United States v. Hammer Contracting Corporation and Aetna Insurance Company

331 F.2d 173, 1964 U.S. App. LEXIS 5620
CourtCourt of Appeals for the Second Circuit
DecidedApril 20, 1964
Docket28534_1
StatusPublished
Cited by9 cases

This text of 331 F.2d 173 (United States v. Hammer Contracting Corporation and Aetna Insurance Company) is published on Counsel Stack Legal Research, covering Court of Appeals for the Second Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States v. Hammer Contracting Corporation and Aetna Insurance Company, 331 F.2d 173, 1964 U.S. App. LEXIS 5620 (2d Cir. 1964).

Opinion

MARSHALL, Circuit Judge.

This' action, brought by the United States of America pursuant to 28 U.S. C.A. § 1345, sought $4,565.32 plus interest for a breach of contract pursuant to which defendant Hammer Contracting Corporation (Hammer) agreed to per *174 form certain landscaping work at the Veterans Administration Hospital in Brockton, Massachusetts. Under the contract, entered into in September, 1954, Hammer agreed to do all the work of landscaping and laying of lawn areas around the hospital. It guaranteed all work under the contract for a period of one year after completion.

The work was completed on October 18, 1954, and Hammer was paid in full. By letter of April 8, 1955, the Veterans Administration’s chief contracting officer notified Hammer that there were numerous areas of the lawn where the grass seed had not germinated and directed it to investigate and take the necessary corrective steps to bring the work in compliance with the contract. Hammer replied on April 18, 1955 that an investigation had been made, the overall con- , dition of the lawn was good and that any additional seeding should be postponed until after August 15th. The contracting officer agreed to the postponement.

On August 17, 1955, the contracting officer wrote Hammer requesting advice as to when the corrective work under the guaranty was to commence. Hammer did not reply. On October 26, 1955 the contracting officer wrote Hammer, reviewing previous correspondence and informing it of the Government’s intention to correct the deficiencies in the work covered by the guaranty. The letter also -stated that no further notice would be sent and that “[a]s soon as the full costs of this corrective work is known, action will be taken to establish the liability of your firm and your surety with these costs.” A copy of the letter was sent to Hammer’s surety. Hammer replied that it had been unable to do the work because of other contracts it was working on. Stating that it intended to “fulfill all our obligations,” Hammer requested an extension of time until April 1, 1956. The extension of time was granted. On April 2, 1956 the contracting officer requested information as to when the corrective work was to start. Hammer replied that its representative had visited the hospital on April 6 where it appeared to him that the grass areas were beginning to grow and would be all right in one or more seasons. Hammer felt its work was satisfactory and no corrective attention was needed. To this the contracting officer replied on April 23, 1956:

“You are advised that this office does not concur in your opinion that the work under your contract has been satisfactorily fulfilled. * * *
“Demand therefore is again made that you immediately proceed to bring all the work under your contract into compliance with your contract requirements. No further notice will be furnished to you regarding this matter.
“In the event that this corrective work is not started on or before May 1, 1956 this office intends to authorize the Station to complete this work. The full cost of the work -will then be charged to your account. Our present estimate indicates that a cost of approximately $5000.00 is involved.”

A copy of this letter was also sent to Hammer’s surety. The Government had the corrective work done and sent Hammer a bill for $4,545.32. Hammer failed to pay and this action was filed.

The Government claimed that, by virtue of the “Disputes” clause in the contract, 1 it was entitled to judgment be *175 cause of Hammer’s failure to appeal the determination of the contracting officer in his letter of April 23, 1956. The district judge rejected this claim because in his opinion that letter did not notify Hammer in clear and unequivocal terms that a final determination under the “Disputes” clause was thereby made. However, Judge Bartels found upon the evidence that Hammer was responsible for correcting the condition of the areas on the lawn, and had failed to do so. He rendered judgment for the Government in the sum of $4,115.32 plus interest. Here, the Government urges us to affirm on the ground urged by it in the district court. While there is no question in our minds that the judgment should be affirmed, we do so on the ground that the Government was entitled to judgment because the appellants had failed to pursue the administrative appeal. The district court should not have reviewed the question of liability.

The contract here involved provided for the usual administrative procedures for resolving disputes arising under it. The procedure specified in the standard “Disputes” clause was reiterated in Article 5, the guaranty clause of the contract: “The opinion of the Contracting Officer as to the liability of this contractor under any such guaranty or as to the satisfactory fulfillment or compensation for the non-fulfillment thereof will be final, subject to written appeal by the contractor, within thirty (30) days, to the Administrator, whose decision will be final and conclusive upon the parties hereto, subject to Public Lav/ 356, 83rd Congress, approved May 11, 1954, 68 Stat. 81.” It is agreed that Hammer did not appeal to the Administrator or his representative.

Consistently since 1878 the Supreme Court has enforced provisions similar to the “Disputes” clause in this' contract. Kihlberg v. United States, 97 U.S. 398, 24 L.Ed. 1106 (1878); United States v. Moorman, 338 U.S. 457, 70 S.Ct. 288, 94 L.Ed. 256 (1950). In Moorman the Court reasoned that “If parties competent to decide for themselves are to be deprived of the privilege of making such anticipatory provisions for settlement of disputes, this deprivation should come from the legislative branch of government.” (338 U.S. at p. 462, 70 S.Ct. at p. 291, 94 L.Ed. 256.) See also: United States v. Callahan Walker Constr. Co., 317 U.S. 56, 63 S.Ct. 113, 87 L.Ed. 49 (1942). In United States v. Blair, 321 U.S. 730, 735, 64 S.Ct. 820, 823, 88 L.Ed. 1039 (1944) the Court stated: “Respondent has thus chosen not to follow ‘the only avenue for relief,’ United States v. Callahan Walker Constr. Co., 317 U.S. 56, 61, 63 S.Ct. 113, 115, 87 L.Ed. 49 [53], available for the settlement of disputes concerning questions arising under this contract.” See also United States v. Joseph A. Holpuch Co., 328 U.S. 234, 66 S.Ct. 1000, 90 L.Ed. 1192 (1946); Annotation, 94 L.Ed. 261. It is not disputed that a final judgment of a contracting officer, or administrative appeal board, may serve as the basis of affirmative relief by the Government as well as a defense to a suit instituted by the contractor. Cf. United States v. Hamden Co-operative Creamery Co., 297 F.2d 130 (2 Cir. 1961); United States v. Smith, 152 F.Supp. 322 (E.D.Pa. 1957).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Seaboard Lumber Company v. United States
903 F.2d 1560 (Federal Circuit, 1990)
Seaboard Lumber Co. v. United States
903 F.2d 1560 (Federal Circuit, 1990)
United States v. Dabbs
608 F. Supp. 507 (S.D. Mississippi, 1985)
United States v. Glens Falls Insurance
534 F. Supp. 109 (N.D. New York, 1981)
Richardson Camera Co. v. United States
467 F.2d 491 (Court of Claims, 1972)
A. Teichert & Son, Inc. v. State of Cal.
238 Cal. App. 2d 736 (California Court of Appeal, 1965)
Gottlieb Contracting, Inc. v. United States
247 F. Supp. 988 (E.D. New York, 1965)

Cite This Page — Counsel Stack

Bluebook (online)
331 F.2d 173, 1964 U.S. App. LEXIS 5620, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-v-hammer-contracting-corporation-and-aetna-insurance-company-ca2-1964.