Shackleford v. Campbell

161 S.W. 1019, 110 Ark. 355, 1913 Ark. LEXIS 406
CourtSupreme Court of Arkansas
DecidedDecember 1, 1913
StatusPublished
Cited by2 cases

This text of 161 S.W. 1019 (Shackleford v. Campbell) is published on Counsel Stack Legal Research, covering Supreme Court of Arkansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Shackleford v. Campbell, 161 S.W. 1019, 110 Ark. 355, 1913 Ark. LEXIS 406 (Ark. 1913).

Opinion

Hart, J.,

(after stating the facts). Article 19-, section 16, of our Constitution provides that the contracts for erecting or repairing public buildings or bridges in any county, or for materials therefor, shall be given to the lowest responsible bidder under such regulation as may be provided by law. Appellant contends that under this provision of the Constitution, and under chapter 35 of Kirby’s Digest, the county court had no authority to order the changes made in the plans and specifications, and that the changes, as made, render the contract void. He relies upon the case of Fones Hardware Company v. Erb, 54 Ark. 645, to sustain his contention; but we do not think that case an authority for the position he has assumed. There, general plans were adopted for building a bridge across the Arkansas River in Pulaski County, and competitive plans and specifications were advertised for and received by the board of commissioners. Each bidder prepared his own plans and specifications and made his bid thereon, and the court said that it was plain that no two of the bids would be made upon the same basis, unless by accident, and therefore, under such a plan, there could be no competition among bidders. This was a palpable violation of the Constitution and statute regulating the erection of public buildings and bridges. Here, complete detailed plans and specifications were prepared by the architect and adopted by the county court. The advertisement for bids was made in accordance with the plans and specifications adopted; and it is perfectly evident that each bidder bid upon the same plans and specifications, and thus competitive bidding was secured.

It is conceded by appellant that the original contract was let in accordance with the provisions of the Constitution and statute's above referred to; but he contends that the modification of the contract was made without authority of law, and that this rendered the whole contract void. The original contract contained a provision that modifications of it might be made. The evidence shows that it is usual to insert in contracts for the erection of buildings of any magnitude provisions for modifications in the contract, so that necessary changes or alterations in the plans of the building may be made, and such clauses have been generally held to be valid when applied to contracts made between private individuals. In the absence of constitutional and statutory prohibition, there seems to be no good reason why such a clause may not be legally inserted in a contract for a public building. The power so to do is recognized in 11 Cyc. 485, but the author adds that in no event can the county board or court make important general changes in the plans of the building, and cites in support of the text the cases of Gibson County v. Cincinnati Steam Heating Company, 128 Ind. 240, 12 L. R. A. 502, and Kitchel v. Union County, 123 Ind. 540, 24 N. E. 366. Under the laws of Indiana, as in this State, contracts for the erection of public buildings must be let at public bidding after the plans and specifications have been adopted and filed in accordance with the statute. In the case last mentioned, certain taxpayers sought to enjoin the county from proceeding in the erection of the courthouse upon the ground that the specifications submitted to the bidders permitted alterations and changes. The Supreme Court of Indiana held that the objection was unavailing, and said that no prudent individual would make a contract for the construction of a building of any magnitude without incorporating a provision somewhere making specific and definite agreements concerning extra work, and that the provision complained of seemed to be of that character. In the first mentioned case, plans and specifications were adopted for the construction of a courthouse as required by law, and it was contended that there was no authority to contract for a steam heating apparatas for the reason that no plans or specifications were ever filed therefor and that the contract was not let at public bidding as required by the statute. In discussing an objection that the board had no authority to contract for the steam heating apparatus, the' Supreme Court of Indiana said: “In our opinion, the statute was not intended to prevent changes in plans and specifications from being made in cases where it became apparent in the progress of the work that changes are required. We do not mean to be understood as holding that changes in the general plan of the work may be made at the pleasure of the board of commissioners, but we do mean to adjudge that changes may be made in details and minor ‘ particulars. ’ ’

In the case of the Board of Commissioners v. Gibson, 63 N. E. (Ind.) 982, the court again had occasion to discuss the question. In that case, a contract to construct a courthouse was let, in accordance with the statute, to the lowest bidder, for $76,000. The contract contained a provision allowing changes and alterations to be made. After the contract was executed and the excavation for the building was commenced, it was discovered that, owing to the character of the soil, the foundation would have to be laid much deeper than was provided for in the contract. It was then suggested that a sub-basement could be added for very little more cost, and this was done at an additional cost of $20,000. The court held the modification thus made in the contract was valid, and in discussing the objections to its validity, said:

“The statute referred to was intended as a safeguard of the public interest, and we are disposed! to enforce it according to its spirit. We do not think, however, that it was intended to apply to a case like this, where a sudden and unforeseen emergency confronts a board of commissioners after it has regularly let a contract for a public building, and where it is to be desired to avoid delay, and not to put a new contractor on the work, but to have the work continued by the general contractor for the construction of the building. In such a case, where it can be said that the new work is but an incident of a work before regularly contracted for, and where it does not appear that the act of the parties was a mere effort to evade the statute, we do not think that the statute is applicable.”

The court also said:

“Where the parties act in good faith, the authority of the board to make changes without complying with the statute referred to should be determined, not primarily by the cost of the change, but by the relation that the change bears to the main work, and the circumstances that confront the commissioners when they order the change.”

In the case of Mueller v. Eau Claire Co., 84 N. W. (Wis.) 430, the court said:

“A clause in the contract provides that: ‘Should said committee, at any time during the progress of the work of said heating' plant, require any alteration, addition or omission from the work specified the same shall be done, and shall not affect or avoid this contract, and will be added to, or deducted from, the contract price, as may be, by a fair and reasonable valu- ' ation.’ Upon this the plaintiffs attempt to found an argument that it is an evasion of the statute, which says that the board shall prepare ‘complete’ plans and specifications for the work. This ‘smacks of over-refinement.’ It is the clause-usually put in building contracts to enable the owner to make changes, correct mistakes, or cause additions or omissions in order to make the building more truly conform to its intended use.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Gatzke v. Weiss
289 S.W.3d 455 (Supreme Court of Arkansas, 2008)
County of Greenlee v. Webster
215 P. 101 (Arizona Supreme Court, 1923)

Cite This Page — Counsel Stack

Bluebook (online)
161 S.W. 1019, 110 Ark. 355, 1913 Ark. LEXIS 406, Counsel Stack Legal Research, https://law.counselstack.com/opinion/shackleford-v-campbell-ark-1913.