McHugh v. City of Tacoma

135 P. 1011, 76 Wash. 127, 1913 Wash. LEXIS 1795
CourtWashington Supreme Court
DecidedOctober 24, 1913
DocketNo. 11243
StatusPublished
Cited by7 cases

This text of 135 P. 1011 (McHugh v. City of Tacoma) is published on Counsel Stack Legal Research, covering Washington Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
McHugh v. City of Tacoma, 135 P. 1011, 76 Wash. 127, 1913 Wash. LEXIS 1795 (Wash. 1913).

Opinion

Mount, J.

The plaintiff brought this action to recover money alleged to be due from the defendant city on the completion of a contract between him and the city, for the construction of a water pipe line and telephone line from the McMillan reservoir, in Pierce county, to South “J” street and Wright avenue, in the city of Tacoma.

It is alleged in the complaint that final payment upon the contract amounted to $76,761.56, which was retained by the city until final completion of the contract, and that the same is now due. It is further alleged that certain extras, aggre[129]*129gating an additional amount of $50,814.75 is also due upon the contract. Upon issues made by the complaint, answer and reply, the cause was tried to the court without a jury. At the conclusion of the trial, the court made certain findings, and concluded that the plaintiff was entitled to a judgment against the defendant for $16,827.02. Judgment was entered for that amount. The plaintiff has appealed.

The facts are substantially as follows: In the year 1910, the city, being desirous of obtaining ah additional water supply, enacted an ordinance which provided therefor. This ordinance was a proposal to be submitted to the voters for ratification or rejection. It was passed on January 5, 1910, and provided that the proposal be submitted to the electors of the city on the 5th day of April, 1910. It provided for detailed plans and specifications and for the method of payment for the construction of the water system. It was submitted to the electors of the city at the time stated, and was approved by the required vote.

This ordinance provided, among other things, that, if the proposal for constructing the water system should be adopted, it should be the duty of the commissioner of light and water of the city to cause all necessary surveys and examinations of lands to be made, and to cause all rights of way, water rights, easements and privileges necessary and proper for the construction, maintenance and operation of the water system to be acquired, and after proper resolutions of the city council, to cause to be prepared full detailed plans and specifications for the water system, with an estimate of the probable cost of the same in detail and as a whole. It provided that, when directed to do so by resolution of the city council, the commissioner of light and water should advertise for bids for the construction of the water system according to the plans and specifications on file in his office, or as the same may have been modified by resolution of the city council; and that the advertisement for bids should stipulate that bids should be [130]*130made in the manner prescribed, and under the terms and conditions as to bids for public work as provided in the charter of the city; that contracts should be entered into for material and work of constructing the water system, and should provide for payment therefor only in special water fund warrants at par. The ordinance also provided: “That whenever during the progress of the work under any contract any work or material not prescribed in the plans and specifications for said work shall be ordered’ by resolution of the city council, the same shall be done or furnished by the contractor at actual cost and ten per cent added.”

After the passage of this ordinance and its approval by the people of the city of Tacoma, plans and specifications were made by the commissioner of light and water, or under his direction, and bids were regularly called for in accordance with these plans and specifications. These plans and specifications provided for a pipe line 58 inches in diameter from outside to outside, to be laid- under the earth in a cut or trench eight feet wide at the bottom, and at a depth sufficient to permit the pipe line to be covered to a depth of not.less than % feet. The pipe line provided for in the plans and specifications from the McMillan reservoir to Wright avenue and South “J” street in the city of Tacoma was about fifteen miles in length.

The plans and specifications submitted to the bidders provided that the pipe line should begin at the McMillan reservoir, and extend thence westerly along Collins’ road a distance of six and one-half miles to Johnson’s road; thence following Johnson’s road north a distance of three and one-half miles, thence west along South Seventy-Second street, in the city of Tacoma, about three miles, thence north along Park avenue a distance of one and three-fourths miles to South Forty-Second street, thence west about one-fourth of a mile on Forty-Second street to South “J” street, thence north about one mile on South “J” street to Wright avenue.

Upon the plans and specifications, quantities estimated to [131]*131be necessary to construct the pipe line were stated. Each bidder was furnished with a form for his bid, the approximate quantities of work to be done and materials to be furnished, and a description of the material and of the character of the work, the form of his contract, and bond. Plans and specifications for the work were on file in the office of the commissioner of light and water of the city. The bids were called for and let upon the unit or quantity system.

The appellant’s bid was determined by the council to be the lowest. It was as follows:

Clearing, per acre....................-................. $75.00

Grubbing, per acre.................................... 100.00

Excavation — solid rock, per cu. yd..................... 1.00

“ loose “ “ “ “ ..................... .80

“ earth “ “ “ “ ..................... .44

WOODEN STAVE PIPE

Staves in place, per lin. ft. of pipe..................... 1.58

Bands, complete in place, each........................ .64

Air valves complete in place, each..................... 100.00

Blow-offs complete in place, each...................... 65.00

Waste pipe in place, per lin. ft....................... 1.50

Cast iron elbows complete in place, each............... 25.00

RAILWAY AND COUNTY ROAD CROSSINGS

Concrete in place per cubic yard........................ 8.00

Timber in place, per thousand feet, B. M............... 25.00

TELEPHONE LINE

Telephone line with poles complete, per mi........... 250.00

“ “ without poles complete, per mi.......... 115.00

Total amount of bid............................$417,441.00

This bid of the appellant was accepted, and on the 29th day of May, 1911, the appellant entered into a contract with the city of Tacoma for the work. The contract, among other things provided:

“Whenever during the progress of the work of said contract any work or material not contained in the plans and specifications thereof shall be ordered by resolution of the city council, the same shall be done or furnished by the contractor at actual cost and ten per cent added.”

[132]*132The specifications, which were referred to in the contract, and made a part thereof, provided as follows:

“The city shall have the right to make any changes in lines, grades and plans that may be deemed advisable by the commissioner after the work is started, and the contractor shall make such changes upon the order of the commissioner.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bignold v. King County
399 P.2d 611 (Washington Supreme Court, 1965)
Walla Walla Port District v. H. G. Palmberg
280 F.2d 237 (Ninth Circuit, 1960)
Mall Tool Co. v. Far West Equipment Co.
273 P.2d 652 (Washington Supreme Court, 1954)
Schuehle v. City of Seattle
92 P.2d 1109 (Washington Supreme Court, 1939)
Wade v. City of Tacoma
230 P. 99 (Washington Supreme Court, 1924)
Wright v. City of Tacoma
151 P. 837 (Washington Supreme Court, 1915)
International Contract Co. v. City of Tacoma
140 P. 373 (Washington Supreme Court, 1914)

Cite This Page — Counsel Stack

Bluebook (online)
135 P. 1011, 76 Wash. 127, 1913 Wash. LEXIS 1795, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mchugh-v-city-of-tacoma-wash-1913.