Morrison v. State Highway Commission

357 P.2d 389, 225 Or. 178, 85 A.L.R. 2d 203, 1960 Ore. LEXIS 676
CourtOregon Supreme Court
DecidedDecember 7, 1960
StatusPublished
Cited by4 cases

This text of 357 P.2d 389 (Morrison v. State Highway Commission) is published on Counsel Stack Legal Research, covering Oregon Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Morrison v. State Highway Commission, 357 P.2d 389, 225 Or. 178, 85 A.L.R. 2d 203, 1960 Ore. LEXIS 676 (Or. 1960).

Opinion

*180 HOWELL, J.

(Pro Tempore)

Plaintiffs, construction contractors, sued the state of Oregon through the State Highway Commission for certain additional costs arising out of the construction of approximately five miles of highway in Wallowa county. Plaintiffs assert they are entitled to additional compensation because of unusual or unexpected conditions encountered during the construction of this highway within the purview of the “Changed Conditions” clause of their contract with the highway commission.

The ease was tried by the court without a jury, and findings of fact, conclusions of law and judgment were entered in favor of plaintiffs. Defendant appeals.

The defendant for its first assignment of error claims the trial court erred in overruling its demurrer to the amended complaint and its objection to the introduction of evidence. The demurrer and objection to the evidence were on the ground the complaint did not state a cause of action.

In the amended complaint plaintiffs alleged in substance a written contract (incorporated by reference) with the defendant to construct 5.04 miles of highway in Wallowa county; that plaintiffs entered into performance of the construction contract; that flooding and inundation of the right of way occurred affecting the progress of the work; and that the flooding of the right of way was a changed condition within that provision in the contract. The complaint also alleged notice and demand for extra compensation and the denial thereof.

The “Changed Conditions” clause of the contract is as follows:

“Should the contractor encounter, or the engineer discover during the progress of the work, [1] *181 subsurface and/or latent conditions at the site materially differing from those shown on the drawings or indicated in the specifications, [2] or unknown conditions of an unusual nature differing materially from those ordinarily encountered and generally recognized as inhering in work of the character provided for in the plans and specifications, the attention of the engineer shall be called immediately to such conditions before they are disturbed. The engineer shall thereupon promptly investigate the conditions, and if he finds that they do so materially differ, the contract may be modified by the engineer to provide for any increase or decrease of cost and/or difference in time resulting from such conditions.” (Emphasis supplied.)

The contract between the parties also included the following as part of the “Special Provisions”:

“In performing the work, the contractor will be held responsible for all damage to crops. The ditch changes shall be built, in so far as is practicable, during the time the farmers are not using water from the existing ditches. When the irrigation ditch changes are constructed during the irrigation season, they shall be constructed, in so far as practicable, before the existing ditches are closed or destroyed.
# # =* #
“The contractor shall so arrange his work that the flow of water to the land will not be interrupted, and he shall cooperate with the users of the water to the greatest possible extent.
“The contractor shall conduct his operations in such manner as will cause no interference with the flow of water in irrigation ditches and canals during the irrigation season. The contractor shall be liable for, and shall protect the State and the Federal Government against, any claims that may arise from any interruption of irrigation service caused by the contractor’s operations or by his negligence.”

*182 It is noted that the plaintiffs alleged the flooding and inundation of the right of way from the irrigation resulted in a changed condition entitling them to additional compensation. The defendant asserts that the special provisions clause above mentioned provided for such contingency as the flooding and that the complaint does not state a cause of action. The special provisions quoted do not provide for a flooding of the right of way as alleged by plaintiffs. They merely state the time of construction of the ditch changes; that the contractor is responsible for damage to crops, will not interrupt the flow of water in ditches and will be liable for any claims caused by his interruption of irrigation.

By alleging, in addition to the other charges, the flooding and inundation of the right of way was a changed condition within the language of that clause in the contract, plaintiffs stated a cause of action. The purpose of a “Changed Conditions” clause is to give a cause of action for recovery of additional compensation if the facts alleged constitute “Changed Conditions.” Navy Contract Law (2d ed) 391, §7.25; 24 Fordham L Rev 588, Government Construction Contracts. Plaintiffs’ allegations present a question of fact, not of pleading. Leal v. United States, 276 F2d 378. The demurrer and objection to the introduction of evidence were properly overruled.

It is axiomatic that where trial by jury is waived, to' sustain the judgment based upon the trial court’s findings, it must appear that the findings support the judgment and, in turn, that there was some substantial evidence to support the findings. State ex rel. Sinclair Provision Co. v. Warren Const. Co. et al., 129 Or 58, 59, 276 P 260; Ryland v. Ryland, 214 Or 548, 330 P2d 175.

*183 The facts are not substantially disputed. The primary question is whether the facts show “unknown conditions of an unusual nature differing materially from those ordinarily encountered and generally recognized as inhering in work of the character provided for in the plans and specifications” entitling plaintiffs to additional compensation.

A portion of the 5.04 miles of highway construction crossed an irrigated field owned by Lawrence Estes, one of the farmers in that area. The highway divided the Estes field in a generally east-west direction, and the field drained or sloped to the north. The land was irrigated by water taken from Wallowa lake by the Silver Lake Irrigation ditch located south of the Estes property. Estes removed his share of the water from the Silver Lake Irrigation ditch by another ditch which, in turn, had at least three lateral ditches traversing his field from south to north. The new construction divided these latter ditches and crossed over Prairie creek, which was also on the Estes property.

Estes testified he used a flood system of irrigation and irrigated the land between the main ditches by the use of contour ditches. The ditches were “dammed off” every 16 feet to spread the water over the ground. After one portion was irrigated, the dams were moved from place to place until the whole area was covered. Normally he irrigated 5 to 10 acres per day by this method.

Mr. Morrison, one of the plaintiffs, testified that he was familiar with irrigation problems, knew the irrigation season was in July and August, and that he had made a careful investigation of the area before submitting his bid.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

New Pueblo Constructors, Inc. v. State
696 P.2d 185 (Arizona Supreme Court, 1985)
A. Teichert & Son, Inc. v. State of Cal.
238 Cal. App. 2d 736 (California Court of Appeal, 1965)
Bignold v. King County
399 P.2d 611 (Washington Supreme Court, 1965)
DeLong Corporation v. Oregon State Highway Com'n
233 F. Supp. 7 (D. Oregon, 1964)

Cite This Page — Counsel Stack

Bluebook (online)
357 P.2d 389, 225 Or. 178, 85 A.L.R. 2d 203, 1960 Ore. LEXIS 676, Counsel Stack Legal Research, https://law.counselstack.com/opinion/morrison-v-state-highway-commission-or-1960.