Monson v. Fischer

5 P.2d 628, 118 Cal. App. 503, 1931 Cal. App. LEXIS 193
CourtCalifornia Court of Appeal
DecidedNovember 24, 1931
DocketDocket No. 7457.
StatusPublished
Cited by23 cases

This text of 5 P.2d 628 (Monson v. Fischer) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Monson v. Fischer, 5 P.2d 628, 118 Cal. App. 503, 1931 Cal. App. LEXIS 193 (Cal. Ct. App. 1931).

Opinion

THE COURT.

Respondents, herein called the contractors, recovered judgment against appellant in the sum of $45,544.69 as damages for the alleged breach of a contract for the construction of a four-story concrete building. It was alleged that the contractors were prevented from com *507 pleting the structure, and the judgment included the value of its partial construction with interest thereon, and the estimated loss of profits. Reversal is sought on the ground that the judgment and findings are unsupported.

The contract price was $124,175. The structure was designed to carry two additional stories and had been leased in advance for factory purposes. The contract required the contractors to furnish the materials and perform the work in accordance with certain plans and specifications which were prepared by appellant’s architect. The contract consisted of two documents, one entitled “Articles of Agreement”, which was a printed form containing certain typewritten stipulations; the other, designated as the “Specifications”, was entirely typewritten, was annexed to the articles of agreement, and by reference made a part thereof.

The specifications with respect to the concrete, so far as the same are material, provided as follows: “The concrete for plain work shall be composed of one part of cement to three parts of sand and five parts of gravel and crushed rock, mixed. Re-inforced concrete shall be composed of one part cement to six parts of sand and crushed rock or gravel, except for all interior and/or free standing columns, where the mix will be a one to four and one-half (1:4½) as noted on the structural plans. . . . The ultimate strength of 1 to 6 concrete shall not be less than 2,000 lbs per square inch, and the 1 to 4% concrete not less than 2500 lbs per square inch. The owner reserves the right to have samples taken. ...”

The articles of agreement provided that the work should be done and the materials furnished under the direction and supervision of the architect or the superintendent selected by the owner; that the same should be paid for in monthly installments of seventy-five per cent of the value of the completed work done during the previous month as estimated by the architect; that when each installment became due a certificate should be obtained from the architect stating the same to be due and the amount thereof; that progress payments by the owner should not be construed as an absolute acceptance of the work done up to the time of such payments except as to such matters as were open and obvious, but that the architect or superintendent should exercise reasonable diligence to discover and report to the contractors unsatisfactory materials and workmanship so as to avoid un *508 necessary trouble and cost to the contractors in making good the defects; otherwise any objection thereto should be deemed waived; and that if the owner should fail to make within seven days of its maturity and presentment any payment provided in the contract, then after three days’ notice the contractors might terminate the contract and recover for any work done, any loss on plant, material or workmanship and the reasonable anticipated profit on the uncompleted portion of the work.

The specifications further stipulated that “the architect or his representative, as agent of the owner, shall have general supervision and direction of the work. He has authority to stop work whenever necessary to ensure proper execution of the contract, and is authorized and empowered to reject or refuse all labor and materials, or methods of application, or any part thereof, that do not comply in kind, quality and quantity with the drawings and specifications.

“To prevent all disputes and litigation the architect shall in all cases determine the amount and the quality of the several kinds of work which are to be paid for under this contract, and he shall determine all questions in relation to said work and the construction thereof, and he shall in all eases decide every question which may arise relative to the execution of this contract on the part of the contractor, and his estimate and decision shall be final and conclusive”; also that “any and all work or material that does not conform to the plans and specifications shall be immediately removed from the premises or made good by the contractor when directed to do so by the architect . . . ”; and that “neither the final certificate nor payment shall relieve the contractor from responsibility for omissions and faulty materials or workmanship, and he shall remedy any defects therein or make good any omissions, and pay for any damage to the other work resulting therefrom which shall appear within a period of one year from the completion and. acceptance of the work”.

Certain of the printed portions of the articles of agreement were as follows: “Should dispute arise as to the true meaning of the plans and specifications, or respecting the manner or sufficiency of the performance of any work thereunder . . . the questions in dispute shall in the first instance be decided by the architect; but should either owner or eon- *509 tractor be dissatisfied with his decision the question shall, on written demand of either delivered to the other at his last-known residence or place of business, be submitted for decision to a board of arbitration, consisting of three disinterested men experienced in the business of building, one to be named in the demand of the party making the demand, one by the other party within five days thereafter, the third by these two, these arbitrators to have plenary power, and the decision of any two of them to be conclusive and binding upon both parties to this agreement. N'o dispute shall interfere with the progress of the general construction, but necessary work shall proceed under the direction of the architect, and the decision of the arbitrators shall award adequate compensation therefor as due.” Further, that “ . . . No portions of the specifications that are in conflict with this agreement, or that are not actually descriptive of the work to be done hereunder or the manner in which it is to be done, are to be considered as part hereof, but such portions, if any, are null and void.”

Excavations preliminary to the erection of the building were completed before the execution of the contract on November 7, 1927. The pouring of the concrete commenced on that date, and work on the structure continued until December 2, 1927.

As stated, appellant had leased the structure. By the lease the tenant assumed responsibility for its maintenance during the term, and agreed that its occupancy should b& deemed an admission that it was sound and constructed in compliance with the above plans and specifications, which were made a part of the lease. Because of this provision the tenant consulted the engineering firm of Smith, Emery & Co. regarding the best method of securing information as to the materials and workmanship used in the construction of the building, and persons employed by Smith, Emery & Co. were present on each day that the mixing and pouring of concrete continued and took samples thereof.

The work progressed to a point where the footings and basement columns upon which the building was to rest were poured. These footings consisted of solid rectangular masses of concrete approximately eight feet square and three feet in height.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State v. Mau
Washington Supreme Court, 2013
MURRAY'S IRON WORKS, INC. v. Boyce
71 Cal. Rptr. 3d 317 (California Court of Appeal, 2008)
Buckingham v. Wray
366 N.W.2d 753 (Nebraska Supreme Court, 1985)
State Dept. of Rev. v. Wilson
Montana Supreme Court, 1981
State Dept. of Rev. v. Fatz
Montana Supreme Court, 1981
Koval v. Peoples
431 A.2d 1284 (Superior Court of Delaware, 1981)
Nordin Construction Company v. City of Nome
489 P.2d 455 (Alaska Supreme Court, 1971)
Glenn R. Sewell Sheet Metal, Inc. v. Loverde
451 P.2d 721 (California Supreme Court, 1969)
Denice v. Spotswood I. Quinby, Inc.
237 A.2d 4 (Court of Appeals of Maryland, 1968)
Integrated, Inc. v. Alec Fergusson Electrical Contractor
250 Cal. App. 2d 287 (California Court of Appeal, 1967)
Gollaher v. Midwood Construction Co.
194 Cal. App. 2d 640 (California Court of Appeal, 1961)
Boomer v. Abbett
315 P.2d 924 (California Court of Appeal, 1957)
Hensler v. City of Los Angeles
268 P.2d 12 (California Court of Appeal, 1954)
Gilmore v. Hoffman
266 P.2d 833 (California Court of Appeal, 1954)
Heple v. Kluge
250 P.2d 694 (California Court of Appeal, 1952)
Tucker v. Beazley
57 A.2d 191 (District of Columbia Court of Appeals, 1948)
Smoll v. Webb
130 P.2d 773 (California Court of Appeal, 1942)
Wenzel & Henoch Const. Co. v. Metropolitan Water Dist.
18 F. Supp. 616 (S.D. California, 1937)

Cite This Page — Counsel Stack

Bluebook (online)
5 P.2d 628, 118 Cal. App. 503, 1931 Cal. App. LEXIS 193, Counsel Stack Legal Research, https://law.counselstack.com/opinion/monson-v-fischer-calctapp-1931.