Criswell v. Board of Directors of Everett School District No. 24

75 P. 984, 34 Wash. 420, 1904 Wash. LEXIS 369
CourtWashington Supreme Court
DecidedMarch 23, 1904
DocketNo. 4773
StatusPublished
Cited by22 cases

This text of 75 P. 984 (Criswell v. Board of Directors of Everett School District No. 24) is published on Counsel Stack Legal Research, covering Washington Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Criswell v. Board of Directors of Everett School District No. 24, 75 P. 984, 34 Wash. 420, 1904 Wash. LEXIS 369 (Wash. 1904).

Opinion

Mount, J.

This action was brought in the lower court by the plaintiff, a resident and taxpayer, to restrain the payment of certain school warrants, issued by the officers of school district No. 24, in Snohomish county, in payment of the contract price of a school building for said district, constructed by defendant Grant. TJpon a trial the court entered a decree, restraining payment of a part of the warrants and refusing to restrain payment of the balance, and also ordered the school district to pay $500 as an attorney’s fee to plaintiff’s attorneys. The plaintiff appeals from that part of the decree refusing to restrain the payment of all the warrants. Defendant Grant appeals from that part of the decree restraining the payment of warrants. The school district appeals from that part awarding an attorney’s fee in favor of the plaintiff.

The amended complaint contains four causes of action, one of which was abandoned by stipulation. The gist of the other three is, (1) failure of the contractor to construct the building in accordance with the plans and specifications; (2) that the contract was void because of failure of the school board to advertise for bids for the erection of the building; and (3) fraud and collusion in mating the contract. The answer of the defendant Grant, after denying the material.allegations of the complaint, alleges substantial compliance with the contract, but admits certain minor departures and omissions from the plans and speci[425]*425cations, and denies any fraud or collusion. For affirmative defenses lie alleges, tbe facts in relation to tbe advertisement for bids; tbat his bid was tbe lowest; tbat, after certain changes in tbe plans and specifications to conform tbe building to a new site, tbe contract was let to him, and was substantially performed before tbe action was brought. For a second affirmative defense be alleges laches on tbe part of tbe plaintiff. Tbe answer of tbe school board denies generally tbe material allegations of tbe complaint, but admits certain departures from tbe original plans, and also pleads laches on the part of tbe plaintiff. Tbe plaintiff for reply denies tbe new matter set up in tbe answers.

Upon tbe facts, as they appear in tbe record, there is substantially no dispute, except as to tbe reasonable value of tbe building which was erected. They are briefly as follows: In February, 1902, the school district was reorganized under tbe law providing for a district in cities containing over 10,000 inhabitants. At tbat time tbe school buildings in tbe district were inadequate to accommodate tbe school children, and there- was great necessity for another school building. Tbe city board of education determined to erect an eight-room school building on tbe site of tbe Jefferson school grounds, to be known as tbe “Jefferson Annex.” Architects were thereupon employed to prepare plans and specifications for such building. A building was designed, consisting of a two-story wooden structure, resting on a basement of masonry. On account of tbe site being a hillside, tbe basement walls were not of tbe same dimensions on all sides. Tbe superstructure contained a number of ornamental wooden columns at tbe entrances. Tbe specifications provided for a complete eight-room building, provided with ventilating and beating apparatus and a basement.

[426]*426Upon these plans and specifications, hids were advertised for. In response to the advertisement, ten bids were filed by different parties. The hid of defendant Grant for $32,900 was the lowest. Upon receipt of these bids, the board was of the opinion that the building was more expensive than the district wanted to build, and a meeting of the electors of the district was called to consider the question of the cost of the building. The result of this meeting was an authorization to the board to purchase another site for the proposed building, after eliminating the ornamental columns and a portion of the foundation.

The board accordingly purchased another site on a level place, and directed the architects to amend the specifications so as to eliminate the ornamental columns and make the basement conform to the new site. These changes, and others necessitated by the location, were made in the plans and specifications. The size of the building Was also slightly reduced without the knowledge of the board. The architects thereupon gave the board an estimate of $6,230 as the amount which should be deducted on account of these changes. Thereafter, on March 29, 1902, the board adopted a resolution authorizing the erection of the building on the new site, “in accordance with the changes and alterations, as suggested by the board and architects, of the original plans;” and the name of the new. building-was changed from “Jefferson Annex” to “Jackson School.”

Uo further advertisement for bids-was published,-but the board deducted $6,230, as estimated by the .architect to be the difference in cost between the original and the modified plans and specifications, from .the bid of Mr. Grant, and authorized a contract with him-for the erection of the building for $26,670. This contract was-entered into on April 1, 1902. It is the usual builder’s-contract, providing for deductions and extras and for the payment [427]*427of seventy-five per cent of the value of the work and materials, as the work progressed. Bonds were given by the contractor, as required by law, for the faithful performance of the contract.

Work was begun on the building on May 1, 1902. During the progress of the work, the district decided to make a change in the heating plant, and it was accordingly made, and a more expensive heating plant was installed, and an allowance of $1,500 was made to the contractor on account thereof. Extra Work on the foundation was. ordered and also allowed, to the amount of $892.50. Numerous other minor changes were made by the contractor for his benefit, without the knowledge or authority of the board, which changes are estimated to amount to about $1,200. In September, 1902, when this action was begun, the building was substantially completed, and was shortly thereafter put to use by the district, and was occupied as a school building during the trial of the case. Warrants amounting to' $27,092.50 had been issued by the board, and delivered to the contractor, and disposed of by him before the action was begun. The holders of these warrants were not made parties to the action. Defendant- Grant held none of the warrants. The building erected is a good, substantial, modem school building, well adapted to the purposes intended, and well supplied with sanitary, lighting, and heating facilities, but lighter in structure, somewhat smaller in size, and- cheaper in many details of construction, than the building first advertised for. '

In addition to the facts above stated, the trial -court found that the defendant Grant and the architects, who were the agents of the board, collusively and fraudulently changed the plans and specifications, and substituted in[428]*428ferior materials in the course of the construction of the building, in order to obtain an excessive and dishonest profit; that the reasonable value of the building, as completed, is $20,535.56. The court upon its findings entered a decree restraining the district from issuing any further warrants, and restraining the payment of all issued in excess of the reasonable value of the building, as stated, ordered the school district to pay to plaintiff’s attorneys $500, and entered judgment against defendant Grant for the costs of the action.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State v. O'CONNELL
523 P.2d 872 (Washington Supreme Court, 1974)
Von Holt v. Izumo Taisha Kyo Mission
44 Haw. 147 (Hawaii Supreme Court, 1960)
Kerr v. King County
259 P.2d 398 (Washington Supreme Court, 1953)
Hailey v. King County
149 P.2d 823 (Washington Supreme Court, 1944)
School Dist. No. 37, Clark County v. Isackson
92 F.2d 768 (Ninth Circuit, 1937)
Council of Village of Bedford v. State Ex Rel. Thompson
175 N.E. 607 (Ohio Supreme Court, 1931)
Jones v. City of Centralia
289 P. 3 (Washington Supreme Court, 1930)
Besoloff v. Whatcom County
233 P. 284 (Washington Supreme Court, 1925)
Appleford v. Snake River Mining, Milling & Smelting Co.
210 P. 26 (Washington Supreme Court, 1922)
Gabrielson v. Gorin
159 P. 387 (Washington Supreme Court, 1916)
Davis v. City of Wenatchee
149 P. 337 (Washington Supreme Court, 1915)
Alsmeier v. Adams
105 N.E. 1033 (Indiana Court of Appeals, 1914)
Ettor v. City of Tacoma
137 P. 820 (Washington Supreme Court, 1914)
McHugh v. City of Tacoma
135 P. 1011 (Washington Supreme Court, 1913)
In re the Guardianship of Williamson
134 P. 1066 (Washington Supreme Court, 1913)
State ex rel. Maddaugh v. Ritter
134 P. 492 (Washington Supreme Court, 1913)
Richards v. Bussell
127 P. 198 (Washington Supreme Court, 1912)
Turner Investment Co. v. City of Seattle
126 P. 426 (Washington Supreme Court, 1912)
Green v. Okanogan County
111 P. 226 (Washington Supreme Court, 1910)
McGuinness v. Hargiss
105 P. 233 (Washington Supreme Court, 1909)

Cite This Page — Counsel Stack

Bluebook (online)
75 P. 984, 34 Wash. 420, 1904 Wash. LEXIS 369, Counsel Stack Legal Research, https://law.counselstack.com/opinion/criswell-v-board-of-directors-of-everett-school-district-no-24-wash-1904.