Richardson Camera Co. v. United States

467 F.2d 491, 199 Ct. Cl. 657, 1972 U.S. Ct. Cl. LEXIS 131
CourtUnited States Court of Claims
DecidedOctober 13, 1972
DocketNo. 126-71
StatusPublished
Cited by14 cases

This text of 467 F.2d 491 (Richardson Camera Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Richardson Camera Co. v. United States, 467 F.2d 491, 199 Ct. Cl. 657, 1972 U.S. Ct. Cl. LEXIS 131 (cc 1972).

Opinion

Per Curiam :

In this case involving a supply contract, the Government has filed a motion for summary judgment pursuant to Buie 163(b) (1) in response to the plaintiff’s petition to this court following an order to dismiss entered by the [660]*660Armed Services Board of Contract Appeals (ASBCA No. 13895). The petition concerns a contract (No. 3037) entered into by the plaintiff, Richardson Camera Company, and the Central Intelligence Agency in June 1961 for three items: a film viewer, a reader, and a counter. After several changes and subsequent agreements, the contracting officer on April 2, 1965, ordered work stopped on the project and requested that the plaintiff submit a cost proposal for settlement. On April 9, 1965, the contractor responded by submitting a breakdown of its costs along with suggested new contract prices or a termination at cost without profit.

Following an audit of the plaintiff’s accounts, the contracting officer on October 7, 1965, sent the contractor a letter stating that if items Nos. 2 and 3 (the reader and counter) did not pass a preliminary inspection by October 26, 1965, the contract would be terminated for default. This same letter lifted the stop-work order.

In the preliminary inspection that followed, items 2 and 3 of the contract did not meet specifications and the contract was terminated by a letter from the contracting officer dated November 11, 1965, reading as follows:

Reference is made to our letter of 7 October 1965 and to our letter of 27 October 1965 extending to 10 November 1965 the time in which you were to correct all deficiencies and to ship to us one each of Items 2 and 3 called for under this contract.
In view of your failure to ship these items by that date, this contract is hereby terminated for default pursuant to Article 11 thereof.
The Government reserves all rights available to it by reason of this default.

In a letter dated November 18, 1965, the contractor requested the contracting officer to reconsider the default termination and to terminate for convenience of the Government. The contracting officer responded in a second letter on November 30,1965, which in pertinent part reads:

For the reasons indicated in our previous correspondence, we feel we are unwarranted in altering our action ' in this case. Under the circumstances, the termination for default must stand.

[661]*661After the receipt of this letter, the plaintiff, on December 9, 1965, wrote the following letter which is the focus of this petition:

We have your letter of 30 November 1965 stating that the termination for default on subject contract must stand.
This default action could be understood by us if this was the production phase of subject contract. However, we have produced development work on this contract during a period of several years while your specifications have been radically changed from time to time.
Due to the large amount of our working capital invested in the prototype units of Items 2 and 3, a termination for default would impose a very serious hardship on our firm.
We respectfully ask that you again consider the “development” nature of our effort and advise if further reconsideration can be granted for a termination other than for default, or ad/vise if we have any recourse for further review. [Emphasis supplied.]

In response to this final paragraph in plaintiff’s letter the contracting officer sent a third letter dated December 22, 1965, in which he reconfirmed the default termination and went on to state:

As to your request that we advise if you “have any recourse for further review”, we refer you to the terms of the subject Contract.

Thus, in the course of two months, the plaintiff contractor was notified on three separate occasions that contract No. 3037 had been terminated for default. Thereafter, the price for item 1 was redetermined, defendant recaptured some progress payments made, and on February 11,1966, defendant, in reply to plaintiff’s protests, wrote that these procedures were pursuant to earlier agreement of the parties. On February 18, 1966, plaintiff wrote the following to the contracting officer:

Your letter dated 11 February, 1966 has been received with regard to your letter of 11 November, 1965 wherein our contract was terminated for default.
We wish to be advised if there is anything further required to close the file on this contract. We have a fiscal [662]*662year ending 3/31/66 and we wish to determine before that date our actual losses sustained during our performance on your development work.
Your early reply will be appreciated. [Emphasis supplied.]

Following this letter, the plaintiff did not again raise the matter until May 18,1966, when, with the aid of counsel, it requested “all rights granted under the dispute clause of the Subject Contract,” thereby noting its appeal to the default termination of contract No. 3037.

While this correspondence was being exchanged, the parties were also involved in the termination of a related contract (No. 6325) which called for the production of two prototype viewers for the C.I.A. On April 2, 1968, the ASBCA converted the default termination on contract No. 6325 to one for convenience. (See, Appeal of Richardson Camera Co., Inc., under contract No. 6325, ASBCA No. 11930, 68-1 BCA ¶ 6690.) Shortly thereafter, on September 6, 1968, the attorney representing the contractor notified the contracting agent that he intended to pursue an appeal of the default termination of contract No. 3037 and that he considered the contracting officer had not issued a final decision or that, alternatively, plaintiff had properly appealed it and defendant had failed to notify the board of the appeal. It was also stated that the default termination was invalid. After a hearing, however, the ASBCA, on February 10, 1970, granted the Government’s motion to dismiss the contractor’s claim as untimely since no notice of appeal was given by the contractor within 30 days of the final default-termination decision.

The contractor now petitions this court for relief. In response, the Government seeks summary judgment on the plaintiff’s petition while the contractor seeks, alternatively, a reversal of the board’s decision or a suspension of this court’s procedure for 90 days to permit the plaintiff to seek a discretionary waiver of the board’s 30-day appeal limitation. (See, Maney Aircraft Parts, Inc. v. United States, 197 Ct. Cl. 159, 453 F. 2d 1260 (1972)).

[663]*663Defendant’s motion to dismiss poses two primary issues which must be resolved. First, was the letter dated November 11, 1965, sent by the contracting officer to plaintiff Eichardson a final decision, and if so, was the reply by the contractor on December 9, 1965, a valid notice of appeal for the purposes of the Disputes Clause?

Tn dealing with these issues the parties first clash over the weight this court should give the prior decision of the ASBCA on these issues (ASBCA No. 13895). The cases on this matter are quite clear. The issue of timeliness of an appeal is a question of law for the court to decide. Moran Bros. v. United

Free access — add to your briefcase to read the full text and ask questions with AI

Related

CiyaSoft Corporation
Armed Services Board of Contract Appeals, 2018
Haddon Housing Associates, LLC v. United States
99 Fed. Cl. 311 (Federal Claims, 2011)
Rivera Agredano v. United States
70 Fed. Cl. 564 (Federal Claims, 2006)
Rodriguez v. United States
69 Fed. Cl. 487 (Federal Claims, 2006)
Cray Research, Inc. v. United States
44 Fed. Cl. 327 (Federal Claims, 1999)
Bennie Collins v. Office of Personnel Management
45 F.3d 1569 (Federal Circuit, 1995)
Oconto Electric, Inc. v. The United States
884 F.2d 1399 (Federal Circuit, 1989)
Tipperary Refining Co. v. United States
11 Cl. Ct. 572 (Court of Claims, 1987)
Carpenter v. United States
4 Cl. Ct. 705 (Court of Claims, 1984)
Vails v. Southwestern Bell Telephone Co.
504 F. Supp. 740 (W.D. Oklahoma, 1980)
Fraass Surgical Mfg. Co. v. United States
571 F.2d 34 (Court of Claims, 1978)
Wickham Contracting Co. v. United States
546 F.2d 395 (Court of Claims, 1976)
William Green Construction Co. v. United States
477 F.2d 930 (Court of Claims, 1973)

Cite This Page — Counsel Stack

Bluebook (online)
467 F.2d 491, 199 Ct. Cl. 657, 1972 U.S. Ct. Cl. LEXIS 131, Counsel Stack Legal Research, https://law.counselstack.com/opinion/richardson-camera-co-v-united-states-cc-1972.