Bignold v. King County

399 P.2d 611, 65 Wash. 2d 817, 1965 Wash. LEXIS 775
CourtWashington Supreme Court
DecidedMarch 4, 1965
Docket37276
StatusPublished
Cited by62 cases

This text of 399 P.2d 611 (Bignold v. King County) is published on Counsel Stack Legal Research, covering Washington Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bignold v. King County, 399 P.2d 611, 65 Wash. 2d 817, 1965 Wash. LEXIS 775 (Wash. 1965).

Opinion

Hill, J.

C. W. Bignold contracted with the state of Washington (for King County) for the construction of a secondary county road. The contract was based on “unit prices” rather than on a “lump sum,” with each of the construction items having a separate unit price and quantity. The total bid was $80,024.15.

The contract called for a “cut and fill” plan of construction. The material excavated from one portion of the roadway was to be used for embankment purposes at other places. The plans called for 8,900 cubic yards of borrow-pit material to supplement the excavation material. However, a considerable portion of the excavated material proved to be too wet to be used for embankment purposes, and it also included huge boulders which were likewise unsuitable. This unsuitable material was “wasted” by direction of the resident engineer. The result was that the common and select borrow pits, which the contractor had procured and opened, were inadequate and it became necessary to open new borrow pits, both common and select, at greater distances from the point of use than originally contemplated. These and other items of increased expenditure will be discussed as necessity requires.

The contractor was paid $13,096.97 over the contract price for items on which it was conceded he was entitled to additional compensation. He brought this action for an additional $50,465.72 on the theory of quantum meruit to compensate him for extra work and increased costs. The trial court found $41,878.40 to be due him, there being a specific recovery on eight different items.

From the judgment in that amount, the defendants (state of Washington and King County) each appealed. Since any judgment would have to be paid by King County, it alone has prosecuted the appeal and will hereafter be referred to as the appellant.

*820 The appellant assigns no error to the specific findings of fact which cover the eight items for which recovery was permitted. 1 The sole assignment of error is:

“The trial court erred in determining that none of respondent’s damages were controlled by the contract, and concluding that these are claims based on quantum meruit, and allowing as recoverable any or all of said claims, and rendering judgment for plaintiff for $41,878.90. . . .”

This is what may be called the “shotgun” approach. By the “rifle” method, a number of specific assignments of error enable counsel and the court to concentrate on successive legal targets in an orderly manner. Needless to say, we prefer the “rifle” method.

There having been no assignments of error directed to any of the findings of fact, they are accepted as verities. Thorndike v. Hesperian Orchards, Inc. (1959), 54 Wn. (2d) 570, 343 P. (2d) 183 (and cases in its train). There being no factual issues in the case, the appellant must rely on issues of law. Its position is that since the contractor chose to keep the contract alive through his continuing performances, the contract defines the rights and obligations of the parties so completely that every item of additional compensation claimed by the contractor is covered directly or indirectly thereby and there is no room for quantum meruit.

Our inquiry, then, as to each item is not as to whether loss was sustained by the contractor or the amount of it, but whether (having the terms of the contract in mind) the contractor was entitled to recover on that particular item. We shall proceed to a consideration of appellant’s position on each of the items making up the judgment of $41,878.40.

Item 1—$ 4,300.00 for increased operating costs resulting from latent subsurface conditions. These subsurface conditions made it necessary to waste the excavated ma *821 terial which was so difficult to move that the contractor’s equipment could be worked at only 56 per cent of its normal capacity, thereby increasing his operating costs by $4,300.00.

Item 2—$13,391.04 for increased operating costs caused by the order to waste the excavation material because of its unsuitability for embankment purposes. This more than tripled the amount of material taken from the common borrow pits, which, in turn, made it necessary to secure and open other common borrow pits, thus making the material cost more than anticipated. The contractor also had to transport the material over a greater distance and to change plans for placing it.

Item 3—$10,475.06 for increased costs resulting from increased requirements for select roadway borrow material. The subsurface conditions raised these requirements beyond the capacity of the original select borrow pit and forced the contractor to locate and utilize an additional pit more distant from the work area.

As to these three items, the appellant contends that the following provisions of the Standard Specifications, incorporated in the contract, prevent any recovery: Section 2.04 which requires a careful examination of the site; Section 4.04A which requires notice in writing to • be given by the contractor of subsurface or latent physical conditions differing materially from those indicated in the contract; and the payment for “extra material” requires the parties to invoke § 4.03 of which condition (3) is applicable.

We are satisfied that the contractor made as careful an examination of the site as the circumstances required. The “changed conditions” section (4.04A) is controlling here, and it is quite similar to that found in other standard construction contracts. Construing such sections, courts have generally allowed recovery for additional costs when the condition complained of could not reasonably have been *822 anticipated by either party to the contract. General Cas. Co. of America v. United States (1955), 127 F. Supp. 805; Shepherd v. United States (1953), 113 F. Supp. 648. And this is true despite admonitory or exculpatory phrases such as those requiring the contractor to carefully examine the site. Thomsen-Abbott Constr. Co. v. City of Wausau (1960), 9 Wis. (2d) 225, 100 N. W. (2d) 921; Ruff v. United States (1942) 96 Ct. Cl. 148.

However, a finding that the contractor should have anticipated the condition will bar recovery. Morrison v. State Highway Comm. (1960), 225 Ore. 178, 357 P. (2d) 389, 85 A. L. R. (2d) 203; Leal v. United States (1960), 276 F. (2d) 378.

The critical question is whether the contractor should have discovered or anticipated the presence of wet subsurface material containing large boulders. This is a question of fact. Tribble v. Yakima Valley Transp. Co. (1918), 100 Wash. 589, 171 Pac. 544; Morrison v. State Highway Comm., supra. The trial court here found that:

“. . . The latent subsurface conditions encountered were neither apparent from a physical examination of the ground prior to construction nor disclosed from an examination of the plans, and were materially different from conditions indicated on the plans. . . .” Finding No. 5.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Skanska Usa Building Inc., V. 1200 Howell Street, Llc
Court of Appeals of Washington, 2025
Pease & Sons, Inc. v. Turner Construction Company
Court of Appeals of Washington, 2024
NOVA Contracting, Inc. v. City of Olympia
426 P.3d 685 (Washington Supreme Court, 2018)
General Construction Company v. Public Utility District No. 2
380 P.3d 636 (Court of Appeals of Washington, 2016)
King County v. Vinci Construction Grands Projets/Parsons RCI/Frontier-Kemper, JV
191 Wash. App. 142 (Court of Appeals of Washington, 2015)
City of Seattle v. Davis
306 P.3d 961 (Court of Appeals of Washington, 2012)
City Of Seattle v. Robert D. Davis
Court of Appeals of Washington, 2012
Young v. Young
164 Wash. 2d 477 (Washington Supreme Court, 2008)
Dragt v. Dragt/DeTray, LLC
139 Wash. App. 560 (Court of Appeals of Washington, 2007)
Mike M. Johnson, Inc. v. Spokane County
150 Wash. 2d 375 (Washington Supreme Court, 2003)
Mike M. Johnson, Inc. v. County of Spokane
78 P.3d 161 (Washington Supreme Court, 2003)
Mike M. Johnson, Inc. v. County of Spokane
49 P.3d 916 (Court of Appeals of Washington, 2002)
Mike M. Johnson, Inc. v. Spokane County
49 P.3d 916 (Court of Appeals of Washington, 2002)
Bort v. Parker
42 P.3d 980 (Court of Appeals of Washington, 2002)
Basin Paving Co. v. Mike M. Johnson, Inc.
107 Wash. App. 61 (Court of Appeals of Washington, 2001)
Dan Nelson Construction, Inc. v. Nodland & Dickson
2000 ND 61 (North Dakota Supreme Court, 2000)
Douglas Northwest, Inc. v. Bill O'Brien & Sons Construction, Inc.
828 P.2d 565 (Court of Appeals of Washington, 1992)

Cite This Page — Counsel Stack

Bluebook (online)
399 P.2d 611, 65 Wash. 2d 817, 1965 Wash. LEXIS 775, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bignold-v-king-county-wash-1965.