Board of Commissioners v. Cincinnati Steam Heating Co.

12 L.R.A. 502, 27 N.E. 612, 128 Ind. 240, 1891 Ind. LEXIS 306
CourtIndiana Supreme Court
DecidedMay 14, 1891
DocketNo. 13,861
StatusPublished
Cited by20 cases

This text of 12 L.R.A. 502 (Board of Commissioners v. Cincinnati Steam Heating Co.) is published on Counsel Stack Legal Research, covering Indiana Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Board of Commissioners v. Cincinnati Steam Heating Co., 12 L.R.A. 502, 27 N.E. 612, 128 Ind. 240, 1891 Ind. LEXIS 306 (Ind. 1891).

Opinion

Elliott, J.

On the 25th day of September, 1883, the board of commissioners of Gibson county entered into a contract with Joseph G. Miller for the erection of a courthouse. The plans and specifications were adopted at a meeting of the board on the 7th day of August, 1883, and notices inviting proposals for building the court-house were published for more than six weeks prior to the time the contract was awarded. The notice was published in a newspaper of general circulation in the county of Gibson. Miller entered upon the work under the contract, and on the 29th day of December, 1884, made a contract with the appellee to furnish a steam heating apparatus and appliances for the court-house. The plans and specifications agreed upon by Miller and the appellee were different from those adopted in the first instance by the board of commissioners, but what the differences were does not appear. The appellee entered upon the work required by its contract and furnished labor and material. On the first day of April, 1885, it received from Miller, in part payment, three thousand dollars, and on the 20th day of June of that year there was owing from Miller to the appellee the sum of two thousand and two hundred dollars; this sum Miller failed to pay, although it had been due for more than two months. The architects, McDonald & Bro., refused to issue an estimate, and the appellee tendered to the board a bond conditioned as follows:

“ The condition of this obligation is such, whereas the said Cincinnati Steam Heating Company has a contract with one Joseph G. Miller, who is chief contractor for the erection of a court-house in Gibson county, Indiana, to place certain steam heating apparatus in said court-house, for which it is to receive the sum of $6,665 in installments [242]*242equal to eighty-five per cent, of the value of the work done and material furnished as said job shall progress, and as there is now due to it the sum of $2,200, on said work on said contract, which said Miller has failed to pay, the said commissioners having refused to advance any more direct to said Miller on his said contract, but being willing and desirous of advancing to the said The Cincinnati Steam Heating Company direct the money now due, and to become due for its said work upon the approval of said architects, and propose to advance at once, at next meeting of said commissioners, the $2,200 aforesaid; now, therefore, if the said The Cincinnati Steam Heating Company shall complete its said job of work in accordance with the plans and specifications and terms of its said contract, and the work so completed shall be accepted by the McDonald Brothers, these presents shall be void, otherwise to remain in full force and virtue.”

The board accepted the bond while in session but made no entry of record. After the acceptance of the bond the board caused a warrant to issue to the appellee on which it received "two thousand two hundred dollars. The order directing the warrant to issue reads thus: “ Comes now Kenneth McDonald, architect on new court-house, and files estimate for work done and materials furnished for steam heating in the sum of twenty-two hundred dollars by Joseph G. Miller, the estimate having been assigned to the Cincinnati Steam Heating Company, and also showing that Joseph G. Miller has been previously paid the sum of $80,679, and making a total allowance of $82,879, and after hearing the evidence, and being fully advised, it is found that said claim ought to be allowed. It is now ordered that the Cincinnati Steam Heating Company be allowed the sum of twenty-two huudred dollars.”

The appellee fully performed its part of the contract, and on the 20th day of December, 1885, demanded an estimate, but the architect refused to certify one. On the 1st day of [243]*243February, 1886, the board entered an order declaring the court-house completed and ready for occupancy, and, pursuant to such order, possession was taken by the county officers and the records placed in the building. The county, by its officers, occupies the court house and uses the steam heating apparatus placed in it by the appellée. On the 14th day of April, 1886, the appellee presented its claim for the remainder due upon its contract, but its claim was rejected. ' There remains owing the appellee the sum of fourteen hundred and sixty-five dollars.

The appellants’ counsel contends that the board had no authority to contract for the steam heating apparatus, for the reason that no plans and specifications were ever placed on file in the auditor’s office, and no notice was published inviting proposals for furnishing the court-house with steam heating apparatus. This contention is based upon the provisions of the statute requiring plans and specifications for the construction of public buildings to be prepared and filed before advertising for proposals. Section 4243, R. S. 1881. We can not accept the views of counsel as correct. In our opinion the statute was not intended to prevent changes in plans and specifications from being made in cases where it becomes apparent in the progress of the work, that changes are required. We do not mean to be understood as holding that changes in the general plan of the work may be made at the pleasure of the board of commissioners, but we do mean to adjudge that changes may be made in details and in minor particulars. If the rigid rule for which the appellant contends were adopted, then the board could not change a window, a door, a chimney, or any like matter, and, certainly, the Legislature did not mean to establish a rule that would prevent such changes. Of course, no important general change in the plan of the building can be made, but a change in a matter of detail, such as the heating or lighting, maybe rightfully made when required. If the board of commissioners secures and files plans and specifications so full and [244]*244specific as to show the character of the proposed building, and duly advertises for proposals, the county can not escape liability without showing that changes in important particulars were made. This conclusion is fairly supported by the case of Bass Foundry, etc., v. Board, etc., 115 Ind. 234.

Neither the county nor its officers can with reason or justice ask that it shall be presumed that the board of commissioners either violated the law or acted in bad faith in ordering changes in a matter of detail, such as that of heating a court-house; on the contrary, the presumption is that what ■ was done was done rightfully and in good faith. Tt must, therefore, be presumed, in the absence of countervailing facts, that the changes respecting the steam heating apparatus were of such minor importance and so necessary that it was not only the right of the board- to order them made, but that it was its duty to cause them to be made. The county is using and enjoying the property placed in its possession by the appellee in good faith, and the least that it can do if it would keep and enjoy the property without paying for it, is to show such facts as make it clearly appear that the acts of its board of commissioners were unauthorized or illegal.

It is argued with ability and plausibility that there was no promise on the part of the board of commissioners to pay the appellee for the heating apparatus. In our judgment the contention, plausible as it is, can not prevail. The facts surrounding the parties when the bond was accepted by the commissioners furnish the light by which the contract must be read.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Walker v. Elkin
758 N.E.2d 972 (Indiana Court of Appeals, 2001)
Sekerez v. Lake County Board of Commissioners
345 N.E.2d 865 (Indiana Court of Appeals, 1976)
PETERS v. Ryan Construction Corp.
127 N.E.2d 242 (Indiana Court of Appeals, 1955)
Busch v. Joint Drainage District No. 49-79
198 Iowa 398 (Supreme Court of Iowa, 1924)
New Amsterdam Casualty Co. v. Madison County Trust Co.
142 N.E. 727 (Indiana Court of Appeals, 1924)
Way v. Baydush
112 S.E. 611 (Supreme Court of Virginia, 1922)
Smith v. Yost
125 N.E. 73 (Indiana Court of Appeals, 1919)
Alsmeier v. Adams
105 N.E. 1033 (Indiana Court of Appeals, 1914)
Shackleford v. Campbell
161 S.W. 1019 (Supreme Court of Arkansas, 1913)
Dale v. Gaither Lumber Co.
68 S.E. 134 (Supreme Court of North Carolina, 1910)
Howell v. Harvey
64 S.E. 249 (West Virginia Supreme Court, 1909)
Breen v. Mayne
118 N.W. 441 (Supreme Court of Iowa, 1908)
Miller v. State ex rel. Prather
74 N.E. 260 (Indiana Court of Appeals, 1905)
American Car & Foundry Co. v. Clark
70 N.E. 828 (Indiana Court of Appeals, 1904)
Board of Commissioners v. Gibson
63 N.E. 982 (Indiana Supreme Court, 1902)
Voris v. Star City Building & Loan Ass'n
50 N.E. 779 (Indiana Court of Appeals, 1898)
Spencer v. McLean
50 N.E. 769 (Indiana Court of Appeals, 1898)
Hyatt v. Bonham
49 N.E. 361 (Indiana Court of Appeals, 1898)
Carskaddon v. City of South Bend
39 N.E. 667 (Indiana Supreme Court, 1895)

Cite This Page — Counsel Stack

Bluebook (online)
12 L.R.A. 502, 27 N.E. 612, 128 Ind. 240, 1891 Ind. LEXIS 306, Counsel Stack Legal Research, https://law.counselstack.com/opinion/board-of-commissioners-v-cincinnati-steam-heating-co-ind-1891.