International Contract Co. v. City of Tacoma

140 P. 373, 79 Wash. 311, 1914 Wash. LEXIS 1199
CourtWashington Supreme Court
DecidedApril 28, 1914
DocketNo. 11474
StatusPublished
Cited by1 cases

This text of 140 P. 373 (International Contract Co. v. City of Tacoma) is published on Counsel Stack Legal Research, covering Washington Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
International Contract Co. v. City of Tacoma, 140 P. 373, 79 Wash. 311, 1914 Wash. LEXIS 1199 (Wash. 1914).

Opinion

Parker, J.

The International Contract Company commenced this action in the superior court for Pierce county, against the city of Tacoma, to recover the sum of $33,885.52, claimed by it as a'balance due from the city upon the construction of the head works, tunnels, and river crossing near there, of the city’s Green river gravity water system. The city denied the factss pleaded by the contract company upon which its claim was rested, and made a counterclaim for which affirmative judgment was demanded, claiming certain errors and mistakes in estimates upon which payments to the contract company were made during the progress of the work. A trial before the court without a jury resulted in findings and judgment in favor of the contract company for the sum. of $1,041.18, from which it has appealed.

In January, 1910, the city council of Tacoma passed an ordinance proposing to the voters of the city, as an addition to its existing water system, a gravity water supply to be taken from Green river, at a point in King county, some thirty miles east of the city, to be conveyed to the city by gravity at an estimated cost of two million dollars. This proposal, having been submitted to the voters at an election held for that purpose, was' duly ratified. Thereafter, plans and specifications for the construction of the head works, together with certain other work near there, were prepared, and bids invited for that portion, as a section of the work, to be constructed under one contract. Bids were invited and submitted upon the unit basis, “approximate quantities of work to be done” being stated in the instructions to bidders. Appellant submitted its bid as follows:

“The undersigned hereby proposes to furnish all the material and construct the headworks, tunnels and river crossing for a gravity water supply on Green river for the city of Tacoma, in accordance with the maps, profiles and plans on file in the office of the commissioner of light and water of Tacoma, and the attached specifications and contract, for the prices named in the following schedule:
[314]*314Headworks :
Excavating earth, per cu. yd..............$ .50
Excavating rock, per cu. yd............... 1.80
Concrete masonry, per cu. yd.............. 10.50
Cement plaster, per sq. yd................ .30
Steel reinforcing bars, per pound.......... .039
Structural steel, per pound............... .062
Railroad rails, per pound. . . „............. . 035
Washout and regulating gates, in place, each 430.00
Steel pipe, per lin. ft..................... 25.00
Timber in place, per 1000 ft. B. M.. .'...... 28.00
Tunnel excavation, per cu. yd............. 3.00
Tunnel :
Excavating earth, per cu. yd..............$ 1.00
Excavating rock, per cu. yd............... 1.50
Concrete masonry, per cu. yd.............. 10.50
Tunnel excavation, per cu. yd............. 4.00
Timbering in place, per 1000 ft. B. M....... 28.00
River Crossing:
Excavating earth, per cu. yd..............$ 2.00
Excavating rock, per cu. yd............... 4.00
Concrete masonry, per cu. yd.............. 10.50
Kalemein pipe, per lin. ft................. 2.00
Steel pipe, per lin. ft..................... 24.00
Blow-offs, in place, each.................. 100.00”

This was accepted by the city as the lowest bid, and thereupon a written contract was entered into accordingly.

Green river flows in a westerly direction where the work involved in this contract is located. The head works consist of a concrete dam across the river, an intake on the north side of the river, a tunnel at the intake, approximately 100 feet long, through a point of rock forming a natural wall at the edge of the river, and a settling basin at the westerly end of the tunnel. This tunnel is known as tunnel No. 1. Other work within the contract consists of tunnel No. 2, 1,200 feet long; tunnel No. 3, 275 feet long; conduits several hundred feet long between the settling basin and tunnel No. 2, and between tunnels No. 2 and No. 3, all on the north side of the river; and also a conduit across the river from the westerly [315]*315end of tunnel No. 3 to the southerly side of the river. The work was under the supervision of the city’s commissioner of light and water and his authorized representatives upon the ground.

The specifications for the work contained the following:

“The city shall have the right to make any changes in lines, grades and plans that may be deemed advisable by the commissioner after the work is started and the contractor shall make such changes upon the order of the commissioner. No allowance shall be made the contractor on account of such changes, except where the quantities of materials are increased and in such cases the contractor shall be paid at the contract prices for the additional amount of material furnished and work done. The contractor shall be paid at the contract prices for only the actual amount of material furnished and work done, regardless of the approximate quantities as stated herein.”

The contract proper contained the following:

“Witnesseth that the said contractor, in consideration of the covenants, agreements and payments hereinafter mentioned to be performed and made by said city, hereby covenant and agree under the penalty expressed in the attached bond bearing even date herewith, to furnish all the material and construct the headworks, tunnels and river crossing for a gravity water supply system on the Green river for the city of Tacoma in accordance with the attached proposal and specifications which are hereby declared and accepted as parts of this agreement, and to accept payment for the actual amount of material furnished and labor performed at the prices named in said proposal as full compensation under this contract.
“The contract prices shall include the furnishing of all machinery, appliances and tools, and all materials and labor and all other expenses necessary to construct the headworks, tunnels and river crossing complete according to the maps, profiles, plans and specifications on file in the office of the commissioner of light and water of said city, and the expense of maintaining the work in good condition until it is accepted by the commissioner. All items of labor, material and expense necessary to finish the headworks, tunnels and river [316]*316crossing complete that are not enumerated in the schedule shall be included in the prices bid for the different classes of work.
“Extea Woek.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Wright v. City of Tacoma
151 P. 837 (Washington Supreme Court, 1915)

Cite This Page — Counsel Stack

Bluebook (online)
140 P. 373, 79 Wash. 311, 1914 Wash. LEXIS 1199, Counsel Stack Legal Research, https://law.counselstack.com/opinion/international-contract-co-v-city-of-tacoma-wash-1914.