Judge.

In this Wunderlich Act review case the court is presented with the question of whether the GSBCA properly dismissed plaintiff’s claim “for lack of jurisdiction for failure to file within the time allowed.” Town Center Management Corp. GSBCA No. 8319, 87-1 BCA (CCH) ¶ 19,640, at 99,419 (1987). For the reasons given below, the court reverses the Board’s decision and remands this case for further consideration consistent with this opinion.

FACTS

The claim here arose under a lease between GSA and plaintiff Town Center Management Corp. (TCM). The contract was entered into on August 16, 1971, and expires on September 13, 1992, unless renewed. The lease contains the usual version of the pre-CDA disputes clause, which reads:

Except as otherwise provided in this contract, any dispute concerning a question of fact arising under this contract which is not disposed of by agreement shall be decided by the contracting officer, who shall reduce his decision in writing and mail or otherwise furnish a copy thereof to the lessor. The decision of the contracting officer shall be final and conclusive unless, within 30 days from the date of receipt of such copy the lessor mails or otherwise furnished to the contracting officer a written appeal addressed to the head of the agency involved. The decision of the head of the agency or his duly authorized representative for the determination of such appeals shall be final and conclusive. This provision shall not [533]*533be pleaded in any suit involving a question of fact arising under this contract as limiting judicial review of any such decision to cases where fraud by such official or his representative or board is alleged. Provided, however, that any such decision shall be final and conclusive, unless the same is fraudulent or capricious or arbitrary or so grossly erroneous as necessary to imply bad faith or is not supported by substantial evidence. In connection with any appeal proceeding under this clause, the contractor shall be afforded an opportunity to be heard and to offer evidence in support of his appeal. Pending final decision of a dispute hereunder, the contractor shall proceed diligently with the performance of the contract and in accordance with the contracting officer’s decision.

The lease also contains an operating cost escalation clause providing for the adjustment of annual rents based upon operating experience during fixed periods (e.g., 1, 3, or 5 years). Pursuant to this clause TCM submitted to GSA an expense escalation proposal of $2,531,525 which covered 484,-144 square feet of the total leased space. The proposal was for projected costs for the base lease year commencing oh September 14, 1982. The GSA field officer (referred to hereinafter as the Contracting Officer or CO) disallowed $1,612,620 of the $2,531,525 by the letter dated January 25, 1985. The CO also attached a proposed supplemental lease agreement, Number 47, to the disallowing letter and asked TCM to execute it if it were acceptable. The amount of cost escalation allowed in proposal Number 47 was the final decision of the CO. The letter also noted that the decision was issued pursuant to the disputes clause and that TCM had 90 days to appeal to the Board or a year to appeal to the Claims Court. The CO, although noting that the appeal could be completed by letter, did not include the standard appeal form with the final decision.

On January 29, 1985, TCM received the CO’s letter and proposal Number 47. And on January 31, 1985, Mr. Charles Bresler, the president of TCM, wrote to the CO:

We have received your letter of January 25, 1985, and Supplement No. 47. We cannot agree with your letter, its rationale, the GSA auditor or the supplement you submitted.
Your letter failed to include the Forms 2465, Notice of Appeal. We have called your office requesting that the forms be sent to us in order that we might note the appeal.
However, prior to filing of the appeal and in an effort to exhause [sic] our remedies we would appreciate a meeting with you as contracting officer in order to attempt to resolve this matter and put forth our position.

The requested meeting was held on February 13, 1985. The meeting was attended by two TCM executives, the CO and two GSA auditors. The GSA representatives explained the audit procedure and the reasons for their conclusions, while TCM presented “detailed calculations, billings, contracts and the information to justify” the proposal. TCM also offered a compromise in the disputed portion of the escalation request. According to plaintiff, the parties ended the meeting with an oral promise that GSA would review the additional material and contact TCM if there were any questions. Also, according to plaintiff, telephone calls between TCM and GSA were periodically exchanged.

On July 30, 1985, TCM again wrote to the CO arguing the validity of the cost escalation proposal. The letter also noted that TCM had offered to “compromise on the operating cost portion of the escalation at our last meeting.” No response to the letter was forthcoming. Thereafter, on September 21, 1985, TCM received a check in the amount of $585,672,45, with no explanatory letter, in payment of invoice No. L0578885. On October 18, 1985, TCM again wrote to the CO and stated that the assumption was that the check was in response to the July 30, 1985, letter. TCM then requested a summary of the payments represented by the check. TCM received a reply from GSA in an October 30, 1985, letter stating that the check represented the undisputed portion of the operating [534]*534costs escalation.1 TCM then replied on November 4,1985, and requested GSA to send a copy of proposal Number 47 and forms for appealing the CO’s January 25, 1985, decision. The letter stated additionally that, “subsequent conversations and correspondence since that date had not indicated that the Contracting Officer’s decision was final this past January.”

TCM wrote again on November 25, 1985, asking for the information referred to in the November 4, 1985, letter. On December 4,1985, the CO wrote a letter disputing TCM’s contention that the January 25, 1985, decision was not final. The CO also enclosed the appeal form. Thereafter TCM mailed a notice of appeal on December 20, 1985, which was received by GSA on January 3, 1986, 343 days after the January 25, 1985, decision of the CO.

The GSBCA Proceedings

After receipt of the appeal on January 3, 1986, the GSBCA sent, on February 4, 1986, a letter stating that it was issuing an order to show cause why the appeal should not be dismissed. The order to show cause accompanied the February 4, 1986, letter. TCM then filed, pro se, a memorandum and attachments on February 20, 1986, in response to the show cause order. This was followed by an additional memorandum and attachments filed with the Board on March 26, 1986. The GSBCA, by order of March 2, 1987, dismissed the case for failure to timely appeal. A dissent objecting to the dismissal was filed by Administrative Judge LaBella.

DISCUSSION

A. The GSBCA’s Equitable Discretion To Waive the appeal period

Because this contract was entered into prior to enactment of the CDA the plaintiff could have, and did, elect to proceed under the disputes clause of the contract. North American Corp. v. United States,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Mullen v. United States
17 Cl. Ct. 578 (Court of Claims, 1989)

Cite This Page — Counsel Stack

Bluebook (online)
35 Cont. Cas. Fed. 75,696, 17 Cl. Ct. 531, 1989 U.S. Claims LEXIS 144, 1989 WL 81647, Counsel Stack Legal Research, https://law.counselstack.com/opinion/town-center-management-corp-v-united-states-cc-1989.