Opinion

LENNON, P. J.

In this action the defendant, A. J. Garibaldi, appeals from the judgment rendered against him and from the order denying his motion for a new trial.

The judgment is based upon the making and acceptance of the following written order, viz.:

“San Francisco, Cal., Jany. 19, 1907. “Mr. A, J. Garibaldi, San Francisco, Cal.
“Dear Sir:
“Please pay to Mr. A. J. O’Brien on completion when house accepted the sum of $900, and deduct same from my payment, and oblige, Tours respectfully,
“J. M. JACKSON.”

As an evidence of his acceptance of this order the defendant signed his name thereon below the signature of Jackson. The *520 record further discloses that at the time of the- presentation and acceptance of the order Jaekson, a contractor and builder, was engaged in the erection of a building on certain real property owned by the defendant, in the city and county of San Francisco, pursuant to the covenants of a building contract, in the usual and ordinary form, .executed by Jackson and defendant on the twelfth day of October, 1906.

The contract price of the building was $7,600, payable as the construction of the building progressed, in four equal installments. Prior to the nineteenth day of January, 1907, the date of the order in question, Jackson, the contractor, had so far progressed with his work, in accordance with the terms of his contract, as to be entitled to and he was paid the first two installments, amounting to the sum of $3,800.

On the second day of March, 1907, Jackson ceased work on the building and abandoned his contract, leaving due and unpaid to various persons for labor performed upon and materials used in the construction of the building the sum of $5,927.73. Thereupon the defendant, having fully complied with the requirements of the contract in such a contingency, personally assumed the further construction of the building, and under his immediate control and supervision the building was completed prior to the commencement of this action.

The last two payments which, under the terms of the contract, would have been due and payable to Jackson had he continued. under his contract and completed the building, amounted to the sum of $3,800. The sum of $410.43 was expended by the defendant Garibaldi in completing the building. This sum, deducted from the amount of the last two payments, which would have been due to Jackson upon a compliance with the contract, left a balance of $3,389.57 in Garibaldi’s hands to be applied in satisfaction of the several liens for labor and materials which, within the time allowed by law, had been filed against the building, and subsequently sued upon. This balance was distributed pro rata among the various lien claimants. O’Brien, the plaintiff, as a subcontractor under Jackson to do the plastering upon the building, was one of the lien claimants. He was paid as his pro rata the sum of $514.63, and after deducting this amount from the $900 specified in the order referred to, commenced this *521 action and obtained judgment against the defendant in the sum of $385.36.

It is conceded that the plaintiff was fully aware of the contractual relations existing, at the date of the order, between Garibaldi and Jackson; that in satisfying and discharging the liens of the several claimants the defendant Garibaldi expended all moneys due or which would have become due to Jackson upon his compliance with the terms of the building contract, and finally, that no part of the moneys due to the several lien claimants was ever paid by Jackson.

The trial court found as a fact “that on the said nineteenth day of January, 1907, the said A. J. Garibaldi duly accepted the said order, and promised and agreed to pay this plaintiff said sum of $900 when the said house was accepted.”

This is a material finding. It is the basis of the judgment in this case. This finding, however, is not wholly supported by the evidence, and it is clearly contrary to the evidence in so far as it finds that appellant’s obligation, under the order, was to pay “the said. $900 when the said house was accepted.”

The order in .question and its acceptance constitute a contract in writing and, upon its face, is not susceptible of any such narrow and limited construction. Some evidence was offered and received at the trial for the single purpose of showing the circumstances under which the order was made and accepted, but the record does not disclose that the appellant accepted the order in any other way than by writing his name thereon, or that the parties thereto in any way altered, varied or limited its terms and conditions. This being so, the order, in conjunction with the subsisting contract for the erection of the building, contains and expresses all the promises and agreements of the parties, and, therefore, for the purpose of ascertaining what the parties promised and agreed to do, resort must be had solely to the language of the order and the circumstances attending its inception and acceptance.

In the original contract it was in substance provided that Jackson was to “erect and finish” the building, and to furnish all labor and material required in the “construction and completion” thereof; the contract was to be deemed ‘ ‘ completed” when the work was “finished in accordance with the original plans”; the third installment of the contract price *522 was to become due and payable when the building was “finished” by Jackson and “accepted” by Garibaldi, and the final payment was due at the expiration of the “usual thirty-five days” after the completion and acceptance of the building.

Manifestly the “completion,” “acceptance” and “payment” referred to in the order of January 19, 1907, related to the completion, acceptance and payment provided for in the original contract.

It is clear, therefore, that in basing its finding as to the promise and agreement of Garibaldi to pay upon the single condition of the acceptance of the building the trial court ignored the remaining and equally controlling conditions of ,the order with reference to the completion of the building by Jackson, and the existence of a fund from which the amount specified was to be deducted and paid.

Construed in connection with the original contract to which it was related, the order is free from any uncertainty as to its scope and effect. So construed it is clearly conditional, and the manner and form of its acceptance imposed upon the defendant Garibaldi no other or greater obligation than to pay to plaintiff whatever money might be due to Jackson upon the happening of all of the conditions of the order.

The order was in effect an assignment to the plaintiff of the sum of $900 out of any moneys due or.to become due to Jackson under the terms of the building contract; and the defendant’s acceptance of the order was but a promise to pay upon the happening of the contingencies expressed therein.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Monson v. Fischer
5 P.2d 628 (California Court of Appeal, 1931)
Ward v. Commissioner
22 B.T.A. 352 (Board of Tax Appeals, 1931)
Tomlin v. Neale
245 P. 800 (California Court of Appeal, 1926)
Tatsuno v. Pedersen
132 P. 608 (California Court of Appeal, 1913)

Cite This Page — Counsel Stack

Bluebook (online)
115 P. 249, 15 Cal. App. 518, 1911 Cal. App. LEXIS 322, Counsel Stack Legal Research, https://law.counselstack.com/opinion/obrien-v-garibaldi-calctapp-1911.