Schuehle v. City of Seattle

92 P.2d 1109, 199 Wash. 675
CourtWashington Supreme Court
DecidedAugust 1, 1939
DocketNo. 27367. En Banc.
StatusPublished
Cited by7 cases

This text of 92 P.2d 1109 (Schuehle v. City of Seattle) is published on Counsel Stack Legal Research, covering Washington Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Schuehle v. City of Seattle, 92 P.2d 1109, 199 Wash. 675 (Wash. 1939).

Opinions

Millard, J.

On December 20,1935, Martin Schuehle

entered into a written contract with the city of Seattle, under the terms of which he was obligated to construct, according to certain plans and specifications, a reinforced concrete bridge, known as Schmitz park bridge, on Admiral way. Two hundred and seventy days were specified as the time for the completion of the work after notice to begin, which was given February 3, 1936, and completion was certified January 15, 1937. The two hundred and seventy days expired November 1, 1936, and an extension of time of forty-five days was then granted.

The contract divided the work into ten separate items, for each of which payment of an amount, lump sum or unit price, was specified in the contract as follows:

Items No. Dollars Cents Unit

Engineering, 10,780.00

Advertising, 250.00 11,030 00 ..........

Clearing and Grubbing 1 3,800 00 lump sum

Excavation 2 2 00 Per Cu. Yd.

Embankment 3 1 00 Per Cu. Yd.

Concrete, Class “B” 4 21 00 Per Cu. Yd.

Concrete, Class “D” 5 18 00 Per Cu. Yd.

Reinforcing Steel 6 05 Per Pound

Copper Work 7 60 Per Pound

Lighting System Complete 8 1,200 00 Lump Sum

Drainage System Complete 9 650 00 Lump Sum

Reinforced Concrete Pavement 10 20 00 Per Cu. Yd.

Figured on a basis of quantity estimates made by the city engineer, the totals amounted to $116,038. The principal item was class B concrete, estimated at 2,236 cubic yards at $21 per yard, a total of $46,956.

Prior to the date of the execution of the contract, the city and the contractor agreed to change the plans and credit the city as follows:

*677 Detour traffic, by removal of the bridge on the site and permitting the use of corbels, $1,000. This was done, and the contractor concedes credit to the city under the quantum meruit rule that, where a service is actually performed as provided in an abortive or ineffective contract, the price specified therefor constituted the reasonable value of the service. The agreement to eliminate the lighting system and credit the city in the amount of $1,200 was not carried out, as the city later required installation of that system. The city conceded that the contractor was entitled to credit for $1,200 plus $225 expense incurred by him in obtaining a new subcontract for that work.

The agreement to eliminate “the most expensive features of the railing and its supporting structure,” amounting to $2,800, was not fulfilled according to the agreement, although changes were made in those features for which it appears the city endeavored to charge appellant $2,000, which is included in the final estimate as part of debit item of $3,033.80. That is, under the foregoing agreement, which is known as the “$5,000 agreement,” the city endeavored to reduce the cost of the bridge and came to an agreement with the contractor as to the amount of. credits the city should receive therefor in the event of the fulfillment of the agreement. On or about the time the contract was awarded, the city engineer made a report to the board of public works, in which he referred to the $5,000 agreement and stated that further changes were then contemplated by the city affecting the final bid quantities which would result in considerable savings to the city, and with no additional cost to it except for small alterations in form work.

The original plans for this construction work contemplated four street car tracks across the bridge and provided for the construction of slots to accommodate *678 the tracks. The board of public works did not approve until February 27, 1936, the proposed elimination of the street railway slots. This change effected considerable savings in the floor, main carrying frames, and footings, and, of course, involved redesign of those units, which had been under way since the date the contract was awarded. There is evidence to the effect that the contractor was not notified and knew nothing of the contemplated changes (those additional to the changes contemplated by the “$5,000 agreement”) until subsequent to two changes — which he signed— pertaining to class D or footings concrete. The right of the city to credit on class D concrete is not questioned. The elimination of the street railway slots enabled the city to reduce the quantity of class B concrete by 129.49 cubic yards in the span of the bridge.

For clarity, we describe the bridge as consisting of the horizontal span, the perpendicular legs, and the earth-retaining wall system outside of the legs. All of these are class B concrete and are covered by item 4 of the contract. The footings of the legs are class D concrete and constitute a separate item (No. 5) of the contract.

The principal parts of the span are four ribs (hollow-box type with two side walls for each), the top slab, bottom slab, beams, diaphragms, and curbs, and the sidewalk, railing and support. The plans for the slabs, frame walls, beams, diaphragms, and curbs were changed by reduction, in most instances, of the thickness in varying amounts up to six out of fifteen and one-half inches in the top slab or thirty-nine per cent in quantity; three out of twelve inches in the curbs, one out of nine inches in the frame walls, except the two walls which form the outside of the bridge, which were first reduced and again changed, and as much as one out of six inches in other parts. The reduction *679 for the entire span as stated above amounted to 129.49 cubic yards of class B concrete or thirteen per cent of the yardage in the span. This is approximately seven per cent of all the concrete in the bridge and, under the testimony, is several times the usual or reasonable variation between the yardage specified in the plans and the actual yardage of the completed structure.

The evidence is to the effect that there was no reduction in the cost of falsework and forms for the changed parts which was included in the unit price of the class B concrete, and the average cost was not less than fourteen dollars per cubic yard for each of the 129.49 cubic yards eliminated by the changes, which, of course, amounted to a corresponding reduction in compensation or loss to the contractor. The changes resulted in an additional loss to the contractor of $1.00 per yard, the extra cost of placing steel and concrete, and working in the narrower spaces inside of the forms set closer together to make the parts thinner.

The .change in plans necessitated changes in forms constructed according to the original plans prior to the changes. Changes were made in the forms at the shop, which changes resulted in expense and loss to the contractor. Other changes which were not of a major nature were made on the job to make previously constructed forms meet the changes in the plans. The contractor was paid for the cost of the latter changes. There were other changes in the class B concrete plans in relation to the earth-retaining wall system, changes in reinforcing steel were made, and there was a delay of a number of months in completion of the work, caused by conditions which resulted from class B concrete changes.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Young v. Young
164 Wash. 2d 477 (Washington Supreme Court, 2008)
V. C. Edwards Contracting Co. v. Port of Tacoma
503 P.2d 1133 (Court of Appeals of Washington, 1972)
Bignold v. King County
399 P.2d 611 (Washington Supreme Court, 1965)
Hensler v. City of Los Angeles
268 P.2d 12 (California Court of Appeal, 1954)
State Ex Rel. Schuehle v. Superior Court
98 P.2d 1073 (Washington Supreme Court, 1940)

Cite This Page — Counsel Stack

Bluebook (online)
92 P.2d 1109, 199 Wash. 675, Counsel Stack Legal Research, https://law.counselstack.com/opinion/schuehle-v-city-of-seattle-wash-1939.