Hensler v. City of Los Angeles

268 P.2d 12, 124 Cal. App. 2d 71, 1954 Cal. App. LEXIS 1701
CourtCalifornia Court of Appeal
DecidedMarch 23, 1954
DocketCiv. 19810
StatusPublished
Cited by41 cases

This text of 268 P.2d 12 (Hensler v. City of Los Angeles) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hensler v. City of Los Angeles, 268 P.2d 12, 124 Cal. App. 2d 71, 1954 Cal. App. LEXIS 1701 (Cal. Ct. App. 1954).

Opinion

FOX, J.

Defendant appeals from a judgment awarding damages for breach of contract and reimbursing plaintiff for expenditures incident to a suspension of work ordered by defendant.

Plaintiff, a licensed general contractor, entered into a contract with the city of Los Angeles on April 12, 1951, whereby he undertook “to furnish all equipment, material and labor necessary for the construction of, and to construct Stage 1 Runways and Taxiways and appurtenant work at the Los Angeles International Airport.” The total agreement between the parties embraced the following documents, which had been furnished to plaintiff in making his bid and which were incorporated by reference in the contract of April 12, 1951:

(a) Published notice inviting bids; (b) standard specifications for construction of airports; (c) special provisions designated as Specification No. 5021; (d) the contractor’s proposal; (e) bonds; and (f) plans for the Work.

The work to be performed by plaintiff was broken down into a detailed set of items embodied in a bid schedule which was contained in the contractor’s proposal, and incorporated into the contract. Each item related to an estimated quantity of work, payment for which was based upon unit prices for the various items of work.

*74 At the time the agreement was executed, automobile traffic which ordinarily proceeded on that part of Sepulveda Boulevard which then bordered one side of the airport had been rerouted to a temporary by-pass road running along the westerly end of the then existing runways. This by-pass road traversed an area which was ultimately to be a part of the airport. The contract included the installation of runways and taxiways over the area occupied by the temporary road, removal of the by-pass, and certain appurtenant work. Both parties knew that the completion of the work would require a discontinuance of traffic over the by-pass and knew that a new by-pass road was being constructed by a different contractor further to the west, which was scheduled for completion by June 30, 1951. The special provisions set up two priorities for plaintiff’s construction work. The first priority, to be completed by June 30, 1951, consisted substantially of the performance of all the work exclusive of the removal of the existing by-pass road and other construction work in the area occupied by that road. The entire job was to be finished by September 1,1951.

Plaintiff commenced work and progressed with his operations until August 20, 1951, at which time defendant issued change order No. 8, deleting certain portions of the work to be performed under the contract. The work so deleted consisted of items relating to the removal of the Sepulveda by-pass road and the installation of appurtenant work, as well as construction work on the runways and taxiways to be installed in the area adjacent to the by-pass road. Defendant ordered these deletions when it discovered that because of the refusal of the Division of Highways of the State of California to grant its consent for the connection of the new by-pass road with existent highways, it would be unable to remove traffic from the Sepulveda by-pass road and so make available to plaintiff the job site contemplated by the contract. As a result of these deletions, the work called for by the agreement remained in an unfinished condition. The new by-pass road was placed in operation several months later, following which defendant let a contract to another contractor for the performance of substantially all of the work which had been deleted from plaintiff’s contract.

The record also shows that while plaintiff was engaged in performance of the work, he was orally notified on May 31, 1951, to cease the mixing operations then taking place. A confirmatory written order was issued the following day. The stop *75 order was released on June 5,1951, but due to the time required for realignment of the personnel, material and equipment, work was not resumed until June 7, 1951. Plaintiff had received no prior warning that work would be halted, nor was he informed as to the reason for the stop order during the cessation of work.

Plaintiff’s complaint states two causes of action. In brief, the first alleges that the defendant’s deletion from the contract of the described items of work upon finding that it could not reroute traffic from the Sepulveda by-pass constituted a breach of contract by which he sustained damages. The second cause of action is based on a claim that he was entitled to be reimbursed for the actual money expended on the job during the period he ceased work pursuant to defendant’s stop order.

The court gave judgment in the sum of $38,421.30 on plaintiff’s first cause of action. The court found that the agreement between the parties contemplated the construction of a completed work of improvement and that the omissions contained in change order No. 8 left the work uncompleted. While the court recognized that defendant was accorded the right under the contract to make certain changes, within specified limitations, in the quantity of the work as might be considered necessary or desirable to complete fully and satisfactorily the proposed construction, it found that the deletions ordered were neither necessary nor desirable to complete the work in a satisfactory manner. The court also found that while the contract allowed defendant to omit items not of a major character deemed unnecessary to the project, the work eliminated by change order No. 8 was necessary to the project and that the effect of the ordered deletions was “to eliminate such an important part of the entire construction as to make the portion that had been constructed of little value for the use intended under the contract. ’ ’ Other findings relating to the first cause of action will be alluded to where pertinent in our subsequent discussion of the issues raised by defendant.

Judgment on the second cause of action was in the sum of $1,735.88. The court found that when defendant issued its stop order, plaintiff was engaged in mixing operations involving the use of an equipment train which sometimes consisted of a tractor and mixer, to which, at times, a water trailer was coupled; occasionally the equipment train comprised a tractor, mixer, water trailer and oil trailer. The tractor was tearing and loosening parts of the sub-base when the water trailer was a part of the equipment train. The court found that the only *76 change which came about after the stop order in plaintiff’s conduct of its mixing operations was the removal of the water trailer from the equipment train, which virtually eliminated the tearing of the sub-base by the tractor. The court found that defendant was aware that this remedial action was neces-. sary at the time the stop order was issued; that under the contract, defendant’s right to issue stop orders was dependent on the reasonable necessity therefor; and that since there was no reasonable necessity for the issuance of the stop order of May 31, 1951, plaintiff was entitled to compensation for his expenses incurred thereby.

Defendant attacks the determination made by the court that the contract between the parties contemplated a complete work of improvement and that defendant was liable to plaintiff for loss of profit by virtue of the deletions made in change order No. 8.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Vidal v. Pick Axe Holding CA4/1
California Court of Appeal, 2023
Alan Schumacher v. David Ray
617 F. App'x 773 (Ninth Circuit, 2015)
Menlo Logistics, Inc. v. Western Express, Inc.
269 F. App'x 715 (Ninth Circuit, 2008)
Howard Contracting, Inc. v. G.A. MacDonald Construction Co.
83 Cal. Rptr. 2d 590 (California Court of Appeal, 1999)
Brown v. Death Row Records, Inc. (In Re Brown)
219 B.R. 373 (E.D. Pennsylvania, 1998)
Nicholson v. United States
29 Fed. Cl. 180 (Federal Claims, 1993)
Sarl De La Motte v. Steven Hilgedick
956 F.2d 274 (Ninth Circuit, 1992)
K.L. Conwell Corp. v. City of Albuquerque
802 P.2d 634 (New Mexico Supreme Court, 1990)
State Ex Rel. Department of Transportation v. Guy F. Atkinson Co.
187 Cal. App. 3d 25 (California Court of Appeal, 1986)
Statler Manufacturing, Inc. v. Brown
691 S.W.2d 445 (Missouri Court of Appeals, 1985)
Juengel Const. Co., Inc. v. Mt. Etna, Inc.
622 S.W.2d 510 (Missouri Court of Appeals, 1981)
Barrett v. Ballard
622 P.2d 180 (Montana Supreme Court, 1980)
Matter of Daben Corp.
469 F. Supp. 135 (D. Puerto Rico, 1979)
Smith v. Zepp
567 P.2d 923 (Montana Supreme Court, 1977)
Ellison v. City of San Buenaventura
48 Cal. App. 3d 952 (California Court of Appeal, 1975)

Cite This Page — Counsel Stack

Bluebook (online)
268 P.2d 12, 124 Cal. App. 2d 71, 1954 Cal. App. LEXIS 1701, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hensler-v-city-of-los-angeles-calctapp-1954.