A. Teichert & Son, Inc. v. State of Cal.

238 Cal. App. 2d 736, 48 Cal. Rptr. 225, 1965 Cal. App. LEXIS 1195
CourtCalifornia Court of Appeal
DecidedDecember 16, 1965
DocketCiv. 11015
StatusPublished
Cited by26 cases

This text of 238 Cal. App. 2d 736 (A. Teichert & Son, Inc. v. State of Cal.) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
A. Teichert & Son, Inc. v. State of Cal., 238 Cal. App. 2d 736, 48 Cal. Rptr. 225, 1965 Cal. App. LEXIS 1195 (Cal. Ct. App. 1965).

Opinion

FRIEDMAN, J.

Plaintiff A. Teichert & Son, Inc., a highway construction contractor, sues the state for damages and extra costs incurred in the course of a highway construction project. The complaint, in 16 separate counts, alleges submission of plaintiff’s claim to the State Board of Control on November 14, 1963, and rejection by that body on December 17, 1963. The complaint was filed February 11, 1964. The state’s demurrer was sustained without leave to amend and plaintiff appeals from the judgment.

The principal issues are: (a) whether the complaint shows compliance with the statutory period of limitations for filing claims with the State Board of Control and (b) whether the various counts state facts sufficient to constitute grounds of relief.

The lawsuit seeks recovery of six distinct money items on alternative legal theories. Assuming the truth of the complaint ’s factual assertions, we summarize its allegations:

A. The first claim, pleaded in five counts, is for $546,204.95, constituting additional construction costs caused by excessive soil moisture along the construction right of way. The construction contract was executed on February 24, 1959. Plaintiff had been furnished- a materials report describing moisture conditions at certain points in the project area. *741 On July 27, 1959, plaintiff notified the state of excessive moisture. Plaintiff proceeded with the work, but encountered excess costs and delay in installing drainage facilities and in meeting soil compaction requirements. The various theories of recovery are described in the first five counts as follows:

(1) The state’s material report misrepresented soil conditions, inducing a lower bid than plaintiff would otherwise have made; as a result of “said breach of warranty and misrepresentations” plaintiff has been damaged in the specified amount.

(2) Failure to compensate for changes in the character of the work and for extra work in accordance with express provisions of the construction contract.

(3) Failure to pay in accordance with an executed oral modification of the written contract.

(4) Excessive moisture conditions made performance of the contract impossible, discharging plaintiff from its obligations ; nevertheless, plaintiff finished the work under modifications of the contract, which the state has refused to perform.

(5) Plaintiff relied to its detriment on oral promises to compensate for the extra work.

B. The second claim, pleaded in Count 6, stems from an interpretive dispute over the equipment rental provisions of the contract. Plaintiff claims that the equipment rental rates fixed by the contract entitle it to $34,606.82 more than the state allowed.

C. The third claim, pleaded in Count 7, seeks recovery of $19,591.70 for extra work authorized by a change order, premised upon plaintiff’s interpretation of contract provisions establishing rates for extra work.

D. The fourth claim, pleaded in Counts 8 through 10, seeks $2,717.33 for cleaning debris- from a conduit. The counts are based, respectively, on the theory of refusal to compensate under the contract provisions, executed oral modification of the written contract, and promissory estoppel.

E. The fifth claim, pleaded in Counts 11 through 13, seeks $1,598.62 for extra work of installing temporary drains, premised upon legal theories of refusal to compensate for extra work under the contract, executed oral modification of the contract, and promissory estoppel.

*742 F. The sixth claim, pleaded in Counts 14 through 16, seeks reimbursement of $1,352.94 for the expense of hiring flagmen, an expense which was occasioned by an earth slide. Recovery is predicated on theories of extra work under the contract, executed oral modification of the contract and promissory estoppel.

As regards compliance with the period of limitations for filing claims with the State Board of Control, all counts of the complaint depend on these basic allegations in the first count:

“XIII On or about May 1, 1961, the revised final estimate of compensation for work performed was returned by plaintiff to defendants with the exceptions to the amount allowed as final payment noted thereon, and on or about April 11, 1963, defendants notified plaintiff of their refusal to fully compensate plaintiff for the work performed.
“XIV On or about November 14, 1963, a claim was filed with the Board of Control of the State of California as required by law, and thereafter, on or about December 17, 1963, the claim was denied by said Board. ”

The reference to “revised final estimate” prompts us at this point to take judicial notice of the Standard Specifications of the State Department of Public Works, Division of Highways (Aug. 1954), which we have power to do. (Code Civ. Proc., § 1875, subd. 3; Chas. L. Harney, Inc. v. State of California, 217 Cal.App.2d 77, 85-86 [31 Cal.Rptr. 524].) These were incorporated in the construction contract between plaintiff and the state, except as superseded by special provisions of the contract. We set out section 9(f) of the Standard Specifications in the margin. 1

*743 At the time of contract performance and for some time thereafter, Government Code section 644 (as enacted by Stats. 1959, eh. 1715) was the governing statute of limitations. (Chas. L. Harney, Inc. v. State of California, supra, 217 Cal.App.2d 77, 90-91.) Applicable to most claims against the state, it required claim presentation to the State Board of Control “within two years after the claim first arose or accrued” and that a lawsuit be filed within six months after claim rejection.

In 1963 the Legislature adopted a comprehensive revision of state liability legislation. (Stats. 1963, ch. 1715.) This legislation repealed section 644 and substituted present Government Code section 911.2. The latter, a permanent provision, requires that claims of the sort involved here be presented to the State Board of Control within one year after accrual of the cause of action. The 1963 legislation became effective on September 21, 1963. One of its features was a temporary provision, section 152 of chapter 1715, which was aimed at clarifying the time limits on claims which had accrued but had not yet been presented to the State Board of Control when the 1963 legislation became effective. In effect, as to claims which were not already barred by the former two-year limitation of section 644, it permitted presentation within one year after September 21, 1963. 2

*744

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Campbell v. Regents of University of California
106 P.3d 976 (California Supreme Court, 2005)
National Railroad Passenger Corp. v. Notter
677 F. Supp. 1 (District of Columbia, 1987)
Arthur L. Sachs, Inc. v. City of Oceanside
151 Cal. App. 3d 315 (California Court of Appeal, 1984)
Weeshoff Construction Co. v. Los Angeles County Flood Control District
88 Cal. App. 3d 579 (California Court of Appeal, 1979)
Jefferson County v. Reach
368 So. 2d 250 (Supreme Court of Alabama, 1978)
Crain v. Krehbiel
443 F. Supp. 202 (N.D. California, 1978)
Elkins v. Derby
525 P.2d 81 (California Supreme Court, 1974)
Olson v. County of Sacramento
38 Cal. App. 3d 958 (California Court of Appeal, 1974)
East San Bernardino County Water District v. City of San Bernardino
33 Cal. App. 3d 942 (California Court of Appeal, 1973)
Campbell v. Graham-Armstrong
509 P.2d 689 (California Supreme Court, 1973)
Magnus v. Jackson
31 Cal. App. 3d 399 (California Court of Appeal, 1973)
Wiechmann Engineers v. State Ex Rel. Department of Public Works
31 Cal. App. 3d 741 (California Court of Appeal, 1973)
Acoustics, Inc. v. Trepte Construction Co.
14 Cal. App. 3d 887 (California Court of Appeal, 1971)
Myers v. County of Orange
6 Cal. App. 3d 626 (California Court of Appeal, 1970)
Warner Construction Corp. v. City of Los Angeles
466 P.2d 996 (California Supreme Court, 1970)
Savage v. State of California
4 Cal. App. 3d 793 (California Court of Appeal, 1970)
Clack v. State of California Ex Rel. Dept. Pub. Wks.
275 Cal. App. 2d 743 (California Court of Appeal, 1969)
Clack v. ST. OF CALIFORNIA EX REL. DEPT. PUB. WKS
275 Cal. App. 2d 743 (California Court of Appeal, 1969)
Fonseca v. County of Santa Clara
263 Cal. App. 2d 257 (California Court of Appeal, 1968)
Petersen v. City of Vallejo
259 Cal. App. 2d 757 (California Court of Appeal, 1968)

Cite This Page — Counsel Stack

Bluebook (online)
238 Cal. App. 2d 736, 48 Cal. Rptr. 225, 1965 Cal. App. LEXIS 1195, Counsel Stack Legal Research, https://law.counselstack.com/opinion/a-teichert-son-inc-v-state-of-cal-calctapp-1965.