Tapper & Associates v. United States

458 F.2d 66, 198 Ct. Cl. 72, 1972 U.S. Ct. Cl. LEXIS 59
CourtUnited States Court of Claims
DecidedApril 14, 1972
DocketNo. 329-70
StatusPublished
Cited by16 cases

This text of 458 F.2d 66 (Tapper & Associates v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Tapper & Associates v. United States, 458 F.2d 66, 198 Ct. Cl. 72, 1972 U.S. Ct. Cl. LEXIS 59 (cc 1972).

Opinions

Davis, Judge,

delivered the opinion of the court:

This is another controversy in which a Board of Contract Appeals has dismissed as untimely an appeal from a contracting officer’s decision, and relief is sought from this court. In 1968 plaintiff Monroe M. Tapper and Associates agreed with the then Post Office Department to construct and lease to the Department a Post Office and Vehicle Maintenance Facility in Worcester, Massachusetts. The Tapper group, which constituted the prime contractor but appeared to have [75]*75been, mainly interested in the leasing phase of the arrangement, subcontracted all the construction work to Granger Contracting Company as general contractor. The prime contract embodied the usual disputes mechanism, allowing 30 days after receipt for an appeal to the Postmaster General from a final decision of the contracting officer.

In the course of performance, Granger disagreed with C. W. Buckley, Inc., the defendant’s architect-engineer, over whether gravel should be used for certain backfill. The position of the architect-engineer was that gravel was demanded by the contract; Granger considered the item an extra for which it should be reimbursed under the Changes clause. When the controversy could not be resolved, Granger asked the contracting officer for a formal “final decision”. This was forthcoming on December S3, 1968, and was sent to Mr. Tapper’s office in Minneapolis, Minnesota, without any copy being furnished to Granger in Worcester. Appeal was not taken by Tapper until February 25, 1969. The Government moved before the Post Office Department Board of Contract Appeals to 'dismiss the appeal as too late.

The Board found — and this finding, which is based on ample evidence, is unchallenged in this court — that the contracting officer’s decision was actually received by Tapper’s office on or before January 16, 1969. Mr. Tapper testified that he went to Arizona for a vacation at Christmas-time 1968 and returned to Minneapolis in the second or third week of January 1969; the contracting officer’s final decision was delivered to his office during his absence; it was apparently misfiled by his secretary and he did not see or know about its arrival until June 1969 after he had made a diligent search in connection with the motion to dismiss the appeal; and he sent his appeal notice of February 25, 1969 after Granger inf ormed him on February 20th that a final decision had been rendered and prompted him to appeal. On this and other evidence, the Board found that the notice of appeal was untimely and dismissed the appeal on that ground.

Before us, plaintiff barely challenges the holding that the appeal was technically late — as it was. The Tapper group, [76]*76though Mr. Tapper took a strange view of his role as prime,1 remained the contractor with which the Government had made its agreement. There was no formal substitution of Granger and the Board permissibly found that neither Tapper nor Granger was led by the Government into the belief that Granger could handle the appeal all by itself, without the prime’s participation. There was, for instance, undisputed testimony that Granger was told by a post office representative that claims under the disputes article for more than $2,000 should be submitted through Tapper, and that Tapper should take the appeal “in the case of a negative decision from the Contracting Officer.”

The major theme of the petition and of plaintiff’s argument is, first, that the Board had power to enlarge the 'appeal-period and waive the lateness of the filing, and, second, that that is what should have 'been done in this instance. We need not linger over the first point. The court has recently reaffirmed the rule that Boards of Contract Appeals have power, in proper circumstances, to waive or extend the appeal period specified in the usual disputes clauses. Maney Aircraft Parts, Inc. v. United States, 197 Ct. Cl. 159, 453 F. 2d 1260 (1972).2 Cf. Schacht v. United States, 398 U.S. 58, 63-65, 66-69 (1970). The Government’s rights under the clause do not “vest” until the Board refuses to take jurisdiction 'because of untimeliness. Thus, if the Board does take jurisdiction, it is not waiving a vested right because the right does not vest until and unless the Board refuses to take jurisdiction. If it 'awards relief, the disbursing officer can take comfort in the fact that he is not waiving a vested right.

[77]*77The plaintiff’s contract is garden variety in this respect, and the Post Office Board possessed full waiver authority. After Maney, the only real issues in this case concern the possibility of waiver of the'strict time-for-appeal.

Plaintiff’s position is that a waiver must be accorded, and the appeal period enlarged, unless the Government can show prejudice from such enlargement. We cannot accept that as the sole and exclusive criterion. First of all, the burden should not be on the defendant; the contractor, which failed to comply with the requirement that an appeal be filed within the specified period, must persuade the tribunal that in the particular circumstances a waiver would be warranted. It is normal to ask that some good cause be shown by an applicant seeking extension of a waivable time-limit for appeal. See, e.g., Schacht v. United States, supra, at 64, 67. Secondly, prejudice to the Government is of course an important factor but the contractor’s own responsibility should not be disregarded. As in most instances where a discretionary waiver of a specific time-limit is involved, carelessness or neglect on the part of the applicant is relevant, though it may not be conclusive. Plaintiff’s contrary rule would undermine the integrity of the appeal period and remove an essential goad to the filing of timely appeal notices. Laxity on the part of contractors would be greatly encouraged. In exercising its discretion whether or not to waive a contract time-limit, a contract appeals board (or similar tribunal) must be able to weigh all elements, including the conduct of both the Government and the contractor.

Although we disagree with the narrow standard plaintiff proposes, we feel, as in Ma/ney Aircraft, supra, that this contractor should be permitted to apply to the Board for consideration, or further consideration, of a discretionary waiver because the course of the defendant’s dealings with Granger may have induced Granger (and Tapper) reasonably to believe that Granger would promptly receive a copy of the contracting officer’s final decision — and thus enable Granger to set in motion a timely appeal by the prime. Without attempting to summarize or weigh all the pertinent evi[78]*78dence in tlie existing record, we point ont several circumstances on which, plaintiff relies. Tapper left almost all of the dealings with the Government, with respect to construction, to Granger — see note 1, sufra — and the communication between Granger and the defendant (including Buckley, the architect-engineer) was extensive, continuous, and routine. In particular, on the backfill dispute (here involved) the relations were wholly between Granger and the Government, without any participation by or notification to Tapper up to Granger’s request for a final decision by the contracting officer.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Mullen v. United States
17 Cl. Ct. 578 (Court of Claims, 1989)
Town Center Management Corp. v. United States
35 Cont. Cas. Fed. 75,696 (Court of Claims, 1989)
Gibson v. United States
11 Cl. Ct. 6 (Court of Claims, 1986)
Cosmic Construction Co. v. United States
32 Cont. Cas. Fed. 72,529 (Court of Claims, 1984)
Cosmic Construction Co. v. The United States
697 F.2d 1389 (Federal Circuit, 1982)
Linair, Inc.
25 Cont. Cas. Fed. 83,091 (Court of Claims, 1979)
Monroe M. Tapper & Associates v. United States
514 F.2d 1003 (Court of Claims, 1975)
J. R. Youngdale Construction Co. v. United States
504 F.2d 1124 (Court of Claims, 1974)
Maney Aircraft Parts, Inc. v. United States
479 F.2d 1350 (Court of Claims, 1973)
Monroe M. Tapper & Associates
202 Ct. Cl. 1084 (Court of Claims, 1973)
William Green Construction Co. v. United States
477 F.2d 930 (Court of Claims, 1973)
Richardson Camera Co. v. United States
467 F.2d 491 (Court of Claims, 1972)

Cite This Page — Counsel Stack

Bluebook (online)
458 F.2d 66, 198 Ct. Cl. 72, 1972 U.S. Ct. Cl. LEXIS 59, Counsel Stack Legal Research, https://law.counselstack.com/opinion/tapper-associates-v-united-states-cc-1972.